I'm having a new bathroom fitted with an over the bath shower (thermostatic
mixer valve) and want to tile the walls and floor. As I've had problems in
the past with the seal between the bath and the tiles, I've been told to fit
the bath first and then tile the walls so that the tiles are resting on the
bath edge, that way if the sealant ever fails the water from the shower will
(hopefully) not drip out of the bath and into the floor below. I've also
been told that to make the tiling easier and to avoid having to fit tiles
around awkward shapes like the WC, I should fit all the pipework, then I
should tile the walls and floor (tiling around the pipes sticking out of the
wall) and then I should fit the WC, sink, shower and shower screen. I'm
intending therefore to fit the bathroom in this order:

1) Fit bath
2) Fit pipework for WC, sink and shower.
3) Tile walls and floor
4) Fit WC, and cistern, sink, shower and shower screen.

As this is my first bathroom can anyone offer advice, is this the best order
to fit everything?


  #2   Report Post  
Rick
 
Posts: n/a
Default

On Sat, 23 Jul 2005 12:27:53 +0000 (UTC), "Brian" wrote:

I'm having a new bathroom fitted with an over the bath shower (thermostatic
mixer valve) and want to tile the walls and floor. As I've had problems in
the past with the seal between the bath and the tiles, I've been told to fit
the bath first and then tile the walls so that the tiles are resting on the
bath edge, that way if the sealant ever fails the water from the shower will
(hopefully) not drip out of the bath and into the floor below. I've also
been told that to make the tiling easier and to avoid having to fit tiles
around awkward shapes like the WC, I should fit all the pipework, then I
should tile the walls and floor (tiling around the pipes sticking out of the
wall) and then I should fit the WC, sink, shower and shower screen. I'm
intending therefore to fit the bathroom in this order:

1) Fit bath
2) Fit pipework for WC, sink and shower.
3) Tile walls and floor
4) Fit WC, and cistern, sink, shower and shower screen.

As this is my first bathroom can anyone offer advice, is this the best order
to fit everything?


My order =

Fith bath, sink, big etc, with 10mm plywood between items and walls.
Plumb it all in.
Remove batch, sink etc
Tile
Refit bath, now without the 10mm plywood spaces, as the tiles have
filled in the place wher the spaces were.

I tile walls behind the sink, and foor under the bog. I don't tile
behind the bath, so here I leave out the spacers, work out where the
tiles start 1 row up from the bath, and attach a batton to tile to.
Then I refit bath, fill with water, and tile to it, using those
plastic waterproofer strips.

This way works for me, they are probably 100 differernt ways.

Rick

  #3   Report Post  
David Lang
 
Posts: n/a
Default


"Brian"
wrote in message

I'm having a new bathroom fitted with an over the bath shower
(thermostatic mixer valve) and want to tile the walls and floor. As I've
had problems in the past with the seal between the bath and the tiles,
I've been told to fit the bath first and then tile the walls so that the
tiles are resting on the bath edge, that way if the sealant ever fails the
water from the shower will (hopefully) not drip out of the bath and into
the floor below.


One good tip, fill the bath with water prior to applying the sealant. That
way, any 'give' will be on your side, if you follow my drift.

Dave


Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT +1. The time now is 04:33 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"