  #1   Report Post  
Leslie
 
Posts: n/a
Default Final Payment Huff

I need a reality check on something unpleasant that happened today
with a roofing contractor. Did I err or is he being a little hinky?

I've been renovating my 100+ year old Victorian (new siding, new
windows, etc.) There is a small mansard roof at the front of the
house, and the historic slate and underlying tin were a mess. I
located a slate specialist and also got my neighbor (whose house
adjoins mine) to agree to do his mansard at the same time. We got a
small break on the price from the roofer because it originally
appeared both could be done at once. The work was going to be
approximately $2,200 for each roof.

For about a month there was a hassle getting my GC and roofer to agree
on who was doing what first, but in the end the GC had to rebuild the
roof deck and reinforce the rotted vertical structural supports before
the copper gutter, downspout and slate could be applied. Because the
tear-out was so extensive and we didn't want to leave the roof open,
both roofs couldn't be done simultaneously as we had planned. I
offered to pay the roofer the difference but he waved it off and said
he wouldn't charge if it it didn't make a difference to his final
profitability on the work, etc.

After a few delays on his side(some weather-related and some not) the
roofer finally came out last Friday and Saturday and installed the
slate. The project is not quite done -- he needs some additional
contrasting slates for the decorative rosettes and has a small area
adjacent to my neighbor's roof which needs shingles -- but he included
a small holdback in the invoice for the last bit of work. Everything
looked great and as he was packing up on Saturday, I offered to write
him a check on the spot, which he declined because he wanted to double
check the invoice before he sent it. I also asked if he would like to
stop by next week to pick up the check. He declined that also.

The roofer FAXed the invoice a day or two later (Sunday or Monday) but
I was so swamped at work over the next few days that I didn't have
time to sit down and write out the check until this morning
(Saturday). The roofer had called once on my cell and sent one or two
E-mails but I couldn't even listen or read the messages through until
today. Even then, they weren't along the lines of "Hey, I haven't
received payment yet. When do you think you can send a check."

I sent the roofer an E-mail this morning letting him know that I'd
torn the house up but couldn't find the FAXed invoice and asked him to
please reFAX it or E-mail it. I got back an E-mail stating "please
send this out immediately. I operate based on volume and the process
I created requires all aspects to function fluidly...unfortunately
this has not happened this on this project. I don't feel that it is
any one person's fault. Regardless, my profit (and scheduling) was
based on the two projects together. We have already discussed this so
no need to reiterate. But, in my business money is constantly
moving, i.e. payroll, materials, and you need the flow to remain
constant." I immediately called him and asked him what on earth was
he upset about, and that's when he went off about the contract stating
he was supposed to be paid upon completion and that he'd been stiffed
before by some woman for a $27,000 roof, and that he had to make sure
he did things promptly so he could file a mechanic's lien, etc. I
told him I was sympathetic about cash flow as I used to be a
freelancer but was offended that he assumed I was going to stiff him.
Among other things, why would I have E-mailed him asking for another
copy of the invoice? And why would I have offered to write him a
check on the spot when he finished the work? And finally, he's still
holding a deposit for my neighbor. Like I'm going to cheat him even as
I'm working with the GC to get the prep done on my neighbor's house.
I told him to come on over and pick up the check if things were that
desperate but once again he declined. He was too busy.

This afternoon I took the $1,200 check to the post office and mailed
it, which is exactly what I was planning on doing anyway. But I'm
still upset. I've never cheated anybody in my life! Was I committing
a cardinal sin by putting the payment off a few days (5 days at most)
until I could get to it, or is something else going on here?

I do want this guy to finish the work because of the quality of work
he does, but how do I approach him to (1) come back to finish my
section; and (2) get him to start and finish my neighbor's roof. He
already told my GC that if the guys can get the neighbor's roof deck
rebuilt before March 27 he could come out on a Saturday and get the
work done. My neighbor does have a signed contract with him, so
should I let him communicate directly with the roofer? I hate to put
the onus on him as he is so far away.

Any insights and strategies would be appreciated! And if I was wrong
let me know. Thanks!
  #2   Report Post  
Gunner
 
Posts: n/a
Default Final Payment Huff


"Leslie" wrote in message
I offered to pay the roofer the difference but he waved it off and said
he wouldn't charge if it it didn't make a difference to his final
profitability on the work, etc.


This shows he is an honest person.


After a few delays on his side(some weather-related and some not) the
roofer finally came out last Friday and Saturday and installed the
slate. The project is not quite done -- he needs some additional
contrasting slates for the decorative rosettes and has a small area
adjacent to my neighbor's roof which needs shingles -- but he included
a small holdback in the invoice for the last bit of work. Everything
looked great and as he was packing up on Saturday, I offered to write
him a check on the spot, which he declined because he wanted to double
check the invoice before he sent it. I also asked if he would like to
stop by next week to pick up the check. He declined that also.


The holdback shows once again he is an honest person. Wanting to double
check his invoice is protecting _both_ parties, so there are no
misunderstandings.

Asking him to stop by to pickup a check is an honorable jesture on your
part. But, you have no idea where he might be working the following week.
Stoping by might be a huge inconvenience on his part. You may be an hour
each way for him to travel to and from, time =$$ .


The roofer FAXed the invoice a day or two later (Sunday or Monday) but
I was so swamped at work over the next few days that I didn't have
time to sit down and write out the check until this morning
(Saturday). The roofer had called once on my cell and sent one or two
E-mails but I couldn't even listen or read the messages through until
today. Even then, they weren't along the lines of "Hey, I haven't
received payment yet. When do you think you can send a check."


Let me get this straight. You claim to be so swamped you can't write out a
check and mail the guy a check for a week, but you want him to come running
over to your place? Be a little more considerate. What makes you think
your time is more valuable than his? You are the one being unreasonable.
Try that tactic anywhere else, you will be making payments with interest.


Among other things, why would I have E-mailed him asking for another
copy of the invoice? And why would I have offered to write him a
check on the spot when he finished the work? And finally, he's still
holding a deposit for my neighbor. Like I'm going to cheat him even as
I'm working with the GC to get the prep done on my neighbor's house.
I told him to come on over and pick up the check if things were that
desperate but once again he declined. He was too busy.


You should've taken care of business and you wouldn't be asking for another
invoice. This tactic is used by deadbeats which collection agencies are
well aware of.

His holding a neighbors deposit has nothing to do with your business. His
contract with neighbor is a seperate contract.

You making a remark that if he is so desparate to come pick up the check,
sounds like you're the uppity type. Just pay the guy his money, what is
your problem?

This afternoon I took the $1,200 check to the post office and mailed
it, which is exactly what I was planning on doing anyway. But I'm
still upset. I've never cheated anybody in my life! Was I committing
a cardinal sin by putting the payment off a few days (5 days at most)
until I could get to it, or is something else going on here?


Something else is going on here, you're a slow pay. You said yourself you
were too busy and finally got to it, but first came the excuse you lost the
fax. Take care of business and you won't have these problems.

I do want this guy to finish the work because of the quality of work
he does, but how do I approach him to (1) come back to finish my
section; and (2) get him to start and finish my neighbor's roof. He
already told my GC that if the guys can get the neighbor's roof deck
rebuilt before March 27 he could come out on a Saturday and get the
work done. My neighbor does have a signed contract with him, so
should I let him communicate directly with the roofer? I hate to put
the onus on him as he is so far away.


Yep, far away. And you want him to chase the $. Good contractors are hard
to find, consider yourself lucky if he shows back up.

  #3   Report Post  
SQLit
 
Posts: n/a
Default Final Payment Huff


"Leslie" wrote in message
om...


snipped

The roofer FAXed the invoice a day or two later (Sunday or Monday) but


Your fault, admit it and move on

I sent the roofer an E-mail this morning letting him know that I'd
torn the house up but couldn't find the FAXed invoice

snipped,

Your fault..... email, should have called the guy. Yea you offered to pay
the guy in the beginning he was honest and sent you a bill, EXPECTING
payment on recipt. You took 5 days to pay. Now he is nervous. I would
have pre leined your property. Of course I pre lein every job I do. Common
in Arizona.

This afternoon I took the $1,200 check to the post office and mailed
it, which is exactly what I was planning on doing anyway. But I'm
still upset. I've never cheated anybody in my life! Was I committing
a cardinal sin by putting the payment off a few days (5 days at most)
until I could get to it, or is something else going on here?

I do want this guy to finish the work because of the quality of work
he does,

again snipped

Yes you want to him to complete the job. Sugar cookies and the appropiate
drink might be in order. If he is good prove to him that you are. Not five
days, the day you get the bill. Devlivering the last payment to him and a
thank you would be in line.

A good contractor that works with ancient materials is hard to find. If your
pleased with the results show the man your pleased. Pay promptly. Five days
may not be much to you, it might be a life time to him... You offered to pay
on the spot. He refused showing respect and confidence. You broke the chain.
Email may be common in your world is it in his?





Any insights and strategies would be appreciated! And if I was wrong
let me know. Thanks!



  #4   Report Post  
Edwin Pawlowski
 
Posts: n/a
Default Final Payment Huff


"Leslie" wrote in message
om...
I need a reality check on something unpleasant that happened today
with a roofing contractor. Did I err or is he being a little hinky?


Could be as simple as he had a bad day or he didn't get any nookiel last
night. He is still probably hurting from the lady that stiffed him and it
just came to his mind. Or he just got a big repair bill for his truck.

You sent the check, he should have it soon and just move on with life. Don't
take it as a reflection of your reputation or his.
Ed


  #5   Report Post  
Tony Hwang
 
Posts: n/a
Default Final Payment Huff

SQLit wrote:
"Leslie" wrote in message
om...


snipped


The roofer FAXed the invoice a day or two later (Sunday or Monday) but



Your fault, admit it and move on


I sent the roofer an E-mail this morning letting him know that I'd
torn the house up but couldn't find the FAXed invoice


snipped,

Your fault..... email, should have called the guy. Yea you offered to pay
the guy in the beginning he was honest and sent you a bill, EXPECTING
payment on recipt. You took 5 days to pay. Now he is nervous. I would
have pre leined your property. Of course I pre lein every job I do. Common
in Arizona.


This afternoon I took the $1,200 check to the post office and mailed
it, which is exactly what I was planning on doing anyway. But I'm
still upset. I've never cheated anybody in my life! Was I committing
a cardinal sin by putting the payment off a few days (5 days at most)
until I could get to it, or is something else going on here?

I do want this guy to finish the work because of the quality of work
he does,


again snipped

Yes you want to him to complete the job. Sugar cookies and the appropiate
drink might be in order. If he is good prove to him that you are. Not five
days, the day you get the bill. Devlivering the last payment to him and a
thank you would be in line.

A good contractor that works with ancient materials is hard to find. If your
pleased with the results show the man your pleased. Pay promptly. Five days
may not be much to you, it might be a life time to him... You offered to pay
on the spot. He refused showing respect and confidence. You broke the chain.
Email may be common in your world is it in his?






Any insights and strategies would be appreciated! And if I was wrong
let me know. Thanks!




Hi,
Ever heard of lien hold back?
Did he show all the material is paid for, if he had helpers, they're
paid for? Otherwise Lien hold back can be one month here where I am.
Tony


  #6   Report Post  
RB
 
Posts: n/a
Default Final Payment Huff

I obtain lien releases signed by all who would have a claim at the time
I make payments, or I don't pay. The need for these lien releases is
know from the start. The standard AIA lien release form is adequate.

RB

Tony Hwang wrote:
SQLit wrote:

"Leslie" wrote in message
om...


snipped


The roofer FAXed the invoice a day or two later (Sunday or Monday) but




Your fault, admit it and move on


I sent the roofer an E-mail this morning letting him know that I'd
torn the house up but couldn't find the FAXed invoice



snipped,

Your fault..... email, should have called the guy. Yea you offered
to pay
the guy in the beginning he was honest and sent you a bill, EXPECTING
payment on recipt. You took 5 days to pay. Now he is nervous. I would
have pre leined your property. Of course I pre lein every job I do.
Common
in Arizona.


This afternoon I took the $1,200 check to the post office and mailed
it, which is exactly what I was planning on doing anyway. But I'm
still upset. I've never cheated anybody in my life! Was I committing
a cardinal sin by putting the payment off a few days (5 days at most)
until I could get to it, or is something else going on here?

I do want this guy to finish the work because of the quality of work
he does,



again snipped

Yes you want to him to complete the job. Sugar cookies and the appropiate
drink might be in order. If he is good prove to him that you are. Not
five
days, the day you get the bill. Devlivering the last payment to him and a
thank you would be in line.

A good contractor that works with ancient materials is hard to find.
If your
pleased with the results show the man your pleased. Pay promptly.
Five days
may not be much to you, it might be a life time to him... You offered
to pay
on the spot. He refused showing respect and confidence. You broke the
chain.
Email may be common in your world is it in his?






Any insights and strategies would be appreciated! And if I was wrong
let me know. Thanks!





Hi,
Ever heard of lien hold back?
Did he show all the material is paid for, if he had helpers, they're
paid for? Otherwise Lien hold back can be one month here where I am.
Tony


  #7   Report Post  
AJScott
 
Posts: n/a
Default Final Payment Huff

There's enough finger-pointing to go around on both sides, IMO. It's not
up to you to make sure a cntractor's billing and collection practices
are in order, and it's not up to a contractor to have to chase clients
for payment on work already done to the satisfaction of the client.

Solution simple: Immediately call the dude by phone or personally visit
his place of business and work it out. If someone's still hacked off
about something or another that results in further financial
disagreements beyond that point, well, that's why God invented small
claims court.

AJS


In article ,
(Leslie) wrote:

I need a reality check on something unpleasant that happened today
with a roofing contractor. Did I err or is he being a little hinky?

I've been renovating my 100+ year old Victorian (new siding, new
windows, etc.) There is a small mansard roof at the front of the
house, and the historic slate and underlying tin were a mess. I
located a slate specialist and also got my neighbor (whose house
adjoins mine) to agree to do his mansard at the same time. We got a
small break on the price from the roofer because it originally
appeared both could be done at once. The work was going to be
approximately $2,200 for each roof.

For about a month there was a hassle getting my GC and roofer to agree
on who was doing what first, but in the end the GC had to rebuild the
roof deck and reinforce the rotted vertical structural supports before
the copper gutter, downspout and slate could be applied. Because the
tear-out was so extensive and we didn't want to leave the roof open,
both roofs couldn't be done simultaneously as we had planned. I
offered to pay the roofer the difference but he waved it off and said
he wouldn't charge if it it didn't make a difference to his final
profitability on the work, etc.

After a few delays on his side(some weather-related and some not) the
roofer finally came out last Friday and Saturday and installed the
slate. The project is not quite done -- he needs some additional
contrasting slates for the decorative rosettes and has a small area
adjacent to my neighbor's roof which needs shingles -- but he included
a small holdback in the invoice for the last bit of work. Everything
looked great and as he was packing up on Saturday, I offered to write
him a check on the spot, which he declined because he wanted to double
check the invoice before he sent it. I also asked if he would like to
stop by next week to pick up the check. He declined that also.

The roofer FAXed the invoice a day or two later (Sunday or Monday) but
I was so swamped at work over the next few days that I didn't have
time to sit down and write out the check until this morning
(Saturday). The roofer had called once on my cell and sent one or two
E-mails but I couldn't even listen or read the messages through until
today. Even then, they weren't along the lines of "Hey, I haven't
received payment yet. When do you think you can send a check."

I sent the roofer an E-mail this morning letting him know that I'd
torn the house up but couldn't find the FAXed invoice and asked him to
please reFAX it or E-mail it. I got back an E-mail stating "please
send this out immediately. I operate based on volume and the process
I created requires all aspects to function fluidly...unfortunately
this has not happened this on this project. I don't feel that it is
any one person's fault. Regardless, my profit (and scheduling) was
based on the two projects together. We have already discussed this so
no need to reiterate. But, in my business money is constantly
moving, i.e. payroll, materials, and you need the flow to remain
constant." I immediately called him and asked him what on earth was
he upset about, and that's when he went off about the contract stating
he was supposed to be paid upon completion and that he'd been stiffed
before by some woman for a $27,000 roof, and that he had to make sure
he did things promptly so he could file a mechanic's lien, etc. I
told him I was sympathetic about cash flow as I used to be a
freelancer but was offended that he assumed I was going to stiff him.
Among other things, why would I have E-mailed him asking for another
copy of the invoice? And why would I have offered to write him a
check on the spot when he finished the work? And finally, he's still
holding a deposit for my neighbor. Like I'm going to cheat him even as
I'm working with the GC to get the prep done on my neighbor's house.
I told him to come on over and pick up the check if things were that
desperate but once again he declined. He was too busy.

This afternoon I took the $1,200 check to the post office and mailed
it, which is exactly what I was planning on doing anyway. But I'm
still upset. I've never cheated anybody in my life! Was I committing
a cardinal sin by putting the payment off a few days (5 days at most)
until I could get to it, or is something else going on here?

I do want this guy to finish the work because of the quality of work
he does, but how do I approach him to (1) come back to finish my
section; and (2) get him to start and finish my neighbor's roof. He
already told my GC that if the guys can get the neighbor's roof deck
rebuilt before March 27 he could come out on a Saturday and get the
work done. My neighbor does have a signed contract with him, so
should I let him communicate directly with the roofer? I hate to put
the onus on him as he is so far away.

Any insights and strategies would be appreciated! And if I was wrong
let me know. Thanks!

  #8   Report Post  
JWB
 
Posts: n/a
Default Final Payment Huff

"Leslie" wrote in message
om...

The roofer FAXed the invoice a day or two later (Sunday or Monday) but
I was so swamped at work over the next few days that I didn't have
time to sit down and write out the check until this morning
(Saturday).


Yes you did. It would have taken 5 minutes to write the check. You cannot
honestly say you didn't have 5 free minutes for an entire week.

I'm not saying you are totally at fault here, but look at his mindset and
expectations. He clearly expected you to pay upon receiving the invoice.
Putting it off almost a full week is not what he expected. *You* knew you
were going to eventually pay it - but he didn't know that, despite your
offer to pay right away. He faxed the invoice Sunday (let's say) - I'll bet
he was checking his mailbox Tuesday, then Wednesday - all the while, you
didn't even look at the invoice, nevermind mail the check he was expecting.

I honestly don't think he was accusing you of stiffing him - If I were you,
I'd call him and say you are sorry for any misunderstanding (not sorry for
your actions, as you thought waiting a week was ok, and that isn't
unreasonable), and in the future will be certain to pay immediately upon
receipt. That should make him happy, and he might even surprise you by
saying immediate payment isn't necessary (I'm a freelancer - I want
immediate payment from new clients, but older ones who I *know* will pay can
take as long as they wish, within reason)

JWB


  #9   Report Post  
Nehmo Sergheyev
 
Posts: n/a
Default Final Payment Huff

- SQLit -
Your fault, admit it and move on


- Nehmo -
I agree. Plus, in order for OP to convince the slate guy that they'll be
no money probs in the future, OP should just tip him $100. (The ones who
have done this to me sure stand out in my memory.) And he shouldn't use
snail to send checks, if you can't just hand over the check, you can
wire the money bank account to bank account. I personally hate waiting
for a check to arrive in the mail.

On the other side, slate guy shouldn't have gotten so crabby.

--
*********************
* Nehmo Sergheyev *
*********************



  #10   Report Post  
Tom Miller
 
Posts: n/a
Default Final Payment Huff

On Sun, 07 Mar 2004 04:15:10 GMT, "Edwin Pawlowski"
wrote:

|
| "Leslie" wrote in message
| om...
| I need a reality check on something unpleasant that happened today
| with a roofing contractor. Did I err or is he being a little hinky?
|
|
| Could be as simple as he had a bad day or he didn't get any nookiel last
| night. He is still probably hurting from the lady that stiffed him and it
| just came to his mind. Or he just got a big repair bill for his truck.
|
| You sent the check, he should have it soon and just move on with life. Don't
| take it as a reflection of your reputation or his.
| Ed
|


Ed's right on target. The guy was grumped off or worried about
something else. My guess is he was annoyed that you lost the invoice.
And if you were a man, I bet he'd have been a lot more diplomatic. In
any case, in the real world 5 days is not exactly what you would call
skipping out on the bill and $1500 is hardly a federal case. But a lot
of these guys are better at their craft than at business. When it gets
towards the end of the week, they get antsy. (Then there are the guys
who say, "No hurry" when what they really mean is "Pay me tomorrow
before 9:00 am or I'll kill you." Hard to figure).

You paid and a piddling five or maybe four days late? Give me a break,
this is nothing. I've had clients pay me a year late, and only when we
were standing in the doorway of the courtroom. It's part of business,
and us big boys learn to deal with it.

Forget it. Don't beat yourself up. You owe him nothing.

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Conservatory cost vs payment schedule bigbrian UK diy 11 June 13th 04 05:14 PM


All times are GMT +1. The time now is 05:45 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"