Hello,

I'm going to fit a new soil stack for an en-suite that I'm installing.
I'm not sure how I should tap into the current inspection chamber
which is about 2 metres away from where the new soil stack entwrs the
ground.

Do I have to replace the inspection chamber in order to add the
additional waste pipe?

Thanks
  #2   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 886
Default New soil stack

On Mon, 23 Feb 2009 07:38:54 -0800, tvmo wrote:

Do I have to replace the inspection chamber in order to add the
additional waste pipe?


It'll be notifiable work so you might want to check with the building
control officer what they'll require.



--
John Stumbles -- http://yaph.co.uk

My karma ran over my dogma
  #3   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 2,488
Default New soil stack

In an earlier contribution to this discussion,
tvmo wrote:

Hello,

I'm going to fit a new soil stack for an en-suite that I'm installing.
I'm not sure how I should tap into the current inspection chamber
which is about 2 metres away from where the new soil stack entwrs the
ground.

Do I have to replace the inspection chamber in order to add the
additional waste pipe?

Thanks


What sort of inspection chamber is it - is it built of brick, or one of
these pre-formed plastic jobbies? How deep is it?

As others have said, you need to consult Building Control at your local
council to find out what they want you to do. You usually have to join in
new soil stacks at invert level (i.e. the open channel at the bottom) - so
if it's deep (mine are 2 metres!) you either need to dig a very deep trench,
or go in through the side higher up and then take a pipe vertically down the
inside. You can't just 'dump' solid waste at high level because it will pile
up in the bottom and cause a blockage.

Building Control will also tell you what you need to do with the top of the
stack. You may need to go up through the roof with an open vent at the top,
or you may get away with just an AAV (air admittance valve) without going
out through the roof.

And, of course, you'll have to pay Building Inspection fees whatever
happens!
--
Cheers,
Roger
______
Email address maintained for newsgroup use only, and not regularly
monitored.. Messages sent to it may not be read for several weeks.
PLEASE REPLY TO NEWSGROUP!


Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to seal new plastic soil stack to old cast iron stack tonyjeffs[_2_] UK diy 4 February 12th 09 04:54 PM
Help: Soil Connection Options for Under Stairs Macerator (Soil Stack/ Manhole) GC UK diy 0 March 23rd 08 12:32 PM
soil stack ANDREW LENWEY UK diy 1 October 23rd 05 08:32 AM
Soil stack? Stinkoman UK diy 4 April 10th 05 01:45 PM
soil stack karla Home Repair 1 February 2nd 05 12:41 AM


All times are GMT +1. The time now is 01:36 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"