View Single Post
  #289   Report Post  
Posted to uk.d-i-y
whisky-dave[_2_] whisky-dave[_2_] is offline
external usenet poster
 
Posts: 10,204
Default So how much power does an oil filled radiator actually use.

On Thursday, 7 December 2017 20:26:23 UTC, Martin Brown wrote:
On 07/12/2017 20:18, T i m wrote:



what about the other two sets of swing doors, which go to unheated corridor areas ?


Then they will be more relevant.

snip waffle


Indeed if they are open the room will lose the hot air at around head
height as it spills out and rises up on the wrong side of the door.

Can an engineering department really be so clueless about basic physics?


Yes they can, as this is the electric engineering building we have **** all idea about heating even our head professor doesn't know about such thigs.

Do you think the queen knows about engineering in buck palace.


They deserve to suffer from frostbite in the coming winter!


It's not me that will suffer it;s the students, and if tehy can;t work out teh heating requitrements of a building then they should have applied to come here should they.

if surgeons don't understand how their opperating theatres are constructed then they should be surgeons should they.
if david attenboough doesn't understand the construction details of the submerables he is in does that make him stupid too.

we have hve www.hutton-group.co.uk doing the work, or do yuo expect the lectures to put up the scaffolding too.

You have to be a reazk ****ing idiot if you believe it's the job of teh academics or admin staff to put up scaffolding.

For teh last few months higgins has sent us disruption details for the coming week.

Here's todays.
First fix mechanical and electrical to basement east, workshop and
Aero lab ground and first and roof
Lay blocks to old window openings 4th and risers.
Dri-line walls to ground, first, and 4th floors.
Plaster walls and make good all areas
Fit single ply membrane to aero lab
Strike and adjust scaffold
Second fix carpentry to G25
Erect steels to stair 7
Second fix mechanical and electrical to G25
Erect curtain walling including glass
Erect LEV to G25
Paint G25
Make good ceilings in Aero lab ground floor
Tape and joint ceilings.
Remove windows and fix scaffold ties back to columns all floors to tower