Thread
:
Building Quote abbreviation PC SUM?
View Single Post
#
3
Posted to uk.d-i-y
Chris B[_2_]
external usenet poster
Posts: 326
Building Quote abbreviation PC SUM?
On 20/03/2019 09:25,
wrote:
On Wednesday, March 20, 2019 at 9:12:05 AM UTC, Chris B wrote:
I have a builders quote for various minor works
Most of the items are £YYY +VAT
But replacing some rotten wood in a car port is
priced as £XXX +VAT-PC SUM
in this context what is PC SUM?
There is an overall condition covering all items that is
PRICES INCLUDES LABOUR, MATERIALS, REQUIRED ACCESS AND REMOVAL OF SPOILS
FROM SITE
--
Chris B (News)
Prime Cost Sum Presumably he has quotedvcfor the work on a PC basis and is noe changing the price to time and materials less the quoted PC sum
Thank you.
Just done a google on Prime Cost Sum and it all makes sense. When we
viewed the job we agreed that the full extent of the repair might not be
visible until the job was well underway.
With that information I think the line item should be
£XXX +VAT (PC SUM) ie not plus VAT minus PC SUM
--
Chris B (News)
Reply With Quote
Chris B[_2_]
View Public Profile
Find all posts by Chris B[_2_]