stryped wrote:
The problem is my blacktop is not level. I am not sure how you eould
pour separate slabs and get both dlabs even with each other.



Not a problem. Do you want to do individual pours because of money or
lack of help or ?? This sort of determines the approach you use for the
pour(s)

Keyed slabs are poured daily all over the world. As for the blacktop not
being level, it won't be there so you can make the base level. If you
need to slope the concrete some that isn't a problem either.

--