When mixing on site, how much concrete could one guy pour and finish in one day?
On May 7, 11:37 am, " wrote:
On May 7, 12:32?pm, dpb wrote:
On May 7, 10:27 am, Lawrence wrote:
On May 7, 9:29 am, " wrote:
On May 7, 10:21?am, "** ? ?Frank ? ?**" wrote:
With a small electric concrete mixer (2 bags of 60# or 80# ready mix at a
time) I'm not able to mix much more than an area of 6' x 12' by 4" thick,
anymore I'm not able to finish before it sets in. That was about 44 bags of
60# of ready mix.
Would having two small mixers on at the same time increase productivity? I
don't think I could, or want to, do more than 100 60# bags day.
your losing fiancially, for larger quanties your better off getting it
ppre mixed by a truck.
last time I did a slab, 70 bucks a yard, by truck
by bag 4 tmes that.....
The guy says he's working alone you have to take his word for it. ?I
live in a remote part of the country where it can be difficult or
impossible to find helpers. ...
You have no friends that will come for a weekend work/party?- Hide quoted text -
- Show quoted text -
try to find some friends, or paid help.
check cost of 5 yards delivered
check cost of 5 yards by bag
then check cost of friends realtives or paid help.
I was just pointing out by the bag is the pricest way to go, and not
good if your placing a large slab......
If you'll note, I agreed w/ you and suggested to OP he get some
help...Lawrence was the one who ragged about being a loner, not me,