dg wrote:
On 18 Dec, 17:30, "Ashnook." contact.by.email"
wrote:
I have planning permission to build a double garage in my garden and I
am looking for some advice regarding the foundations.

I am hoping to get away with a 1M deep strip foundation but there is a
hedge on one side so I assume I will need to go a bit deeper on this side.

The bigger issue, though, is that a sewer pipe run under where the
garage is to be built and this will likely clash with the foundation
concrete. I would rather not move the sewer pipe. What are my options?

Can I run the foundation concrete round the pipe if I somehow line the
outside of the pipe so as to leave a gap for the pipe to move within the
concrete? Would this be allowed and would this work? I know I have to
get the building inspector involved at some stage but I want to do a bit
of research first.

If this is not possible then can I build a raft foundation slab instead
and build the garage in this slab?

Or what other options do I have?

Thanks, Brian


Does this garage require Building Regs approval?

If not a shallow trench or a raft would suffice. A raft may be better
to overcome the drain problem

If it requires approval, then your options are more limited. But
generally, you would bridge over the drain, and would take the
foundations down to a teast the invert level or 1000mm.

If the drain is a public sewer, then you also need your water
authority's permission

dg

I don't know if it required building regs approval, I just assumed it
would.

Bridging over the drain means having no foundation concrete under the
sewer at that point?

It's a sewer pipe from some adjacent bungalows that runs across my land.