I had the riggers come in and rearrange all the machine tools in the
lab: two manual lathes, 2 Bridgeports, Haas toolroom mill and lathe,
Haas VF-0, a Haas turning center, and an Injection molder. Everything
got moved once, one of the Bridgeports got moved 4 times as we tried to
get the clearances just right.

I was blown away with how easy the riggers made it look, as well as the
total simplicity of the tools used: the foreman had a shop made steel
Johnson bar. Standard 26 pound railroad bar with a 2" stub welded on the
end and 2 super duty roller skate wheels on the sides. Each of the 2
grunts had a dolly made from a 2"x2" x1/4" angle with another super duty
roller skate wheel on the side. That's all they needed to move
everything except the big Haas lathe! (Haas lathe case was too bulky to
allow access underneath)

To move a Bridgeport, the foreman would hook the base at the back, lift
it up an inch or so. Grunts would slide the angle iron blocks in along
the sides, near the back. Foreman would set the load on the side
rollers, go around and get a 1" lift off the front. A bit of a push and
off it went. When I wanted the Bridgeport moved over 9" and a bit more
angle, it took no move than 3 minutes with not the least bit of grunting
and groaning.

The Haas VF-0 had to go down a long hallway and through several
doorways. Same Johnson Bar and roller skates.

Did I say I was impressed?
  #2   Report Post  
Posted to rec.crafts.metalworking
external usenet poster
 
Posts: 6,746
Default Moving machinery


RoyJ wrote:

I had the riggers come in and rearrange all the machine tools in the
lab: two manual lathes, 2 Bridgeports, Haas toolroom mill and lathe,
Haas VF-0, a Haas turning center, and an Injection molder. Everything
got moved once, one of the Bridgeports got moved 4 times as we tried to
get the clearances just right.

I was blown away with how easy the riggers made it look, as well as the
total simplicity of the tools used: the foreman had a shop made steel
Johnson bar. Standard 26 pound railroad bar with a 2" stub welded on the
end and 2 super duty roller skate wheels on the sides. Each of the 2
grunts had a dolly made from a 2"x2" x1/4" angle with another super duty
roller skate wheel on the side. That's all they needed to move
everything except the big Haas lathe! (Haas lathe case was too bulky to
allow access underneath)

To move a Bridgeport, the foreman would hook the base at the back, lift
it up an inch or so. Grunts would slide the angle iron blocks in along
the sides, near the back. Foreman would set the load on the side
rollers, go around and get a 1" lift off the front. A bit of a push and
off it went. When I wanted the Bridgeport moved over 9" and a bit more
angle, it took no move than 3 minutes with not the least bit of grunting
and groaning.

The Haas VF-0 had to go down a long hallway and through several
doorways. Same Johnson Bar and roller skates.

Did I say I was impressed?


Since most of us HSM guys are short on grunts, we have to use somewhat
more complicated moving techniques.
  #3   Report Post  
Posted to rec.crafts.metalworking
external usenet poster
 
Posts: 762
Default Moving machinery

You're right. You absolutely do not want to have helpers that do not
follow instructions EXACTLY when moving heavy objects. The grunts didn't
do any heavy work, the foreman was wiry guy who didn't weigh that much.

Pete C. wrote:
RoyJ wrote:
I had the riggers come in and rearrange all the machine tools in the
lab: two manual lathes, 2 Bridgeports, Haas toolroom mill and lathe,
Haas VF-0, a Haas turning center, and an Injection molder. Everything
got moved once, one of the Bridgeports got moved 4 times as we tried to
get the clearances just right.

I was blown away with how easy the riggers made it look, as well as the
total simplicity of the tools used: the foreman had a shop made steel
Johnson bar. Standard 26 pound railroad bar with a 2" stub welded on the
end and 2 super duty roller skate wheels on the sides. Each of the 2
grunts had a dolly made from a 2"x2" x1/4" angle with another super duty
roller skate wheel on the side. That's all they needed to move
everything except the big Haas lathe! (Haas lathe case was too bulky to
allow access underneath)

To move a Bridgeport, the foreman would hook the base at the back, lift
it up an inch or so. Grunts would slide the angle iron blocks in along
the sides, near the back. Foreman would set the load on the side
rollers, go around and get a 1" lift off the front. A bit of a push and
off it went. When I wanted the Bridgeport moved over 9" and a bit more
angle, it took no move than 3 minutes with not the least bit of grunting
and groaning.

The Haas VF-0 had to go down a long hallway and through several
doorways. Same Johnson Bar and roller skates.

Did I say I was impressed?


Since most of us HSM guys are short on grunts, we have to use somewhat
more complicated moving techniques.

  #4   Report Post  
Posted to rec.crafts.metalworking
external usenet poster
 
Posts: 6,746
Default Moving machinery


RoyJ wrote:

You're right. You absolutely do not want to have helpers that do not
follow instructions EXACTLY when moving heavy objects. The grunts didn't
do any heavy work, the foreman was wiry guy who didn't weigh that much.


The greatest danger with untrained grunts is that they won't know when
to just get out of the way and watch something fall.
  #5   Report Post  
Posted to rec.crafts.metalworking
external usenet poster
 
Posts: 652
Default Moving machinery

"Pete C." wrote in message
ster.com...

RoyJ wrote:

You're right. You absolutely do not want to have helpers that do not
follow instructions EXACTLY when moving heavy objects. The grunts didn't
do any heavy work, the foreman was wiry guy who didn't weigh that much.


The greatest danger with untrained grunts is that they won't know when
to just get out of the way and watch something fall.


Or to keep their hands off and wait for instructions when the see somebody
struggling with an awkward manuever.




  #6   Report Post  
Posted to rec.crafts.metalworking
external usenet poster
 
Posts: 856
Default Moving machinery

RoyJ wrote:
I had the riggers come in and rearrange all the machine tools in the
lab: two manual lathes, 2 Bridgeports, Haas toolroom mill and lathe,
Haas VF-0, a Haas turning center, and an Injection molder. Everything
got moved once, one of the Bridgeports got moved 4 times as we tried
to get the clearances just right.

I was blown away with how easy the riggers made it look, as well as
the total simplicity of the tools used: the foreman had a shop made
steel Johnson bar. Standard 26 pound railroad bar with a 2" stub
welded on the end and 2 super duty roller skate wheels on the sides.
Each of the 2 grunts had a dolly made from a 2"x2" x1/4" angle with
another super duty roller skate wheel on the side. That's all they
needed to move everything except the big Haas lathe! (Haas lathe case
was too bulky to allow access underneath)

To move a Bridgeport, the foreman would hook the base at the back,
lift it up an inch or so. Grunts would slide the angle iron blocks in
along the sides, near the back. Foreman would set the load on the side
rollers, go around and get a 1" lift off the front. A bit of a push
and off it went. When I wanted the Bridgeport moved over 9" and a bit
more angle, it took no move than 3 minutes with not the least bit of
grunting and groaning.

The Haas VF-0 had to go down a long hallway and through several
doorways. Same Johnson Bar and roller skates.

Did I say I was impressed?

I can see the points made by others about making sure you're out of the
danger zone like each side of a BP or front to back on a lathe move. I
found moving a BP and lathes easy on level concrete using a pry bar and
some 1" round bars. The nice thing about the BP was the notch in the
front and rear skirt and the level skirt in between. The notches made
using the pry bar easy and the level skirt allowed the bars to run the
full length and then being replaced at the other end. Some BP copies I
have seen only had the corners on the ground and were relieved in
between which would make using bars more difficult. My Kerry 11x40 has a
level base so is easy to move on bars, the Harrison M300 was more time
consuming as it has a box under the headstock and another under the
tailstock, more work to move but still fairy easy.
Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Roller ball positioning plates for moving machinery? AL Metalworking 13 September 22nd 05 04:17 PM
Machinery-moving mattock (pry bar) -- new project page Richard J Kinch Metalworking 8 February 11th 05 09:30 PM
The IDEAL Machinery Moving Trailer? dhost Metalworking 0 February 11th 04 11:02 PM
links to pix of machinery moving skates I made Grant Erwin Metalworking 0 January 26th 04 03:38 AM
The IDEAL Machinery Moving Trailer? Too_Many_Tools Metalworking 56 January 12th 04 06:01 PM


All times are GMT +1. The time now is 11:26 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"