Default Building Square Walls On New Construction Sill Plates

On Saturday, March 17, 2018 at 6:10:04 PM UTC-4, Tim Daneliuk wrote:
On 03/17/2018 02:32 PM, DerbyDad03 wrote:
You make it sound like uneven pours are a common problem in this guy's
world, so how is that he is just getting around to asking you to figure
out how to do his job?


1) Is is common.

2) He has solutions, but wants a faster one.


You didn't address my question as to why "you get what you get" when a foundation
is poured in a remote area. Why is it so common that the foundation sucks?

Is it that the good comtractors would charge too much to make the trip, so you have to
settle for Larry, Darryl and Darryl?

If it's a cost saving matter, has your pro figured out whether he actually saves anything
after spending extra time working around the results of saving that upfront cost?