Woodworking (rec.woodworking) Discussion forum covering all aspects of working with wood. All levels of expertise are encouraged to particiapte.

Reply
 
LinkBack Thread Tools Search this Thread Display Modes
  #1   Report Post  
Andrew Barss
 
Posts: n/a
Default National Electrical Code question



I'm in a dispute with an electrician, who wired my house with an
underground feed. After signing a contract in which he promised to do all
work, and supply all parts, to refeed the existing house from a new
building, he imposed an additional charge of $350 for an "underground pull
box", which is basically a 15" x 24" cement rectangle with a plastic lid.
The pull box had to be installed, according to the city, because there
were too many 45- and 90-degree turns in the wire run to do it in one
single pull.

Does anyone know whether this is mandated by the NEC? It would make
resolution of the dispute easier if so.


thanks,

Andy Barss

  #2   Report Post  
Bob Gramza
 
Posts: n/a
Default National Electrical Code question


"Andrew Barss" wrote in message
...
:
:
: I'm in a dispute with an electrician, who wired my house with an
: underground feed. After signing a contract in which he promised to do all
: work, and supply all parts, to refeed the existing house from a new
: building, he imposed an additional charge of $350 for an "underground pull
: box", which is basically a 15" x 24" cement rectangle with a plastic lid.
: The pull box had to be installed, according to the city, because there
: were too many 45- and 90-degree turns in the wire run to do it in one
: single pull.
:
: Does anyone know whether this is mandated by the NEC? It would make
: resolution of the dispute easier if so.
:
:
: thanks,
:
: Andy Barss
:
A city can require additional requirements in addition to the NEC. If your city says it is required
thats pretty much it. They will not approve it if it is not up to their specs. I do not have a copy
of the NEC but there are pull box requirements based on the number of turns in a pipe.


  #3   Report Post  
 
Posts: n/a
Default National Electrical Code question

On Tue, 1 Jul 2003 19:14:58 +0000 (UTC), Andrew Barss wrote:



I'm in a dispute with an electrician, who wired my house with an
underground feed. After signing a contract in which he promised to do all
work, and supply all parts, to refeed the existing house from a new
building, he imposed an additional charge of $350 for an "underground pull
box", which is basically a 15" x 24" cement rectangle with a plastic lid.
The pull box had to be installed, according to the city, because there
were too many 45- and 90-degree turns in the wire run to do it in one
single pull.

Does anyone know whether this is mandated by the NEC? It would make
resolution of the dispute easier if so.


thanks,

Andy Barss



Regardless, didn't you say it's required by the City? I believe the
city can have a stricter code as long as it satisfies the NEC as well.
Best to talk to a Professional Electrical Engineer to verify this.


** remove .invalid from my email address to reply by email **





  #4   Report Post  
Jeff Cochran
 
Posts: n/a
Default National Electrical Code question

On Tue, 1 Jul 2003 19:14:58 +0000 (UTC), Andrew Barss
wrote:

I'm in a dispute with an electrician, who wired my house with an
underground feed. After signing a contract in which he promised to do all
work, and supply all parts, to refeed the existing house from a new
building, he imposed an additional charge of $350 for an "underground pull
box", which is basically a 15" x 24" cement rectangle with a plastic lid.
The pull box had to be installed, according to the city, because there
were too many 45- and 90-degree turns in the wire run to do it in one
single pull.

Does anyone know whether this is mandated by the NEC? It would make
resolution of the dispute easier if so.


Check the code directly for the number of turns between pull boxes, it
is specified. But if the city requires it, even if NEC doesn't,
that's the rule you have to meet.

Jeff
  #5   Report Post  
TURTLE
 
Posts: n/a
Default National Electrical Code question


"Andrew Barss" wrote in message
...


I'm in a dispute with an electrician, who wired my house with an
underground feed. After signing a contract in which he promised to do all
work, and supply all parts, to refeed the existing house from a new
building, he imposed an additional charge of $350 for an "underground pull
box", which is basically a 15" x 24" cement rectangle with a plastic lid.
The pull box had to be installed, according to the city, because there
were too many 45- and 90-degree turns in the wire run to do it in one
single pull.

Does anyone know whether this is mandated by the NEC? It would make
resolution of the dispute easier if so.


thanks,

Andy Barss


This is Turtle.

If you have a contract that states that he will furnish all parts and labor
to bring service from the other building to your building. Then the City
inspector comes along and says it must have a turn box. if he has signed the
contract and then this box came up. you can go two routes here.

1) be a Ass Hole and hold his feet to the fire and tell him finish the job
as the contract says and you will furnish all parts. Pay as the contract
states. He is stuck with putting in the turn box for no extra cost. Hold his
feet to the fire.

2) Be a nice guy and talk to him about helping pay for the turn box in the
form of he furnish labor and you furnish added material to install turn box.

3) Be a push over and Mr Good Guy and pay him the $350.00 added cost for
the turn box.

If he signed the contract as stated. You have a fishing hook in his mouth
tied to your rod and reel. He's hooked if you want to be Mr. bad guy. I
might pay him to keep trouble down but if he got bad mouth with me. I will
reel him in and dress and fry him up.

TURTLE




Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Yale Electric Chain Hoist Question MP Toolman Metalworking 3 July 13th 04 08:24 AM
another electrical question alan UK diy 8 September 29th 03 12:11 AM
New Electrical Regs PoP UK diy 22 September 1st 03 08:41 PM
Forthcoming Building Regulations on electrical work (Part P) Andrew McKay UK diy 42 July 30th 03 08:05 AM


All times are GMT +1. The time now is 07:10 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"