Home |
Search |
Today's Posts |
![]() |
|
UK diy (uk.d-i-y) For the discussion of all topics related to diy (do-it-yourself) in the UK. All levels of experience and proficency are welcome to join in to ask questions or offer solutions. |
Reply |
|
LinkBack | Thread Tools | Display Modes |
|
#1
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
Unbelievable an *on topic* thread:-)
Is there a time limit between laying oversite concrete and fitting the insulation, dpc and screed? Concrete drying time must be similar to screed and there are lots of warnings about that. Does it matter if the insulation foil is in contact with moist concrete? -- Tim Lamb |
#2
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
Logic would suggest that if you have a DPM below the concrete then the only way out for the moisture is through the top surface. I believe curing time for concrete is 28 days.
I have not consulted this site in a while but checking it out may definitively answer your question; http://pavingexpert.com/ Richard |
#3
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
On 29/09/2019 10:23, Tricky Dicky wrote:
Logic would suggest that if you have a DPM below the concrete then the only way out for the moisture is through the top surface. I believe curing time for concrete is 28 days. I have not consulted this site in a while but checking it out may definitively answer your question; http://pavingexpert.com/ Is the OP talking about 'drying' or 'curing'? If it dries out too quickly it won't be able to cure properly; on the other hand nearly all concrete is made with more than enough water to make it workable, and the excess water will need to dry out eventually, depending on where it is. With ordinary cement 28 days is the 'official' curing time, i.e. nearly all strength is achieved by then. -- Max Demian |
#4
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
In message , Max
Demian writes On 29/09/2019 10:23, Tricky Dicky wrote: Logic would suggest that if you have a DPM below the concrete then the only way out for the moisture is through the top surface. I believe curing time for concrete is 28 days. I have not consulted this site in a while but checking it out may definitively answer your question; http://pavingexpert.com/ Is the OP talking about 'drying' or 'curing'? If it dries out too quickly it won't be able to cure properly; on the other hand nearly all concrete is made with more than enough water to make it workable, and the excess water will need to dry out eventually, depending on where it is. With ordinary cement 28 days is the 'official' curing time, i.e. nearly all strength is achieved by then. It is a *sequencing* issue. I am constructing a corridor linking an extension to a now cut off garage. Planning and Building Control kindly allowed the garage to be used domestically subject to the usual insulation requirements. For future proofing, the link also needs to meet the regs. hence underfloor insulation. It would be convenient to finish the floor before the structure is weatherproof and before serious frosts arrive. -- Tim Lamb |
#5
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
On 29/09/2019 10:23, Tricky Dicky wrote:
Logic would suggest that if you have a DPM below the concrete then the only way out for the moisture is through the top surface. I believe curing time for concrete is 28 days. I have not consulted this site in a while but checking it out may definitively answer your question; http://pavingexpert.com/ Richard I always thought proper drying time was a month per inch of concrete, i.e. longer than you expect. You can put a secondary dpc on top of the slab. |
#6
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
On 29/09/2019 13:17, Andrew wrote:
On 29/09/2019 10:23, Tricky Dicky wrote: Logic would suggest that if you have a DPM below the concrete then the only way out for the moisture is through the top surface. I believe curing time for concrete is 28 days. I have not consulted this site in a while but checking it out may definitively answer your question; http://pavingexpert.com/ Richard I always thought proper drying time was a month per inch of concrete, i.e. longer than you expect. You can put a secondary dpc on top of the slab. where then would the moisture go? (I thought that was why DPM above the slab was an /alternative/ to DPM below it.) -- Robin reply-to address is (intended to be) valid |
#7
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
On 29/09/2019 14:07, Robin wrote:
On 29/09/2019 13:17, Andrew wrote: On 29/09/2019 10:23, Tricky Dicky wrote: Logic would suggest that if you have a DPM below the concrete then the only way out for the moisture is through the top surface. I believe curing time for concrete is 28 days. I have not consulted this site in a while but checking it out may definitively answer your question; http://pavingexpert.com/ Richard I always thought proper drying time was a month per inch of concrete, i.e. longer than you expect. You can put a secondary dpc on top of the slab. where then would the moisture go? Doesnt need to go anywhere. Concrete sort of meeds CO2 to set tho, so its not great hermetically sealed (I thought that was why DPM above the slab was an /alternative/ to DPM below it.) -- it should be clear by now to everyone that activist environmentalism (or environmental activism) is becoming a general ideology about humans, about their freedom, about the relationship between the individual and the state, and about the manipulation of people under the guise of a 'noble' idea. It is not an honest pursuit of 'sustainable development,' a matter of elementary environmental protection, or a search for rational mechanisms designed to achieve a healthy environment. Yet things do occur that make you shake your head and remind yourself that you live neither in Joseph Stalins Communist era, nor in the Orwellian utopia of 1984. Vaclav Klaus |
#8
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
In message , The Natural Philosopher
writes On 29/09/2019 14:07, Robin wrote: On 29/09/2019 13:17, Andrew wrote: On 29/09/2019 10:23, Tricky Dicky wrote: Logic would suggest that if you have a DPM below the concrete then the only way out for the moisture is through the top surface. I believe curing time for concrete is 28 days. I have not consulted this site in a while but checking it out may definitively answer your question; http://pavingexpert.com/ Richard I always thought proper drying time was a month per inch of concrete, i.e. longer than you expect. You can put a secondary dpc on top of the slab. where then would the moisture go? Doesnt need to go anywhere. Concrete sort of meeds CO2 to set tho, so its not great hermetically sealed (I thought that was why DPM above the slab was an /alternative/ to DPM below it.) Umm. I thought CO2 absorbtion by concrete was an issue for steel reinforcement rather than a necessary part of the cure. I put plastic sheet below the concrete to save properly blinding the hardcore and will put dpm over the insulation. I can re-plan the work and tarpaulin over the roof to create a tent. -- Tim Lamb |
#9
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
On 29/09/2019 14:24, The Natural Philosopher wrote:
On 29/09/2019 14:07, Robin wrote: On 29/09/2019 13:17, Andrew wrote: On 29/09/2019 10:23, Tricky Dicky wrote: Logic would suggest that if you have a DPM below the concrete then the only way out for the moisture is through the top surface. I believe curing time for concrete is 28 days. I have not consulted this site in a while but checking it out may definitively answer your question; http://pavingexpert.com/ Richard I always thought proper drying time was a month per inch of concrete, i.e. longer than you expect. You can put a secondary dpc on top of the slab. where then would the moisture go? Doesnt need to go anywhere. Concrete sort of meeds CO2 to set tho, so its not great hermetically sealed No it doesn't. That's lime mortar. Portland cement sets if sealed or underwater. There's just the issue of whether the excess water in the mix could cause a problem. -- Max Demian |
#11
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
If done properly the oversite is stable, is topped with compacted
crushed stone or the like, and blinded with fines. So there's nothing to move which could "wear out" the DPM. From the little I see of ground work around here I can see why some prefer block and beam ![]() On 30/09/2019 09:00, Brian Gaff wrote: Would not a dpm just under the slab tend to wear out rather fast letting all those problems reoccur? Brian -- Robin reply-to address is (intended to be) valid |
#12
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
On Sunday, 29 September 2019 10:03:42 UTC+1, Tim Lamb wrote:
Unbelievable an *on topic* thread:-) Is there a time limit between laying oversite concrete and fitting the insulation, dpc and screed? Concrete drying time must be similar to screed and there are lots of warnings about that. Does it matter if the insulation foil is in contact with moist concrete? -- Tim Lamb Concrete doesn't set by "drying" (it will set underwater.) A non-linear chemical reaction takes place. You need to wet concrete down as is sets. Chemicals in wet concrete will attack aluminium foil (strongly alkaline). You can buy a plastic film to put down to separate the two. https://www.concreteconstruction.net...ect-concrete_o |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Cloth Drying Ceiling Hangers | Cloth Drying Racks | Cloth DryingStands | Pulley Ceiling hangers | Home Repair | |||
Condensation in conservatory wall : drying time ? | UK diy | |||
Drying time : condensation in conservatory wall | UK diy | |||
Drying time for concrete foundations ? | UK diy | |||
electronic cleaner drying time | Electronics Repair |