Default Replacement bathroom - fastest procedure?

I'm doing a total bathroom refurb next week - it started off as a bath
change, now the whole lot is being changed/decorated, including
tiles/laminate floor.
I'd like some views as to the best way of going about this, firstly to
get things done as soon as possible, and to cause as little disruption
to the customer.
My plan is:
Monday: Drain/freeze system, fit isolators to all pipes in the bathroom
(none fitted at all now).
Remove row of tiles above bath (possibly remove all if they come off
easily)
Remove old bath and refit new.
If all goes well, this should be easily achievable in 6 hours.

Tuesday. Remove sink and toilet, fit new laminate floor below where sink
and bog were, then refit new sink and bog.
Maybe a morning?
Any spare time, carry on fitting the rest of the flooring.

Wednesday. Finish off flooring, then start on tiling.

Thursday, finish tiling, get paid.

I've told the chap that it could take 5 days, which gives me some
leeway.

Any thoughts on what I've missed, or potential flaws in my plan?

Thanks
Alan.

--
To reply by e-mail, change the ' + ' to 'plus'.
  #2   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 8,319
Default Replacement bathroom - fastest procedure?

A.Lee wrote:
I'm doing a total bathroom refurb next week - it started off as a bath
change, now the whole lot is being changed/decorated, including
tiles/laminate floor.
I'd like some views as to the best way of going about this, firstly to
get things done as soon as possible, and to cause as little disruption
to the customer.
My plan is:
Monday: Drain/freeze system, fit isolators to all pipes in the
bathroom (none fitted at all now).
Remove row of tiles above bath (possibly remove all if they come off
easily)
Remove old bath and refit new.
If all goes well, this should be easily achievable in 6 hours.

Tuesday. Remove sink and toilet, fit new laminate floor below where
sink and bog were, then refit new sink and bog.
Maybe a morning?
Any spare time, carry on fitting the rest of the flooring.

Wednesday. Finish off flooring, then start on tiling.

Thursday, finish tiling, get paid.

I've told the chap that it could take 5 days, which gives me some
leeway.

Any thoughts on what I've missed, or potential flaws in my plan?


Seems about right to me Al. Tiling always takes me longer than I think
though - don't forget the grouting - that takes up some time.

I always use 22mm flexibles for fitting baths - you can get them 1:5m long.
Means you can do all the plumbing then slide the bath into places - saves a
lot of time & fiddle.

Good idea removing bog & sink prior to laminating - thats gonna save a lot
of time & aggro - do they have another bog they can use though?

You were wise to quote 5 days - finish early & you are a hero.

Let us know how it goes?


--
Dave - The Medway Handyman
www.medwayhandyman.co.uk
01634 717930
07850 597257


  #3   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 222
Default Replacement bathroom - fastest procedure?

On 14 Dec, 17:28, (A.Lee) wrote:
I'm doing a total bathroom refurb next week - it started off as a bath
change, now the whole lot is being changed/decorated, including
tiles/laminate floor.
I'd like some views as to the best way of going about this, firstly to
get things done as soon as possible, and to cause as little disruption
to the customer.
My plan is:
Monday: Drain/freeze system, fit isolators to all pipes in the bathroom
(none fitted at all now).
Remove row of tiles above bath (possibly remove all if they come off
easily)
Remove old bath and refit new.
If all goes well, this should be easily achievable in 6 hours.

Tuesday. Remove sink and toilet, fit new laminate floor below where sink
and bog were, then refit new sink and bog.
Maybe a morning?
Any spare time, carry on fitting the rest of the flooring.

Wednesday. Finish off flooring, then start on tiling.

Thursday, finish tiling, get paid.

I've told the chap that it could take 5 days, which gives me some
leeway.

Any thoughts on what I've missed, or potential flaws in my plan?

Thanks
Alan.

--
To reply by e-mail, change the ' + ' to 'plus'.




Best to allow 3 days for repairing the chips and scratches where the
old tiles fell into the new bath.
  #4   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 104
Default Replacement bathroom - fastest procedure?

On Fri, 14 Dec 2007 14:44:57 -0800 (PST), Mr Fuxit
wrote:

On 14 Dec, 17:28, (A.Lee) wrote:
I'm doing a total bathroom refurb next week - it started off as a bath
change, now the whole lot is being changed/decorated, including
tiles/laminate floor.
I'd like some views as to the best way of going about this, firstly to
get things done as soon as possible, and to cause as little disruption
to the customer.
My plan is:
Monday: Drain/freeze system, fit isolators to all pipes in the bathroom
(none fitted at all now).
Remove row of tiles above bath (possibly remove all if they come off
easily)
Remove old bath and refit new.
If all goes well, this should be easily achievable in 6 hours.

Tuesday. Remove sink and toilet, fit new laminate floor below where sink
and bog were, then refit new sink and bog.
Maybe a morning?
Any spare time, carry on fitting the rest of the flooring.

Wednesday. Finish off flooring, then start on tiling.

Thursday, finish tiling, get paid.

I've told the chap that it could take 5 days, which gives me some
leeway.

Any thoughts on what I've missed, or potential flaws in my plan?

Thanks
Alan.

--
To reply by e-mail, change the ' + ' to 'plus'.




Best to allow 3 days for repairing the chips and scratches where the
old tiles fell into the new bath.


Yeah.I'd be inclined to get rid of ALL the old tiles first and have
the walls prepped for tiling new THEN put in the new bath ,leaving
the shrink wrap on and cover it well with several thicknesses of
whatever . If you remove the old tiles with the new bath in ,with
the best will in the world something is bound to happen to damage it
when doing this ( It is Sod's Law) ,like a large chunk of old sharp
tile,or a hammer or chisel getting dropped .
  #5   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 483
Default Replacement bathroom - fastest procedure?


"A.Lee" wrote in message
...
I'm doing a total bathroom refurb next week - it started off as a bath
change, now the whole lot is being changed/decorated, including
tiles/laminate floor.
I'd like some views as to the best way of going about this, firstly to
get things done as soon as possible, and to cause as little disruption
to the customer.
My plan is:
Monday: Drain/freeze system, fit isolators to all pipes in the bathroom
(none fitted at all now).
Remove row of tiles above bath (possibly remove all if they come off
easily)
Remove old bath and refit new.
If all goes well, this should be easily achievable in 6 hours.

Tuesday. Remove sink and toilet, fit new laminate floor below where sink
and bog were, then refit new sink and bog.
Maybe a morning?
Any spare time, carry on fitting the rest of the flooring.

Wednesday. Finish off flooring, then start on tiling.

Thursday, finish tiling, get paid.

I've told the chap that it could take 5 days, which gives me some
leeway.

Any thoughts on what I've missed, or potential flaws in my plan?


Let us know how you get on (time wise). Depending on the tiling area to do
I think you may have under estimated. If it were me I would remove ALL the
tiles before fitting the bath. What if after fitting the bath a large chunk
of wall/plaster comes off with the higher row of tiles? Good Luck!!

HTH

John





  #6   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 1,307
Default Replacement bathroom - fastest procedure?

Mr Fuxit wrote:


Monday: Drain/freeze system, fit isolators to all pipes in the bathroom
(none fitted at all now).
Remove row of tiles above bath (possibly remove all if they come off
easily)


Best to allow 3 days for repairing the chips and scratches where the
old tiles fell into the new bath.


No, it wont happen - that has been planned for before when I've done
tiling in bathrooms - I've got a sheet of mdf for sitting on top of the
bath - makes life so much easier with no chance fo damaging the bath,
and a 6' x 2' ready made workbench.
Alan.
--
To reply by e-mail, change the ' + ' to 'plus'.
  #7   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 36
Default Replacement bathroom - fastest procedure?

A.Lee wrote:
I'm doing a total bathroom refurb next week - it started off as a bath
change, now the whole lot is being changed/decorated, including
tiles/laminate floor.
I'd like some views as to the best way of going about this, firstly to
get things done as soon as possible, and to cause as little disruption
to the customer.
My plan is:
Monday: Drain/freeze system, fit isolators to all pipes in the bathroom
(none fitted at all now).
Remove row of tiles above bath (possibly remove all if they come off
easily)
Remove old bath and refit new.
If all goes well, this should be easily achievable in 6 hours.

Tuesday. Remove sink and toilet, fit new laminate floor below where sink
and bog were, then refit new sink and bog.
Maybe a morning?
Any spare time, carry on fitting the rest of the flooring.

Wednesday. Finish off flooring, then start on tiling.

Thursday, finish tiling, get paid.

I've told the chap that it could take 5 days, which gives me some
leeway.

Any thoughts on what I've missed, or potential flaws in my plan?

Thanks
Alan.

SWMBO wants the same, exactly as your scenario, started out with her
wanting a bath change and ended up with moving the sink and covering the
floor with tiles and underfloor heating.
Not starting till the new year so will be very interested as to how you
get on, I do have another toilet downstairs so the bog is no problem but
having a good wash could be a problem, long time since I could fit in
the kitchen sink.
Keep us informed of your progress.

Bazza
  #8   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 1,307
Default Replacement bathroom - fastest procedure?

The Medway Handyman wrote:
A.Lee wrote:
I'm doing a total bathroom refurb next week - ...
My plan is:
Monday: Drain/freeze system, fit isolators to all pipes in the
bathroom (none fitted at all now).
Remove row of tiles above bath (possibly remove all if they come off
easily)
Remove old bath and refit new.
Tuesday. Remove sink and toilet, fit new laminate floor below where
sink and bog were, then refit new sink and bog.
Maybe a morning?
Wednesday. Finish off flooring, then start on tiling.
Thursday, finish tiling, get paid.


Seems about right to me Al. Tiling always takes me longer than I think
though - don't forget the grouting - that takes up some time.


Well, things didnt go quite as planned.
Got there at 8am Monday, and was told it wasnt laminate floor now, but
tiles. That buggered up the plan to lay floor then put the bog own 10
minutes later.
Monday went OK, removing old tiles, and fitting the new bath. Had a
little trouble getting a good seal on the waste, and had to re-pipe the
existing waste, as it was such a bad design. Took ~8 hours.

Tuesdays plan was to fit the new bog and sink.Had to stop off at the
wood shop to get a sheet of ply for putting on the T+G floor to allow
laying of tiles.Lost a hour there. Removed bog, and cut the wood and
fitted that, then cut tiles to size that fit around the soil outlet.
Before tiling began, it was time to make sure the new pan fitted the
soli pipe ok. Oh dear. 1st major problem here - the sol pipe was too far
forward to allow the fitting of the new close coupled WC.
Ok, off to the plumbers merchant (Plumb Centre, which I hadnt used
before, but was nearest), who didnt seem to have much of a clue, and
said my only choice was a flexible soil pipe. So I bought that at £15.

It fitted, in a kind of way, but looked awful.It was now 2pm, and
customer would be home at 4pm, and didnt have a toilet or sink at this
time. Rushed back, laid the tiles around the soil/pan area. It'd be an
hour or so before the pan can go down, so time to build up the new
cistern and sink fittings.
Put the siphon in, and realised there was no large nut to hold it in
place. OK, I've got a new one in the van, so go and get that.The only
trouble was, this one I was fitting was a centre button, with a large
outlet, the one in the van was a std fitting. Damn. Off again to the
cluless Plumb Centre, who dont keep centre button siphons in stock, but
will sell me a complete cistern. Err, no thanks. Off to my normal
Plumbers, who had a spare nut, and gave it me FOC.
Back in, it was 3:45pm now, so running out of time swiftly. Go to fit
nut, and realise that the clamp plate was also missing. ****e. OK, I've
got a new one in the van, get that. Not realising that the hole would be
too small for this siphon. Double ****e.
Ok, just leave the pan, and tell them to flush it with a bucket of
water. He was quite sympathetic as I explained that the bits were not
supplied, and now too late to go and fetch some.
It was now 4:30pm.
OK, I'll get the sink fitted, then bugger off - it shouldnt be too bad,
as all pipes and waste had been prepared ready. Then, as documented
earlier this week, the basin and pedestal fit was so bad that I thought
they must be wrong. Things were getting worse.
Made my excuses and left, feeling shattered and disappointed/embarrassed
that I'd left them without a flushing bog, and no sink.

Wednesday. First call at 9am at the Plumbers. He seemed to think the
sink/pedestal wasnt too bad. He gave me some putty, "use that to fill
the gaps". He knew it was a crap fit, but didnt have any similar in
stock. I also got a much better 'proper' toilet waste pipe from them as
well as the missing toilet pieces.
The rest of the day went fairly well, toilet and sink went on, a few
more floor tiles were laid under the sink, then I heard a constant
dribbling. The toilet siphon was leaking into the pan. Ok, maybe a bit
of muck on the seal, will clear overnight, so leave it as is until
tomorrow.Got a few wall tiles on.

Thursday. Most of the plumbing done now, so just tiling the floor and
walls. Customers comes in, "oh, I've changed my mind now, we will be
having a new shower after all - oh, and the spare tiles, we may as well
do the whole wall around the window". So another days work just like
that.
I'd been told all the stuff for the tiling was sorted, I'd even told him
to get a good quality bath/tile edging strip.
So I get the adhesive out, and was just about to start, when I realised
I hadnt seen the edging strips. Give him a ring - "oh, I forgot to get
them". Off to the tilers to get 2 strips and some other odds and sods.
Another hour lost.
The rest of the day went reasonably well, albeit slowly.

Friday.Screwfix at 7:30am to buy some white grout. Tiling to do, and fit
a new toilet siphon. Siphon went on fine with no leaks this time - I
inspected the old one and couldnt see any fault with it at all, strange.
Finish floor tiles,Customer there, OK, I'll get the floor grouted before
I go.
"What, with white grout?"
'Yes'
"No, I want grey grout"
Me to self, groaning inside, this is the first time grey grout has been
mentioned.
'Ok, it cant be done today, but I'll be here Monday to finish off.'

I know it all cannot be done today.
Fit bath panel, then put up some more wall tiles.
Cutting and measuring is very time consuming, and it felt like I was
getting nowhere.
Remove old shower, after having to fit 2 new isolators, as the gate
valve isolators they currently had (in the loft) were dribbling when
fully turned off. More time wasted.
3:30pm now, and I'm getting frustrated, so spend the next half hour
cleaning up, and bugger off home at 4pm.

Work left to be done:
There's only around 30 (large) tiles to be put up, and all grouted, as
well as fitting the shower (which shouldnt take too long), but I think
there is easily another days work there.
I'll be making up a box section for hiding the pipes over the weekend.
I'll be back there on Monday to do a bit more, and hopefully finish
what I had originally intended to do. the tiles around the window can
wait for another day.

If it had been the original plan, I think it would have been finished
today, but the tiled floor chucked a large spanner in the works, and the
other problems I come across definitley put me back a day.
Still, it's all experience.
2 pics, before, and as left today.
See the lovely colour of the old, and the numerous cleaning bottles
liberally spread around the room - you can see less than half of what is
in there.
http://www.maydavid.co.uk/old.jpg
http://www.maydavid.co.uk/nearlydone.jpg

Alan.
--
To reply by e-mail, change the ' + ' to 'plus'.
  #9   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 1,368
Default Replacement bathroom - fastest procedure?

A.Lee wrote:
The Medway Handyman wrote:
A.Lee wrote:
I'm doing a total bathroom refurb next week - ...
My plan is:
Monday: Drain/freeze system, fit isolators to all pipes in the
bathroom (none fitted at all now).
Remove row of tiles above bath (possibly remove all if they come off
easily)
Remove old bath and refit new.
Tuesday. Remove sink and toilet, fit new laminate floor below where
sink and bog were, then refit new sink and bog.
Maybe a morning?
Wednesday. Finish off flooring, then start on tiling.
Thursday, finish tiling, get paid.


Seems about right to me Al. Tiling always takes me longer than I
think though - don't forget the grouting - that takes up some time.


Well, things didnt go quite as planned.
Got there at 8am Monday, and was told it wasnt laminate floor now, but
tiles. That buggered up the plan to lay floor then put the bog own 10
minutes later.
Monday went OK, removing old tiles, and fitting the new bath. Had a
little trouble getting a good seal on the waste, and had to re-pipe
the existing waste, as it was such a bad design. Took ~8 hours.

Tuesdays plan was to fit the new bog and sink.Had to stop off at the
wood shop to get a sheet of ply for putting on the T+G floor to allow
laying of tiles.Lost a hour there. Removed bog, and cut the wood and
fitted that, then cut tiles to size that fit around the soil outlet.
Before tiling began, it was time to make sure the new pan fitted the
soli pipe ok. Oh dear. 1st major problem here - the sol pipe was too
far forward to allow the fitting of the new close coupled WC.
Ok, off to the plumbers merchant (Plumb Centre, which I hadnt used
before, but was nearest), who didnt seem to have much of a clue, and
said my only choice was a flexible soil pipe. So I bought that at £15.

It fitted, in a kind of way, but looked awful.It was now 2pm, and
customer would be home at 4pm, and didnt have a toilet or sink at this
time. Rushed back, laid the tiles around the soil/pan area. It'd be an
hour or so before the pan can go down, so time to build up the new
cistern and sink fittings.
Put the siphon in, and realised there was no large nut to hold it in
place. OK, I've got a new one in the van, so go and get that.The only
trouble was, this one I was fitting was a centre button, with a large
outlet, the one in the van was a std fitting. Damn. Off again to the
cluless Plumb Centre, who dont keep centre button siphons in stock,
but will sell me a complete cistern. Err, no thanks. Off to my normal
Plumbers, who had a spare nut, and gave it me FOC.
Back in, it was 3:45pm now, so running out of time swiftly. Go to fit
nut, and realise that the clamp plate was also missing. ****e. OK,
I've got a new one in the van, get that. Not realising that the hole
would be too small for this siphon. Double ****e.
Ok, just leave the pan, and tell them to flush it with a bucket of
water. He was quite sympathetic as I explained that the bits were not
supplied, and now too late to go and fetch some.
It was now 4:30pm.
OK, I'll get the sink fitted, then bugger off - it shouldnt be too
bad, as all pipes and waste had been prepared ready. Then, as
documented earlier this week, the basin and pedestal fit was so bad
that I thought they must be wrong. Things were getting worse.
Made my excuses and left, feeling shattered and
disappointed/embarrassed that I'd left them without a flushing bog,
and no sink.

Wednesday. First call at 9am at the Plumbers. He seemed to think the
sink/pedestal wasnt too bad. He gave me some putty, "use that to fill
the gaps". He knew it was a crap fit, but didnt have any similar in
stock. I also got a much better 'proper' toilet waste pipe from them
as well as the missing toilet pieces.
The rest of the day went fairly well, toilet and sink went on, a few
more floor tiles were laid under the sink, then I heard a constant
dribbling. The toilet siphon was leaking into the pan. Ok, maybe a bit
of muck on the seal, will clear overnight, so leave it as is until
tomorrow.Got a few wall tiles on.

Thursday. Most of the plumbing done now, so just tiling the floor and
walls. Customers comes in, "oh, I've changed my mind now, we will be
having a new shower after all - oh, and the spare tiles, we may as
well do the whole wall around the window". So another days work just
like that.
I'd been told all the stuff for the tiling was sorted, I'd even told
him to get a good quality bath/tile edging strip.
So I get the adhesive out, and was just about to start, when I
realised I hadnt seen the edging strips. Give him a ring - "oh, I
forgot to get them". Off to the tilers to get 2 strips and some other
odds and sods. Another hour lost.
The rest of the day went reasonably well, albeit slowly.

Friday.Screwfix at 7:30am to buy some white grout. Tiling to do, and
fit a new toilet siphon. Siphon went on fine with no leaks this time
- I inspected the old one and couldnt see any fault with it at all,
strange. Finish floor tiles,Customer there, OK, I'll get the floor
grouted before I go.
"What, with white grout?"
'Yes'
"No, I want grey grout"
Me to self, groaning inside, this is the first time grey grout has
been mentioned.
'Ok, it cant be done today, but I'll be here Monday to finish off.'

I know it all cannot be done today.
Fit bath panel, then put up some more wall tiles.
Cutting and measuring is very time consuming, and it felt like I was
getting nowhere.
Remove old shower, after having to fit 2 new isolators, as the gate
valve isolators they currently had (in the loft) were dribbling when
fully turned off. More time wasted.
3:30pm now, and I'm getting frustrated, so spend the next half hour
cleaning up, and bugger off home at 4pm.

Work left to be done:
There's only around 30 (large) tiles to be put up, and all grouted, as
well as fitting the shower (which shouldnt take too long), but I think
there is easily another days work there.
I'll be making up a box section for hiding the pipes over the weekend.
I'll be back there on Monday to do a bit more, and hopefully finish
what I had originally intended to do. the tiles around the window can
wait for another day.

If it had been the original plan, I think it would have been finished
today, but the tiled floor chucked a large spanner in the works, and
the other problems I come across definitley put me back a day.
Still, it's all experience.
2 pics, before, and as left today.
See the lovely colour of the old, and the numerous cleaning bottles
liberally spread around the room - you can see less than half of what
is in there.
http://www.maydavid.co.uk/old.jpg
http://www.maydavid.co.uk/nearlydone.jpg



Apart from the bath panel and the paint on pipework, I saw no problem.

Readers of the Mirror, Sun, Mail?

Distorted fingers could be apparent from damaging the remote whlst
avoiding adverts to gawp at more Household Refurbs.?

Long live Darwin.

  #10   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 8,319
Default Replacement bathroom - fastest procedure?

A.Lee wrote:

Well, things didnt go quite as planned.
Got there at 8am Monday, and was told it wasnt laminate floor now, but
tiles. That buggered up the plan to lay floor then put the bog own 10
minutes later.


Often happens, punters change their minds part way through a job. I alway
make it clear that I can change things but it will affect the price.

He was quite sympathetic as I explained that the bits were not
supplied, and now too late to go and fetch some.


Depends on who supplied the kit. I'm never sure what is best; (1) let the
customer get the suite, helps the cash flow & you can blame them if bits are
missing or (2) get the suite myself & know its all there. I'm starting to
favour option (1) to be honest.

Made my excuses and left, feeling shattered and
disappointed/embarrassed that I'd left them without a flushing bog,
and no sink.


I know that feeling well Alan. But its not your fault - its thiers. They
completely changed the job spec. They should be feeling bad, not you.


Thursday. Most of the plumbing done now, so just tiling the floor and
walls. Customers comes in, "oh, I've changed my mind now, we will be
having a new shower after all - oh, and the spare tiles, we may as
well do the whole wall around the window". So another days work just
like that.


Which I hope you are charging for. Second time the customer has chamged the
job spec.

I'd been told all the stuff for the tiling was sorted, I'd even told
him to get a good quality bath/tile edging strip.
So I get the adhesive out, and was just about to start, when I
realised I hadnt seen the edging strips. Give him a ring - "oh, I
forgot to get them". Off to the tilers to get 2 strips and some other
odds and sods. Another hour lost.


Third screw up by the customer. He has to pay for it.

The rest of the day went reasonably well, albeit slowly.

Finish floor tiles,Customer there, OK, I'll get the floor
grouted before I go.
"What, with white grout?"
'Yes'
"No, I want grey grout"
Me to self, groaning inside, this is the first time grey grout has
been mentioned.


Forth change of plan/screw up by customer.


If it had been the original plan, I think it would have been finished
today, but the tiled floor chucked a large spanner in the works, and
the other problems I come across definitley put me back a day.
Still, it's all experience.


But it shouldn't cost you money mate. The customer has changed the job at
least 4 times.

Can you imagine taking a car to the garage to have new brake pads fitted,
then asking for a new clutch, new tyres etc? They charge for what they do &
so should you.

Sometimes you have to be hard not nice. I'm still learning that lesson
after two years.

2 pics, before, and as left today.
See the lovely colour of the old, and the numerous cleaning bottles
liberally spread around the room - you can see less than half of what
is in there.


Looks good, but why would the customer want to cover up that lovely wood
floor?


--
Dave - The Medway Handyman
www.medwayhandyman.co.uk
01634 717930
07850 597257





  #11   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 1,307
Default Replacement bathroom - fastest procedure?

The Medway Handyman wrote:

A.Lee wrote:

Well, things didnt go quite as planned.


Forth change of plan/screw up by customer.


He dosnt know if he is indecisive, or just not quite sure.
A couple of things I didnt get an answer to, so just did it how I
thought - I said the skirting needs packing out, so I'll fit some new
skirting, "do you want fancy or plain skirting?" He hummed and hahhed, I
never did get an answer, so just bought plain.Other things were the
same.He just hadnt thought about it, and bought a new suite on impulse,
when he only wanted the leaking bath changing at first.

Looks good, but why would the customer want to cover up that lovely wood
floor?


It was a horrible crinkly vinyl.
Ta
Alan.

--
To reply by e-mail, change the ' + ' to 'plus'.
Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
The Fastest Growing Religion in the world [email protected] Metalworking 17 November 29th 07 05:48 PM
THE fastest material removal.... Proctologically Violated©® Metalworking 52 August 13th 07 06:09 AM
Philips CRT coolant replacement 9P6031C- proper procedure? 427Cobraman Electronics Repair 2 September 21st 06 08:56 PM


All times are GMT +1. The time now is 03:35 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"