"John Stumbles" ] wrote in message
...
"Mitch" wrote in message
...
I had a gas safety check on a Bosch 24i combi and the man said that the
pressure relief pipework was sub-standard as it simply runs from the

boiler
to the floor with the exit inside rather than an external exit.

Can someone please tell me what the Building Regs require as I am

thinking
of correcting this myself (especially as the main work is do drill a

hole)?
EG is it 15mm or 22mm pipe, what are restrictions on the exit, such as

is
it
downward facing etc etc.


Also where could I read or access these regs?


I don't know which regs cover it - it certainly should be in the
manufacturer's installation instructions - but it should terminate outside

a
few inches from, and facing, the ground; so that if/when the pressure

relief
valve opens the blast of potentially boiling water + steam can hit the
ground without injuring anyone. 15mm is generally used.


Not quite. 15mm pipe, outside at a low level and the pipe being turned into
the wall using an elbow. If boiling water/steam is lets off it hits the
wall. The pipe need not be sleeved going through the wall.


---
--