Home |
Search |
Today's Posts |
![]() |
|
UK diy (uk.d-i-y) For the discussion of all topics related to diy (do-it-yourself) in the UK. All levels of experience and proficency are welcome to join in to ask questions or offer solutions. |
Reply |
|
LinkBack | Thread Tools | Display Modes |
|
#1
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
On 08/07/2012 21:00, Bill Wright wrote:
Ellie wrote: We have planning permission for a 2-story extension but can only afford to do the ground floor at the moment. Can we build the ground floor and then put a flat roof on it until we have money to do the upper floor? Does anyone have experience of this? Waste money on a temporary roof? Why not complete the brickwork and roof and wait until you have more money to do the inside work? Bill I dont know for sure but there will probably be a time limit on what you applied to do and doing just the gound floor (I think) would mean you have failed to build what you applied to do and if you therefore go over the time limit you may have to go through the planning process again. One problem could be that each council has its own take on this it maybe best to speak to them about it. |
#2
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
ss wrote:
I dont know for sure but there will probably be a time limit on what you applied to do and doing just the gound floor (I think) would mean you have failed to build what you applied to do and if you therefore go over the time limit you may have to go through the planning process again. Planning permission usually comes with a latest start date, but no stipulated finish date ... |
#3
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
Andy Burns wrote:
Planning permission usually comes with a latest start date, but no stipulated finish date ... I was told that as I hadn't completed my work within the stipulated five years (as it was then) I had to re-apply. JGH |
#4
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
On 08/07/2012 21:27, jgharston wrote:
Andy Burns wrote: Planning permission usually comes with a latest start date, but no stipulated finish date ... I was told that as I hadn't completed my work within the stipulated five years (as it was then) I had to re-apply. JGH Very odd. Planning permission usually stipulates starting within 4 years, but does not stipulate a finish date - hence occassional stories of neighbours fed up of ongoing work lasting a decade or more. SteveW |
#5
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
On 08/07/2012 22:37, SteveW wrote:
On 08/07/2012 21:27, jgharston wrote: Andy Burns wrote: Planning permission usually comes with a latest start date, but no stipulated finish date ... I was told that as I hadn't completed my work within the stipulated five years (as it was then) I had to re-apply. JGH Very odd. Planning permission usually stipulates starting within 4 years, but does not stipulate a finish date - hence occassional stories of neighbours fed up of ongoing work lasting a decade or more. SteveW When I built my house several years back they give me a must finish by date. I cant remember how long it was though but it wasnt excessive, and they did check the final build to make sure it complied with regs and the plans. |
#6
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
SteveW wrote:
I was told that as I hadn't completed my work within the stipulated five years (as it was then) I had to re-apply. Very odd. Planning permission usually stipulates starting within 4 years, but does not stipulate a finish date That's what I argued, but they insisted on their 150 quid and the paperwork. JGH |
#7
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
On Sun, 08 Jul 2012 21:25:50 +0100, Andy Burns
wrote: ss wrote: I dont know for sure but there will probably be a time limit on what you applied to do and doing just the gound floor (I think) would mean you have failed to build what you applied to do and if you therefore go over the time limit you may have to go through the planning process again. Planning permission usually comes with a latest start date, but no stipulated finish date ... Here, if you stick a spade in the ground within five years of the grant of PP, that's it started, and no end date applies. Just as well, really... |
#8
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]() "Grimly Curmudgeon" wrote in message ... Here, if you stick a spade in the ground within five years of the grant of PP, that's it started, and no end date applies. Just as well, really... However building regs may change and that may well require you to change what you build and hence need new planning consent. AIUI building regs apply at the time you build not when you plan, and that the inspector can require you to build to the new regs if he wants. |
#9
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
[Default] On Mon, 9 Jul 2012 07:53:13 +0100, a certain chimpanzee,
"dennis@home" , randomly hit the keyboard and wrote: However building regs may change and that may well require you to change what you build and hence need new planning consent. AIUI building regs apply at the time you build not when you plan, and that the inspector can require you to build to the new regs if he wants. How many levels of wrong was this answer? Once building work has commenced on an application, the 'requirements' [1] of the regulations that were in force at the time will apply [2]. Planning consent [3] has nothing to do with the Building Regulations [4]. If you submit a Full Plans application, and it is approved, then provided work is commenced on this application within three years, the requirements in force at the time the original application was submitted apply to the work [5]. The same applies to a building notice. However, there have been occasions when changes to the requirements have been applied to work that has not been commenced and was either submitted on a building notice or plans had not been fully approved. A building control surveyor or officer [6] can't require you to build to the new regs 'if he wants'[7]. There has to be a legal basis (i.e., Statutury Instruments) to any change in guidance, and any BCO would know this. 7 factual errors in four lines. -- Hugo Nebula "If no-one on the internet wants a piece of this, just how far from the pack have I strayed"? |
#10
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]()
Hugo Nebula wrote:
[Default] On Mon, 9 Jul 2012 07:53:13 +0100, a certain chimpanzee, "dennis@home" , randomly hit the keyboard and wrote: However building regs may change and that may well require you to change what you build and hence need new planning consent. AIUI building regs apply at the time you build not when you plan, and that the inspector can require you to build to the new regs if he wants. How many levels of wrong was this answer? Once building work has commenced on an application, the 'requirements' [1] of the regulations that were in force at the time will apply [2]. Planning consent [3] has nothing to do with the Building Regulations [4]. If you submit a Full Plans application, and it is approved, then provided work is commenced on this application within three years, the requirements in force at the time the original application was submitted apply to the work [5]. The same applies to a building notice. However, there have been occasions when changes to the requirements have been applied to work that has not been commenced and was either submitted on a building notice or plans had not been fully approved. A building control surveyor or officer [6] can't require you to build to the new regs 'if he wants'[7]. There has to be a legal basis (i.e., Statutury Instruments) to any change in guidance, and any BCO would know this. 7 factual errors in four lines. That's actually quite good going for den:-) -- Adam |
#11
![]()
Posted to uk.d-i-y
|
|||
|
|||
![]() "Hugo Nebula" wrote in message ... [Default] On Mon, 9 Jul 2012 07:53:13 +0100, a certain chimpanzee, "dennis@home" , randomly hit the keyboard and wrote: However building regs may change and that may well require you to change what you build and hence need new planning consent. AIUI building regs apply at the time you build not when you plan, and that the inspector can require you to build to the new regs if he wants. How many levels of wrong was this answer? Well i can see that your answer actually says exactly what I said so I guess its all wrong because you always are! Once building work has commenced on an application, the 'requirements' [1] of the regulations that were in force at the time will apply [2]. Planning consent [3] has nothing to do with the Building Regulations [4]. "building regs apply at the time you build not when you plan" is the correct answer and is the same as what you quoted. If you submit a Full Plans application, and it is approved, then provided work is commenced on this application within three years, the requirements in force at the time the original application was submitted apply to the work [5]. The same applies to a building notice. However, there have been occasions when changes to the requirements have been applied to work that has not been commenced and was either submitted on a building notice or plans had not been fully approved. Building regs have nothing to do with planning and are not approved when you submit plans for planning applications. A building control surveyor or officer [6] can't require you to build to the new regs 'if he wants'[7]. There has to be a legal basis (i.e., Statutury Instruments) to any change in guidance, and any BCO would know this. Funny "inspector can require you to build to the new regs " How do you get new regs unless there has been a legal change? 7 factual errors in four lines. Yes you really did manage to post proof of what I said and then claim I was wrong, well done. -- Hugo Nebula "If no-one on the internet wants a piece of this, just how far from the pack have I strayed"? |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Do I need Planning permission? | UK diy | |||
Planning Permission Plans | UK diy | |||
Will I ever get planning permission??? | UK diy | |||
Planning Permission Required ? | UK diy | |||
Planning Permission | UK diy |