  #1   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 2,853
Default staged payments

What's the usual schedule on a sub-10k job?

The builder has just dropped a schedule on us, and I'm not happy with
it. It was not agreed in advance.

Andy
  #2   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 28
Default staged payments

On 26/11/2013 21:27, Vir Campestris wrote:
What's the usual schedule on a sub-10k job?

The builder has just dropped a schedule on us, and I'm not happy with
it. It was not agreed in advance.

Andy


You need to have some form of contract written done in place, with when
payments will be made. I done mine myself, and made sure I had never
paid more than the work done at the time was worth.

Payment when foundations poured.
Payment when Timber kit completed.
Payment when blockwork completed.
Payment when First fix completed.
Payment when roof tiled.
Payment when Windows Installed.

I never paid anything upfront. If the builder doesn't have the cashflow
to buy materials first, look elsewhere.

--
yendor
If it's not broken, let's fix it till it is.
  #3   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 11,175
Default staged payments

In article ,
yendor writes:
On 26/11/2013 21:27, Vir Campestris wrote:
What's the usual schedule on a sub-10k job?

The builder has just dropped a schedule on us, and I'm not happy with
it. It was not agreed in advance.

Andy


You need to have some form of contract written done in place, with when
payments will be made. I done mine myself, and made sure I had never
paid more than the work done at the time was worth.

Payment when foundations poured.
Payment when Timber kit completed.
Payment when blockwork completed.
Payment when First fix completed.
Payment when roof tiled.
Payment when Windows Installed.


For those items requiring BCO inspection (such as foundations),
it should be after approval, not after completion, and you
should hook a payment to each of these inspections.

My parents paid an architect to draw up the contract stating when
partial payments were due and to approve the partial payments for
other stages. It you're not using an architect, you could use a
building surveyor for this. But this was for something over 40k.

The last 10% was due 6 months after completion, to allow for
snagging fixes.

I never paid anything upfront. If the builder doesn't have the cashflow
to buy materials first, look elsewhere.


Builder should be able to buy on 30 days credit anyway, or they
don't have any credibility with their suppliers either.

Builder was perfectly happy with this, and probably used to it as
he was one of several the architect recommended.

--
Andrew Gabriel
[email address is not usable -- followup in the newsgroup]
  #4   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 2,024
Default staged payments

On Tue, 26 Nov 2013 21:27:55 +0000, Vir Campestris
wrote:

What's the usual schedule on a sub-10k job?


The builder has just dropped a schedule on us, and I'm not happy with
it. It was not agreed in advance.


If you don't have a written contract you need one quickly. The
standard one would be the Joint Contracts Tribunal "Building Contract
for a home owner/occupier who has not appointed a consultant to
oversee the work" You can find a copy at
http://www.sandwell.gov.uk/download/...wnerocc upier

The payment schedule is whatever you and the builder decide but should
be tied to measurable milestones such as foundations installed and
inspected. The builder should be familiar with the JCT contract.
Normally 5% of the contract value should be withheld at the end for a
period of three months to ensure any small defects discovered after
work is complete are remedied.
  #5   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 6,896
Default staged payments

The payment schedule is whatever you and the builder decide but should
be tied to measurable milestones such as foundations installed and
inspected. The builder should be familiar with the JCT contract.
Normally 5% of the contract value should be withheld at the end for a
period of three months to ensure any small defects discovered after
work is complete are remedied.


And do psych yourself up for the invariable disputes that will happen,
not known a project to go "just so" yet;!...

If you are unhappy with something raise the issue there and then, don't
wait for it to become a bigger one..
--
Tony Sayer




  #6   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 175
Default staged payments


"yendor" wrote in message
...
On 26/11/2013 21:27, Vir Campestris wrote:
What's the usual schedule on a sub-10k job?

The builder has just dropped a schedule on us, and I'm not happy with
it. It was not agreed in advance.

Andy


You need to have some form of contract written done in place, with when
payments will be made. I done mine myself, and made sure I had never paid
more than the work done at the time was worth.

Payment when foundations poured.
Payment when Timber kit completed.
Payment when blockwork completed.
Payment when First fix completed.
Payment when roof tiled.
Payment when Windows Installed.


six tranches for a 10K job sounds like three too many to me

tim


Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Question about disability payments Willard Lazybe Home Repair 55 September 26th 12 01:10 PM
TOT; Debit card payments The Medway Handyman UK diy 29 April 16th 08 10:04 PM
Where did my extra Principal payments go? [email protected] Home Ownership 6 July 21st 06 02:43 PM
Progress Payments Greg Oliva Home Repair 2 May 29th 06 05:59 PM
Lower your monthly payments hansf Home Ownership 0 October 16th 05 05:36 AM


All times are GMT +1. The time now is 02:21 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"