Home |
Search |
Today's Posts |
![]() |
|
UK diy (uk.d-i-y) For the discussion of all topics related to diy (do-it-yourself) in the UK. All levels of experience and proficency are welcome to join in to ask questions or offer solutions. |
Reply |
|
LinkBack | Thread Tools | Display Modes |
|
#1
![]() |
|||
|
|||
![]() In the process of having a conservatory built, the builders digging out the base have identified that the rainwater pipe to the soakaway ends in an area that is going to be concreted over. This will then (apparently, I'm none too familiar with this stuff) result in a new soakaway having to be dug further down the garden, and the pipework rerouted into it around the conservatory. My question is is this something that the surveyor should have anticipated when the project was specified, or are they likely to want to charge me extra for it (they've said nothing yet but its only been discovered this morning, so I'm trying to get some info for when they do, as I expect, try to charge me extra) . The contract doesn't seem to make any specific mention either way of reserving the right to charge me extra for unforeseen problems in the building element of the job Thanks for any feedback Brian |
#2
![]() |
|||
|
|||
![]()
"bigbrian" wrote
| My question is is this something that the surveyor should have | anticipated when the project was specified, He should have anticipated that it is *possible* that there *may* be a soakaway. | The contract doesn't seem to make any specific mention either way | of reserving the right to charge me extra for unforeseen problems | in the building element of the job Depends on whether the contract says, and the price was for, "erect a conservatory" or "do all works necessary to erect a conservatory". Owain |
#3
![]() |
|||
|
|||
![]()
On Wed, 8 Sep 2004 18:58:55 +0100, "Owain"
wrote: "bigbrian" wrote | My question is is this something that the surveyor should have | anticipated when the project was specified, He should have anticipated that it is *possible* that there *may* be a soakaway. | The contract doesn't seem to make any specific mention either way | of reserving the right to charge me extra for unforeseen problems | in the building element of the job Depends on whether the contract says, and the price was for, "erect a conservatory" or "do all works necessary to erect a conservatory". Naturally, it says neither Brian |
#4
![]() |
|||
|
|||
![]()
On Wed, 08 Sep 2004 23:25:06 +0100,
wrote: On Wed, 8 Sep 2004 18:58:55 +0100, "Owain" wrote: "bigbrian" wrote | My question is is this something that the surveyor should have | anticipated when the project was specified, He should have anticipated that it is *possible* that there *may* be a soakaway. | The contract doesn't seem to make any specific mention either way | of reserving the right to charge me extra for unforeseen problems | in the building element of the job Depends on whether the contract says, and the price was for, "erect a conservatory" or "do all works necessary to erect a conservatory". Naturally, it says neither Brian I would take the moral high ground and treat it as a fait accompli - in other words and assumptive approach that of course they are going to do it. If they haven't allowed for it then it's their issue. I had a similar situation. There was an inspection chamber in a position that would have been right under the conservatory floor - in fact about a metre inside one door. I was not prepared to have a manhole cover in my slate floor so the supplier was asked to account for moving it to a position outside. Unfortunately they screwed up and made a wrong assumption about the direction of slope of the drains. This meant that the chamber needed to be moved to a point some 7m from its original position and in the other direction. This meant a great deal more digging which probably took them half a day plus some extra soil pipe. Needless to say, they tried to wriggle out of it and increase the cost. It was suggested that they might enjoy sex and travel, and they saw my point. It all worked in my favour because it positioned the drains better for my kitchen remodelling. One general point is to keep as much money back at all times until *all* the work is complete. As part of the negotiation, I did not agree to more than 25% of the total being given before completion of the base, a further 25% on delivery of the frame and glass, 20% on completing erection and the remainder when all snagging was complete. Make sure that you use something covered by the Consumer Credit Act. EIther a credit agreement which you pay off quickly, or a credit card. The if something goes tits up you are better protected. ..andy To email, substitute .nospam with .gl |
#5
![]() |
|||
|
|||
![]()
On Thu, 09 Sep 2004 00:46:56 +0100, Andy Hall
wrote: On Wed, 08 Sep 2004 23:25:06 +0100, wrote: On Wed, 8 Sep 2004 18:58:55 +0100, "Owain" wrote: "bigbrian" wrote | My question is is this something that the surveyor should have | anticipated when the project was specified, He should have anticipated that it is *possible* that there *may* be a soakaway. | The contract doesn't seem to make any specific mention either way | of reserving the right to charge me extra for unforeseen problems | in the building element of the job Depends on whether the contract says, and the price was for, "erect a conservatory" or "do all works necessary to erect a conservatory". Naturally, it says neither Brian I would take the moral high ground and treat it as a fait accompli - in other words and assumptive approach that of course they are going to do it. If they haven't allowed for it then it's their issue. I had a similar situation. There was an inspection chamber in a position that would have been right under the conservatory floor - in fact about a metre inside one door. I was not prepared to have a manhole cover in my slate floor so the supplier was asked to account for moving it to a position outside. Unfortunately they screwed up and made a wrong assumption about the direction of slope of the drains. This meant that the chamber needed to be moved to a point some 7m from its original position and in the other direction. This meant a great deal more digging which probably took them half a day plus some extra soil pipe. Needless to say, they tried to wriggle out of it and increase the cost. It was suggested that they might enjoy sex and travel, and they saw my point. It all worked in my favour because it positioned the drains better for my kitchen remodelling. One general point is to keep as much money back at all times until *all* the work is complete. As part of the negotiation, I did not agree to more than 25% of the total being given before completion of the base, a further 25% on delivery of the frame and glass, 20% on completing erection and the remainder when all snagging was complete. Make sure that you use something covered by the Consumer Credit Act. EIther a credit agreement which you pay off quickly, or a credit card. The if something goes tits up you are better protected. To date I've only paid 10% (by credit card), with 20% more payable on completion of the building work and the remaining 70% payable on completion of the whole project, so I have enough leverage (unless they decide to pull out altogether). To date, they haven't even indicated that they'll want to charge me at all, but the builder seems to suggest that the conservatory company will pursue me for what he's going to charge them for digging a new soakaway. Not trying to rip anyone off.......I don't mind paying if its normal practice that these things are excluded....just trying to find out what the conventional wisdom (if there is any) is Brian |
#6
![]() |
|||
|
|||
![]()
the builder seems to suggest that the conservatory company will pursue
me for what he's going to charge them for digging a new soakaway. IANAL I`d be tempted to argue that the quote should have included all necessary works, and that their failure to allow for all contingencies is not your problem. -- Please add "[newsgroup]" in the subject of any personal replies via email --- My new email address has "ngspamtrap" & @btinternet.com in it ;-) --- |
#7
![]() |
|||
|
|||
![]()
On Thu, 09 Sep 2004 01:11:02 +0100,
wrote: To date I've only paid 10% (by credit card), with 20% more payable on completion of the building work and the remaining 70% payable on completion of the whole project, so I have enough leverage (unless they decide to pull out altogether). To date, they haven't even indicated that they'll want to charge me at all, but the builder seems to suggest that the conservatory company will pursue me for what he's going to charge them for digging a new soakaway. OK. This is a fairly typical arrangement. Actually the numbers give a pretty good clue. The 20-30% is what they will need to pay the builder producing the base, with 70% being the frame, glass and the conservatory company's margin. What I would do is to keep a note of the total time that the builder takes to make the base, and also for how much time (ask him "as a matter of interest") it will take to do the soakaway stuff. I took photos at the end of each working day so that I had a record of the stage reached. Not trying to rip anyone off.......I don't mind paying if its normal practice that these things are excluded....just trying to find out what the conventional wisdom (if there is any) is Armed with the above information, you can calculate roughly what should be involved. Let's say that the total project is £10k and that we therefore assume that the builder is getting paid £3k for the base. Let's also say that he would normally take 3 days (he's probably on a fixed price from the conservatory supplier so time is critical). If he takes half a day longer to do the drain, then this is costing the builder £500. As an opening gambit, I would therefore push the conservatory supplier to take the £500 out of margin. If not, then I would argue that £500 is a reasonable figure. I wouldn't accept them marking it up in proportion to the project - i.e. to an implied £1000-1500. This is an example, but you can see the scaling..... Brian ..andy To email, substitute .nospam with .gl |
#8
![]() |
|||
|
|||
![]()
On Wed, 8 Sep 2004 18:58:55 +0100, "Owain"
wrote: "bigbrian" wrote | My question is is this something that the surveyor should have | anticipated when the project was specified, He should have anticipated that it is *possible* that there *may* be a soakaway. | The contract doesn't seem to make any specific mention either way | of reserving the right to charge me extra for unforeseen problems | in the building element of the job Depends on whether the contract says, and the price was for, "erect a conservatory" or "do all works necessary to erect a conservatory". Owain Further update: Still no word from the company on who's paying for the new soakaway, but the old one was concreted in this afternoon. If it rains before the new one is dug, the rain water is going to collect at the end of the existing pipe against the concrete. Is this going to cause a problem at all? Brian |
#9
![]() |
|||
|
|||
![]()
On Wed, 8 Sep 2004 18:58:55 +0100, "Owain"
wrote: "bigbrian" wrote | My question is is this something that the surveyor should have | anticipated when the project was specified, He should have anticipated that it is *possible* that there *may* be a soakaway. | The contract doesn't seem to make any specific mention either way | of reserving the right to charge me extra for unforeseen problems | in the building element of the job Depends on whether the contract says, and the price was for, "erect a conservatory" or "do all works necessary to erect a conservatory". Next question: anybody got any idea about a likely additional cost for a new soakaway? Brian |
#10
![]() |
|||
|
|||
![]()
wrote in message . ..
In the process of having a conservatory built, the builders digging out the base have identified that the rainwater pipe to the soakaway ends in an area that is going to be concreted over. This will then (apparently, I'm none too familiar with this stuff) result in a new soakaway having to be dug further down the garden, and the pipework rerouted into it around the conservatory. My question is is this something that the surveyor should have anticipated when the project was specified, or are they likely to want to charge me extra for it (they've said nothing yet but its only been discovered this morning, so I'm trying to get some info for when they do, as I expect, try to charge me extra) . The contract doesn't seem to make any specific mention either way of reserving the right to charge me extra for unforeseen problems in the building element of the job Thanks for any feedback Brian This would normally be an unforeseen item. The company would expect to tap into some near by drains, and not have to make a completely new soakaway and drain run. Unless they are prepared to cover the cost, it would be unreasonable for you not to pay for this extra work. dg |
#11
![]() |
|||
|
|||
![]() |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Conservatory base | UK diy | |||
House airbricks and conservatory base | UK diy | |||
Conservatory cost vs payment schedule | UK diy | |||
Conservatory Cowboy supplier | UK diy | |||
Neighbours new conservatory nightmare... | UK diy |