Home |
Search |
Today's Posts |
|
UK diy (uk.d-i-y) For the discussion of all topics related to diy (do-it-yourself) in the UK. All levels of experience and proficency are welcome to join in to ask questions or offer solutions. |
Reply |
|
LinkBack | Thread Tools | Display Modes |
#1
Posted to uk.d-i-y
|
|||
|
|||
floor slab - need hardcore ?
My extension spec says the floor slab will be "50mm soft sand on
oversite as required", then DPM, 100mm polystyrene , 100mm concrete slab etc. What does "oversite" mean ? I read elsewhere that 6 inches of compacted hardcore is usually required under the sand. The area to be slabbed is at present compacted sub-soil and some areas of pea shingle around the drains. I was going to put the sand etc onto this. Will this be OK, or do I need to dig out 6 inches and replace with hardcore ? Thanks, Simon. |
#2
Posted to uk.d-i-y
|
|||
|
|||
floor slab - need hardcore ?
sm_jamieson wrote:
My extension spec says the floor slab will be "50mm soft sand on oversite as required", then DPM, 100mm polystyrene , 100mm concrete slab etc. What does "oversite" mean ? I read elsewhere that 6 inches of compacted hardcore is usually required under the sand. The area to be slabbed is at present compacted sub-soil and some areas of pea shingle around the drains. I was going to put the sand etc onto this. Will this be OK, or do I need to dig out 6 inches and replace with hardcore ? Thanks, Simon. Starting from the bottom: 150mm MOT (hardcore) whacked down 50mm sand blinding whacked down 125mm of polystyrene (100mm is not enough - you can use 75mm celotex but this is often more expensive than a 75 + 50 sheet of polystyrene (they don't make 125mm for some reason, although this is now standard)) visqueen (1200dpm) 100mm concrete. The sand blinding is now surplus to requirements because it was originally to stop the DPM being perforated by the MOT, but considering most people now put the DPM *above* the polystyrene, it's not required, although the BCO doesn't see it that way. You can put the DPM under the insulation, but the concrete sometimes rides underneath it and shoves it upwards. HTH |
#3
Posted to uk.d-i-y
|
|||
|
|||
floor slab - need hardcore ?
On 11 May, 17:04, "Phil L" wrote:
sm_jamieson wrote: My extension spec says the floor slab will be "50mm soft sand on oversite as required", then DPM, 100mm polystyrene , 100mm concrete slab etc. What does "oversite" mean ? I read elsewhere that 6 inches of compacted hardcore is usually required under the sand. The area to be slabbed is at present compacted sub-soil and some areas of pea shingle around the drains. I was going to put the sand etc onto this. Will this be OK, or do I need to dig out 6 inches and replace with hardcore ? Thanks, Simon. Starting from the bottom: 150mm MOT (hardcore) whacked down 50mm sand blinding whacked down 125mm of polystyrene (100mm is not enough - you can use 75mm celotex but this is often more expensive than a 75 + 50 sheet of polystyrene (they don't make 125mm for some reason, although this is now standard)) visqueen (1200dpm) 100mm concrete. The sand blinding is now surplus to requirements because it was originally to stop the DPM being perforated by the MOT, but considering most people now put the DPM *above* the polystyrene, it's not required, although the BCO doesn't see it that way. You can put the DPM under the insulation, but the concrete sometimes rides underneath it and shoves it upwards. HTH !00mm polystyrene is OK since I'm full plans approved before 2006. I've checked on this. But the 6 inches of MOT is required as far as you are aware ? Where new drains would come within the MOT layer, how would these be protected ? They would have pea shingle around, but how is this separated from the MOT, when there is no "edge" as such ? Simon. |
#4
Posted to uk.d-i-y
|
|||
|
|||
floor slab - need hardcore ?
sm_jamieson wrote:
!00mm polystyrene is OK since I'm full plans approved before 2006. I've checked on this. OK But the 6 inches of MOT is required as far as you are aware ? You may get away with 100mm, but yes, it is definately required. Where new drains would come within the MOT layer, how would these be protected ? unless they are a few feet down (I think 2 or 3) of the slab, then they need capping in concrete prior to the MOT going in....certainly if they are so high that the MOT is going to touch them, they will require capping, ask your BCO before commencing with this though as some are more picky than others. snip |
#5
Posted to uk.d-i-y
|
|||
|
|||
floor slab - need hardcore ?
On 11 May, 17:27, "Phil L" wrote:
sm_jamieson wrote: !00mm polystyrene is OK since I'm full plans approved before 2006. I've checked on this. OK But the 6 inches of MOT is required as far as you are aware ? You may get away with 100mm, but yes, it is definately required. Where new drains would come within the MOT layer, how would these be protected ? unless they are a few feet down (I think 2 or 3) of the slab, then they need capping in concrete prior to the MOT going in....certainly if they are so high that the MOT is going to touch them, they will require capping, ask your BCO before commencing with this though as some are more picky than others. snip One other thing, I have an inspection chamber penetrating the floor slab (i.e. will be internal). The only thing to do here will be to have a gap in the insulation I suppose, but what do you do with the DPM ? Just bring it up and cut off at the top ? Simon. |
#6
Posted to uk.d-i-y
|
|||
|
|||
floor slab - need hardcore ?
sm_jamieson wrote:
On 11 May, 17:27, "Phil L" wrote: sm_jamieson wrote: !00mm polystyrene is OK since I'm full plans approved before 2006. I've checked on this. OK But the 6 inches of MOT is required as far as you are aware ? You may get away with 100mm, but yes, it is definately required. Where new drains would come within the MOT layer, how would these be protected ? unless they are a few feet down (I think 2 or 3) of the slab, then they need capping in concrete prior to the MOT going in....certainly if they are so high that the MOT is going to touch them, they will require capping, ask your BCO before commencing with this though as some are more picky than others. snip One other thing, I have an inspection chamber penetrating the floor slab (i.e. will be internal). The only thing to do here will be to have a gap in the insulation I suppose, but what do you do with the DPM ? Just bring it up and cut off at the top ? Simon. What has the BCO said about the manhole? - I think you wil have to re-route it so that it's outside the building, if that's possible, if it isn't possible, then you'll have to have it inside,and as you say, cut it off at the top. |
#7
Posted to uk.d-i-y
|
|||
|
|||
floor slab - need hardcore ?
On 11 May, 21:55, "Phil L" wrote:
sm_jamieson wrote: On 11 May, 17:27, "Phil L" wrote: sm_jamieson wrote: !00mm polystyrene is OK since I'm full plans approved before 2006. I've checked on this. OK But the 6 inches of MOT is required as far as you are aware ? You may get away with 100mm, but yes, it is definately required. Where new drains would come within the MOT layer, how would these be protected ? unless they are a few feet down (I think 2 or 3) of the slab, then they need capping in concrete prior to the MOT going in....certainly if they are so high that the MOT is going to touch them, they will require capping, ask your BCO before commencing with this though as some are more picky than others. snip One other thing, I have an inspection chamber penetrating the floor slab (i.e. will be internal). The only thing to do here will be to have a gap in the insulation I suppose, but what do you do with the DPM ? Just bring it up and cut off at the top ? Simon. What has the BCO said about the manhole? - I think you wil have to re-route it so that it's outside the building, if that's possible, if it isn't possible, then you'll have to have it inside,and as you say, cut it off at the top. The manhole was always part of the plans, required due to a junction between the main soil pipe and a new toilet. Anyway, a cut in the DPM would not form much of an upstand, so DPM would have to be added like a vertical cylinder, which would serve no purpose at all. It looks like I'll have to contact the BCO to sort out a few of these issues ! Simon. |
#8
Posted to uk.d-i-y
|
|||
|
|||
floor slab - need hardcore ?
sm_jamieson wrote:
The manhole was always part of the plans, required due to a junction between the main soil pipe and a new toilet. Anyway, a cut in the DPM would not form much of an upstand, so DPM would have to be added like a vertical cylinder, which would serve no purpose at all. It looks like I'll have to contact the BCO to sort out a few of these issues ! Simon. All you need to do is cut a piece of DPM around 7ft square and place it over the manhole, then tuck the edges in so that it's touching the sides of the manhole, however creased it is, it will be OK. Then lay the rest of the DPM as normal, obvioulsy the square will need cutting out for the manhole, but the first one will stay in place, underneath, as long as there is an overlap of a foot or two, then nothing will get through. Then cut out around the manhole lid once the concrete is finished |
#9
Posted to uk.d-i-y
|
|||
|
|||
floor slab - need hardcore ?
On 12 May, 00:15, "Phil L" wrote:
sm_jamieson wrote: The manhole was always part of the plans, required due to a junction between the main soil pipe and a new toilet. Anyway, a cut in the DPM would not form much of an upstand, so DPM would have to be added like a vertical cylinder, which would serve no purpose at all. It looks like I'll have to contact the BCO to sort out a few of these issues ! Simon. All you need to do is cut a piece of DPM around 7ft square and place it over the manhole, then tuck the edges in so that it's touching the sides of the manhole, however creased it is, it will be OK. Then lay the rest of the DPM as normal, obvioulsy the square will need cutting out for the manhole, but the first one will stay in place, underneath, as long as there is an overlap of a foot or two, then nothing will get through. Then cut out around the manhole lid once the concrete is finished OK thats great. I'll ask the BCO about the drain capping. I'll post details back here for completeness when I know. Thanks, Simon. |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|