A yard of dirt is only about a ton damp, and he's only talking about roughly
166 yards. So it's considerably less than your mistaken math.
--
Steve Barker
YOU should be the one
controlling YOUR car.
Check out:
www.lightsout.org
"BobK207" wrote in message
ups.com...
Good to see you're a CE but what do you plan to do with the ~200 yds
of dirt?
~ 3000 tons
That's ~8 "double dumps"
btw I've done the shop vac "moving sandy soil / damp sand" experiment
medium sized shop vac ~10 gallon........ soil removal rate ~ 1gpm
so you've got something on the order of 650 hours of vacuum
time.....not including time to empty & dispose of the dirt.
We're taking about ~100 days of vacuuming (if you can keep at it for 6
hours per day) Even if I'm high by 2x .....still 50 days of
vacuuming!
Consider contracting with a vacuum excavator.
Your new footings are 24" wide? How deep?
I hope they go below your intended excavation depth.