  #1   Report Post  
Posted to alt.home.repair
external usenet poster
 
Posts: 2
Default How do I avoid Contractor nickel and diming me?

I found a local contractor to build a deck for me out of a imported
exotic hardwood (ipe). The project involved removing an existing deck
and rebuilding it. He did seem to be very knowledgeable and
enthusiastic. He quoted me a price (labor only) approximately 70%
more than two other contractors because he did his research and knew
that this wood is difficult to work with. The suppliers of the wood
estimate labor costs approximately 50% higher than using a traditional
deck wood, so I did not think his estimate was totally unreasonable.
The other two contractors have never heard of ipe wood, and I believe
simply ignorant of the difficulty in working with this EXTREMELY hard
dense wood (all screws and holes must be predrilled, and cannot hammer
through this wood). I accepted his bid without haggling, and I told
him that I expected that he was a master craftsman, and I expected that
he is an expert, and that is why I would pay him top dollar. He
quoted me a time estimate of 2 1/2 weeks to complete the deck.

Since beginning he has taken every opportunity to charge me extra labor
costs. Firstly, on demolition of the existing deck, he said that the
existing deck posts were deeper than anticipated, and so he charged me
rental for a larger jack hammer than he had, and charged me $650 extra
($65 an hour for extra 10 hours). I told him that I was not pleased,
but agreed for him to proceed. I do not know exactly how much EXTRA
time (beyond what he expected and should have been covered by the
original bid) but I seriously doubt it was 10 hours.

Then when I discovered that the wood supplier would not unload the
delivery truck, he said he wanted to unload it, and that he needed a
fork-lift (approximately 6000 lbs total weight of wood). The
supplier told me that there were about 5 batches of wood. I told him
to go ahead, and that I could not imagine that it would take more than
an hour to unload the truck using a fork-lift. Well after this
occured, he charged me 2 1/2 hrs labor (this time he charged $75 an
hour) time. When I said that I could not understand how it could have
taken 2 1/2 hours to unload with a fork-lift, he said he examined each
piece of wood, and that is why it took that length of time. When I
complained, he asked if I wanted him to just accept lousy wood, I told
him I felt that examining the building materials should included in his
original labor bid. But I went ahead and paid him.

He has worked on the project a total of 4 days, and the posts, and
joists are all up and now he says he will be finished within a week.

I find it very f**ked-up, that he takes every opportunity to charge me
additional labor costs when he says a particular step is taking longer
than anticipated, but when and if he finishes the project in less than
half the time he said it would, why should not I request a 50% return
of the labor costs he bid. Obviously, the overall labor time is way
less than he proposed to me, why am paying for extra labor costs. Do
all contractors pay this game, and how can I prevent this in the future?

  #2   Report Post  
Posted to alt.home.repair
external usenet poster
 
Posts: 296
Default How do I avoid Contractor nickel and diming me?

Just say no!!!!! If you think a contractor is milking you and
charging extra just say no. Remind them of the contract you signed
and his estimate. If he balks remind him that he is not going to be
paid until deck is X% finshed and then final payment is made upon
finishing,. You do have a signed contract right? You did check
references? If you keep letting it go the deck will cost a lot more
than the estimate.

wrote:
I found a local contractor to build a deck for me out of a imported
exotic hardwood (ipe). The project involved removing an existing deck
and rebuilding it. He did seem to be very knowledgeable and
enthusiastic. He quoted me a price (labor only) approximately 70%
more than two other contractors because he did his research and knew
that this wood is difficult to work with. The suppliers of the wood
estimate labor costs approximately 50% higher than using a traditional
deck wood, so I did not think his estimate was totally unreasonable.
The other two contractors have never heard of ipe wood, and I believe
simply ignorant of the difficulty in working with this EXTREMELY hard
dense wood (all screws and holes must be predrilled, and cannot hammer
through this wood). I accepted his bid without haggling, and I told
him that I expected that he was a master craftsman, and I expected that
he is an expert, and that is why I would pay him top dollar. He
quoted me a time estimate of 2 1/2 weeks to complete the deck.

Since beginning he has taken every opportunity to charge me extra labor
costs. Firstly, on demolition of the existing deck, he said that the
existing deck posts were deeper than anticipated, and so he charged me
rental for a larger jack hammer than he had, and charged me $650 extra
($65 an hour for extra 10 hours). I told him that I was not pleased,
but agreed for him to proceed. I do not know exactly how much EXTRA
time (beyond what he expected and should have been covered by the
original bid) but I seriously doubt it was 10 hours.

Then when I discovered that the wood supplier would not unload the
delivery truck, he said he wanted to unload it, and that he needed a
fork-lift (approximately 6000 lbs total weight of wood). The
supplier told me that there were about 5 batches of wood. I told him
to go ahead, and that I could not imagine that it would take more than
an hour to unload the truck using a fork-lift. Well after this
occured, he charged me 2 1/2 hrs labor (this time he charged $75 an
hour) time. When I said that I could not understand how it could have
taken 2 1/2 hours to unload with a fork-lift, he said he examined each
piece of wood, and that is why it took that length of time. When I
complained, he asked if I wanted him to just accept lousy wood, I told
him I felt that examining the building materials should included in his
original labor bid. But I went ahead and paid him.

He has worked on the project a total of 4 days, and the posts, and
joists are all up and now he says he will be finished within a week.

I find it very f**ked-up, that he takes every opportunity to charge me
additional labor costs when he says a particular step is taking longer
than anticipated, but when and if he finishes the project in less than
half the time he said it would, why should not I request a 50% return
of the labor costs he bid. Obviously, the overall labor time is way
less than he proposed to me, why am paying for extra labor costs. Do
all contractors pay this game, and how can I prevent this in the future?


  #3   Report Post  
Posted to alt.home.repair
external usenet poster
 
Posts: 286
Default How do I avoid Contractor nickel and diming me?

you definately took it in both ends on this one, he had you over a
barell and knew it. you should have made sure the lumber yard was going
to unload it upfront, I do that all the time when I'm not buying
through home depot (and I will only buy wood from the main area
distributer for home depot, the rest of them screw you around here).
the rest of it was B.S. and should have been covered by the original
bid, thats why you got it in the first place. the only changes to the
original should come from mistakes you made not because the contractor
didn't figure on something. (changing from the plan is a good way to
rack up your bill).

Empressess #124457


The best Games


a href=http://www.gamestotal.com/Multiplayer Online Games/a a
href=http://www.gamestotal.com/Strategy Games/abra
href=http://uc.gamestotal.com/Unification Wars/a - a
href=http://uc.gamestotal.com/Massive Multiplayer Online
Games/abra href=http://gc.gamestotal.com/Galactic Conquest/a -
a href=http://gc.gamestotal.com/Strategy Games/abra
href=http://www.stephenyong.com/runescape.htmRunescape/abra
href=http://www.stephenyong.com/kingsofchaos.htmKings of chaos/abr

wrote:
I found a local contractor to build a deck for me out of a imported
exotic hardwood (ipe). The project involved removing an existing deck
and rebuilding it. He did seem to be very knowledgeable and
enthusiastic. He quoted me a price (labor only) approximately 70%
more than two other contractors because he did his research and knew
that this wood is difficult to work with. The suppliers of the wood
estimate labor costs approximately 50% higher than using a traditional
deck wood, so I did not think his estimate was totally unreasonable.
The other two contractors have never heard of ipe wood, and I believe
simply ignorant of the difficulty in working with this EXTREMELY hard
dense wood (all screws and holes must be predrilled, and cannot hammer
through this wood). I accepted his bid without haggling, and I told
him that I expected that he was a master craftsman, and I expected that
he is an expert, and that is why I would pay him top dollar. He
quoted me a time estimate of 2 1/2 weeks to complete the deck.

Since beginning he has taken every opportunity to charge me extra labor
costs. Firstly, on demolition of the existing deck, he said that the
existing deck posts were deeper than anticipated, and so he charged me
rental for a larger jack hammer than he had, and charged me $650 extra
($65 an hour for extra 10 hours). I told him that I was not pleased,
but agreed for him to proceed. I do not know exactly how much EXTRA
time (beyond what he expected and should have been covered by the
original bid) but I seriously doubt it was 10 hours.

Then when I discovered that the wood supplier would not unload the
delivery truck, he said he wanted to unload it, and that he needed a
fork-lift (approximately 6000 lbs total weight of wood). The
supplier told me that there were about 5 batches of wood. I told him
to go ahead, and that I could not imagine that it would take more than
an hour to unload the truck using a fork-lift. Well after this
occured, he charged me 2 1/2 hrs labor (this time he charged $75 an
hour) time. When I said that I could not understand how it could have
taken 2 1/2 hours to unload with a fork-lift, he said he examined each
piece of wood, and that is why it took that length of time. When I
complained, he asked if I wanted him to just accept lousy wood, I told
him I felt that examining the building materials should included in his
original labor bid. But I went ahead and paid him.

He has worked on the project a total of 4 days, and the posts, and
joists are all up and now he says he will be finished within a week.

I find it very f**ked-up, that he takes every opportunity to charge me
additional labor costs when he says a particular step is taking longer
than anticipated, but when and if he finishes the project in less than
half the time he said it would, why should not I request a 50% return
of the labor costs he bid. Obviously, the overall labor time is way
less than he proposed to me, why am paying for extra labor costs. Do
all contractors pay this game, and how can I prevent this in the future?


  #4   Report Post  
Posted to alt.home.repair
DK DK is offline
external usenet poster
 
Posts: 257
Default How do I avoid Contractor nickel and diming me?

On 25 Sep 2006 16:15:46 -0700, "
wrote:

I found a local contractor to build a deck for me out of a imported
exotic hardwood (ipe). The project involved removing an existing deck
and rebuilding it. He did seem to be very knowledgeable and
enthusiastic. He quoted me a price (labor only) approximately 70%
more than two other contractors because he did his research and knew
that this wood is difficult to work with. The suppliers of the wood
estimate labor costs approximately 50% higher than using a traditional
deck wood, so I did not think his estimate was totally unreasonable.
The other two contractors have never heard of ipe wood, and I believe
simply ignorant of the difficulty in working with this EXTREMELY hard
dense wood (all screws and holes must be predrilled, and cannot hammer
through this wood). I accepted his bid without haggling, and I told
him that I expected that he was a master craftsman, and I expected that
he is an expert, and that is why I would pay him top dollar. He
quoted me a time estimate of 2 1/2 weeks to complete the deck.

Since beginning he has taken every opportunity to charge me extra labor
costs. Firstly, on demolition of the existing deck, he said that the
existing deck posts were deeper than anticipated, and so he charged me
rental for a larger jack hammer than he had, and charged me $650 extra
($65 an hour for extra 10 hours). I told him that I was not pleased,
but agreed for him to proceed. I do not know exactly how much EXTRA
time (beyond what he expected and should have been covered by the
original bid) but I seriously doubt it was 10 hours.

Then when I discovered that the wood supplier would not unload the
delivery truck, he said he wanted to unload it, and that he needed a
fork-lift (approximately 6000 lbs total weight of wood). The
supplier told me that there were about 5 batches of wood. I told him
to go ahead, and that I could not imagine that it would take more than
an hour to unload the truck using a fork-lift. Well after this
occured, he charged me 2 1/2 hrs labor (this time he charged $75 an
hour) time. When I said that I could not understand how it could have
taken 2 1/2 hours to unload with a fork-lift, he said he examined each
piece of wood, and that is why it took that length of time. When I
complained, he asked if I wanted him to just accept lousy wood, I told
him I felt that examining the building materials should included in his
original labor bid. But I went ahead and paid him.

He has worked on the project a total of 4 days, and the posts, and
joists are all up and now he says he will be finished within a week.

I find it very f**ked-up, that he takes every opportunity to charge me
additional labor costs when he says a particular step is taking longer
than anticipated, but when and if he finishes the project in less than
half the time he said it would, why should not I request a 50% return
of the labor costs he bid. Obviously, the overall labor time is way
less than he proposed to me, why am paying for extra labor costs. Do
all contractors pay this game, and how can I prevent this in the future?


No. You are being had.

However, in the real world, you have to ask whether you are better
off finishing the job by patronizing him or proceeding with legal
threats and even suing. How firm is your contract?




  #5   Report Post  
Posted to alt.home.repair
external usenet poster
 
Posts: 3
Default How do I avoid Contractor nickel and diming me?


" wrote

Do all contractors pay this game, and how can I prevent this in the
future?


Sounds as if you hired a handyman, hoping to get a professional job.

You do not mention a contract, and though assumption is not a good thing
for me to do, I assume you do not have a contract.

You mention "When I said that I could not understand how it could have
taken 2 1/2 hours to unload with a fork-lift, he said he examined each
piece of wood, and that is why it took that length of time. When I
complained, he asked if I wanted him to just accept lousy wood, I told
him I felt that examining the building materials should included in his
original labor bid."
A professional will inspect, and crown wood before installing, any
reputable supplier will honor rejects. You don't inspect while the delivery
driver is still there.

You can prevent being bent over, by having someone familiar with contracts,
make sure all parties are protected, especially you.

Additional work above the work spelled out in a contract, is always extra.
Cost factors should be agreed to, before signing the contract.






  #6   Report Post  
Posted to alt.home.repair
external usenet poster
 
Posts: 79
Default How do I avoid Contractor nickel and diming me?

Q: How do I avoid Contractor nickel and diming me?

A: Have a contract.

S


  #7   Report Post  
Posted to alt.home.repair
external usenet poster
 
Posts: 289
Default How do I avoid Contractor nickel and diming me?


"mrsgator88" wrote in message
...
Q: How do I avoid Contractor nickel and diming me?

A: Have a contract.

S


And any and all change orders must be in writing and signed by both parties.
Any disputes can be immediately cleared up by pulling out the original
contract or change order.

PUT IT IN WRITING.

Steve


  #8   Report Post  
Posted to alt.home.repair
external usenet poster
 
Posts: 4,500
Default How do I avoid Contractor nickel and diming me?

This doesn't sound like nickel and diming to me. It's more like $10's
and $20's. There are several ways to avoid it:

1 - Check out the guys references

2 - Have a written contract that is clear

3 - Just say no

In the case of the paying extra to jack hammer the existing posts out,
why did you agree to pay for an extra 10hrs X $65? plus tool rental.
Did you verify that the post footings even were anything out of the
normal? Was removal not included in the contract? If it was, then I
would have just told him, sorry, but this is included in the agreement.
End of discussion. And at that point, it was the beginning of the
job, where you should have either got him under control or gotten rid
of him.

In the case of the wood, unless specified otherwise, it's not the
contractor's responsibility to unload wood that you are supplying. I'd
put part of the blame on the supplier for this one. Surely many of the
sites they deliver to don't have a fork lift waiting. When someone is
ordering 3 tons of wood, they should have discussed how it's going to
be unloaded. At that point, if they couldn't provide an unloading
option, you might have been able to find another supplier.

I think the contractor's story of 2.5 hours to unload the wood because
he had to inspect it is BS. In any construction contract, unless it's
stated otherwise, it's implied that would be part of the job. The only
exception would be if you used salvaged wood, or similar that is in
totally unknown condition. But, if the 2.5hrs x $75 includes the
forklift, that really doesn't sound too bad. What other options were
there and how much would they have cost?

As to trying to get your money back at the end of the job, forget it.
You don't have a leg to stand on. At both these points, you agreed to
what he was doing, either before or after the fact and you paid him.
If you try to recover it later, no court is gonna find in your favor.
Next time, just say no.

  #10   Report Post  
Posted to alt.home.repair
external usenet poster
 
Posts: 61
Default How do I avoid Contractor nickel and diming me?


Next time ... references, references, references ... and a work
breakdown. If you ever contract any work, ask for references ... and
talk to the people the person has done work for. That's the best way I
know of to avoid most problems. For this job though, the extra
(unforseen) may be reasonable.



  #11   Report Post  
Posted to alt.home.repair
jd jd is offline
external usenet poster
 
Posts: 44
Default How do I avoid Contractor nickel and diming me?

You are being taken advantage of.

do you have a contract? if so, simply point to it (assuming that its
detailed enough).

I've done a ton of small jobs, including "special work" (things like odd
woods or custom made parts).

I always have contract - it protects both me and the customer. If there are
parts of the project that are impossible to set a solid price on (like
digging holes where there may be ledge, unknown shipping costs for large
custom parts that may come from far away, etc), I simply include a line that
states something like "if ledge is present, customer will either pay actual
additional costs incurred, or may, at his option, terminate the contract by
paying all outstanding charges at that time" for things like the shipping
problems, I include language like "parts needed for XXXX are being supplied
by CompanyZZZZ. Cost of shipping parts to teh job site are not included in
this quote, and are customers responsibility"...

On occasion, a customer complains about the "loopholes", but when I explain
that if I have to put a number in, it will have to be the maximum possible
cost, which the customer will then be obligated to pay, regardless of the
actual cost. Usually they are OK with it, but now and then they insist on
including an actual price. Their choice.

Thing like loading trucks, inspecting stock, etc are part of the basic bid -
its simply a part of the job. Charging extra for it is like charging extra
to go buy nails.

Any time I'm digging (no matter how little), the ledge clause goes into the
contract. once again, if a customer complains, I explain that a chunk of
ledge in the wrong spot can cost tousands of dollars to deal with. The
clause simply gives the customer the choice of continuing the job and paying
the actual costs, or stopping. I insist on having them pay the costs up to
that point for two reasons; first, simply because i have to make a living,
and second, because usually it would be discovered fairly early in the job.
Either right after demo is done or right at the begining (when new
foundations footings or whatever are being dug).

My basic premise is that if the customer is never surprised b an additional
cost, and is given the option of stopping if a large unexpected cost comes
up, they'll be happy. so far, its worked. The worst thing I've had happen
was a customer that had started a job (major deck/sunporch enlargement), and
we did hit a large area of ledge. We spent a few hours trying to work around
it (looking for other ways to place the footings), and when it just wasn't
possible, the customer decided to stop the job because they could not afford
the extra work. We chatted for a bit, and came up with a fairly low-cost way
to close things down for a year (so that there wouldn't be weather damage to
the exposed parts), and scheduled the job to continue the following year.
Not ideal, but it gave the client time to save up for the ledge removal,
caused a minor additional expense (we both gave a bit in the closing up and
re-opening part of the work), and meant that the client had a year without a
porch or deck. The following spring, they were the first job I did, and they
are still one of the best references I have.
They weren't happy that they had to go so long without their porch, and they
weren't happy about paying to have the ledge removed, but they weren't
surprised (we had discussed the possibility of ledge during the contract
phase), and they were happy that I was willing to work with them to close
the house back up as economically as possible, and in a way that would make
it easy to continue the job later. When it became clear that we were going
to have to find a work around to the situation, we both sat down and talked
about our options, and came up with a solution that worked - not perfect or
ideal, but it did work.....

--JD



" wrote in message
ups.com...
I found a local contractor to build a deck for me out of a imported
exotic hardwood (ipe). The project involved removing an existing deck
and rebuilding it. He did seem to be very knowledgeable and
enthusiastic. He quoted me a price (labor only) approximately 70%
more than two other contractors because he did his research and knew
that this wood is difficult to work with. The suppliers of the wood
estimate labor costs approximately 50% higher than using a traditional
deck wood, so I did not think his estimate was totally unreasonable.
The other two contractors have never heard of ipe wood, and I believe
simply ignorant of the difficulty in working with this EXTREMELY hard
dense wood (all screws and holes must be predrilled, and cannot hammer
through this wood). I accepted his bid without haggling, and I told
him that I expected that he was a master craftsman, and I expected that
he is an expert, and that is why I would pay him top dollar. He
quoted me a time estimate of 2 1/2 weeks to complete the deck.

Since beginning he has taken every opportunity to charge me extra labor
costs. Firstly, on demolition of the existing deck, he said that the
existing deck posts were deeper than anticipated, and so he charged me
rental for a larger jack hammer than he had, and charged me $650 extra
($65 an hour for extra 10 hours). I told him that I was not pleased,
but agreed for him to proceed. I do not know exactly how much EXTRA
time (beyond what he expected and should have been covered by the
original bid) but I seriously doubt it was 10 hours.

Then when I discovered that the wood supplier would not unload the
delivery truck, he said he wanted to unload it, and that he needed a
fork-lift (approximately 6000 lbs total weight of wood). The
supplier told me that there were about 5 batches of wood. I told him
to go ahead, and that I could not imagine that it would take more than
an hour to unload the truck using a fork-lift. Well after this
occured, he charged me 2 1/2 hrs labor (this time he charged $75 an
hour) time. When I said that I could not understand how it could have
taken 2 1/2 hours to unload with a fork-lift, he said he examined each
piece of wood, and that is why it took that length of time. When I
complained, he asked if I wanted him to just accept lousy wood, I told
him I felt that examining the building materials should included in his
original labor bid. But I went ahead and paid him.

He has worked on the project a total of 4 days, and the posts, and
joists are all up and now he says he will be finished within a week.

I find it very f**ked-up, that he takes every opportunity to charge me
additional labor costs when he says a particular step is taking longer
than anticipated, but when and if he finishes the project in less than
half the time he said it would, why should not I request a 50% return
of the labor costs he bid. Obviously, the overall labor time is way
less than he proposed to me, why am paying for extra labor costs. Do
all contractors pay this game, and how can I prevent this in the future?



  #12   Report Post  
Posted to alt.home.repair
external usenet poster
 
Posts: 182
Default How do I avoid Contractor nickel and diming me?

You can have a regular deck and work that is not perfect - wood which is not
so perfect, and get this done for a lower cost.

However if you want top quality materials - top quality work, and you hire a
perfectionist, then it can cost a pretty penny.

I would say that at the higher end, it is not uncommon to have additional
costs. Also it is not uncommon to have the customer suddenly decide to make
changes and of course pay for this. Some very rich customers will have all
work torn out and start again with a new idea and different design. Again
they pay up the wazoo for this.

I would say you get what you pay for. When you hire a perfectionist, they
will not do substandard work. But it costs big $$.


  #14   Report Post  
Posted to alt.home.repair
DK DK is offline
external usenet poster
 
Posts: 257
Default How do I avoid Contractor nickel and diming me?


what's a ledge? Do you mean a ledge or outcrop of granite or bedrock
near the surface of the ground that makes digging a foundation a
little extra work? Power tools?

I'm afraid I would never agree to such a clause in a contract. I
would expect the bidder to assume that there is always a 'ledge' and
bid accordingly.





On Tue, 26 Sep 2006 08:30:38 -0400, "jd" wrote:

You are being taken advantage of.

do you have a contract? if so, simply point to it (assuming that its
detailed enough).

I've done a ton of small jobs, including "special work" (things like odd
woods or custom made parts).

I always have contract - it protects both me and the customer. If there are
parts of the project that are impossible to set a solid price on (like
digging holes where there may be ledge, unknown shipping costs for large
custom parts that may come from far away, etc), I simply include a line that
states something like "if ledge is present, customer will either pay actual
additional costs incurred, or may, at his option, terminate the contract by
paying all outstanding charges at that time" for things like the shipping
problems, I include language like "parts needed for XXXX are being supplied
by CompanyZZZZ. Cost of shipping parts to teh job site are not included in
this quote, and are customers responsibility"...

On occasion, a customer complains about the "loopholes", but when I explain
that if I have to put a number in, it will have to be the maximum possible
cost, which the customer will then be obligated to pay, regardless of the
actual cost. Usually they are OK with it, but now and then they insist on
including an actual price. Their choice.

Thing like loading trucks, inspecting stock, etc are part of the basic bid -
its simply a part of the job. Charging extra for it is like charging extra
to go buy nails.

Any time I'm digging (no matter how little), the ledge clause goes into the
contract. once again, if a customer complains, I explain that a chunk of
ledge in the wrong spot can cost tousands of dollars to deal with. The
clause simply gives the customer the choice of continuing the job and paying
the actual costs, or stopping. I insist on having them pay the costs up to
that point for two reasons; first, simply because i have to make a living,
and second, because usually it would be discovered fairly early in the job.
Either right after demo is done or right at the begining (when new
foundations footings or whatever are being dug).

My basic premise is that if the customer is never surprised b an additional
cost, and is given the option of stopping if a large unexpected cost comes
up, they'll be happy. so far, its worked. The worst thing I've had happen
was a customer that had started a job (major deck/sunporch enlargement), and
we did hit a large area of ledge. We spent a few hours trying to work around
it (looking for other ways to place the footings), and when it just wasn't
possible, the customer decided to stop the job because they could not afford
the extra work. We chatted for a bit, and came up with a fairly low-cost way
to close things down for a year (so that there wouldn't be weather damage to
the exposed parts), and scheduled the job to continue the following year.
Not ideal, but it gave the client time to save up for the ledge removal,
caused a minor additional expense (we both gave a bit in the closing up and
re-opening part of the work), and meant that the client had a year without a
porch or deck. The following spring, they were the first job I did, and they
are still one of the best references I have.
They weren't happy that they had to go so long without their porch, and they
weren't happy about paying to have the ledge removed, but they weren't
surprised (we had discussed the possibility of ledge during the contract
phase), and they were happy that I was willing to work with them to close
the house back up as economically as possible, and in a way that would make
it easy to continue the job later. When it became clear that we were going
to have to find a work around to the situation, we both sat down and talked
about our options, and came up with a solution that worked - not perfect or
ideal, but it did work.....

--JD



" wrote in message
oups.com...
I found a local contractor to build a deck for me out of a imported
exotic hardwood (ipe). The project involved removing an existing deck
and rebuilding it. He did seem to be very knowledgeable and
enthusiastic. He quoted me a price (labor only) approximately 70%
more than two other contractors because he did his research and knew
that this wood is difficult to work with. The suppliers of the wood
estimate labor costs approximately 50% higher than using a traditional
deck wood, so I did not think his estimate was totally unreasonable.
The other two contractors have never heard of ipe wood, and I believe
simply ignorant of the difficulty in working with this EXTREMELY hard
dense wood (all screws and holes must be predrilled, and cannot hammer
through this wood). I accepted his bid without haggling, and I told
him that I expected that he was a master craftsman, and I expected that
he is an expert, and that is why I would pay him top dollar. He
quoted me a time estimate of 2 1/2 weeks to complete the deck.

Since beginning he has taken every opportunity to charge me extra labor
costs. Firstly, on demolition of the existing deck, he said that the
existing deck posts were deeper than anticipated, and so he charged me
rental for a larger jack hammer than he had, and charged me $650 extra
($65 an hour for extra 10 hours). I told him that I was not pleased,
but agreed for him to proceed. I do not know exactly how much EXTRA
time (beyond what he expected and should have been covered by the
original bid) but I seriously doubt it was 10 hours.

Then when I discovered that the wood supplier would not unload the
delivery truck, he said he wanted to unload it, and that he needed a
fork-lift (approximately 6000 lbs total weight of wood). The
supplier told me that there were about 5 batches of wood. I told him
to go ahead, and that I could not imagine that it would take more than
an hour to unload the truck using a fork-lift. Well after this
occured, he charged me 2 1/2 hrs labor (this time he charged $75 an
hour) time. When I said that I could not understand how it could have
taken 2 1/2 hours to unload with a fork-lift, he said he examined each
piece of wood, and that is why it took that length of time. When I
complained, he asked if I wanted him to just accept lousy wood, I told
him I felt that examining the building materials should included in his
original labor bid. But I went ahead and paid him.

He has worked on the project a total of 4 days, and the posts, and
joists are all up and now he says he will be finished within a week.

I find it very f**ked-up, that he takes every opportunity to charge me
additional labor costs when he says a particular step is taking longer
than anticipated, but when and if he finishes the project in less than
half the time he said it would, why should not I request a 50% return
of the labor costs he bid. Obviously, the overall labor time is way
less than he proposed to me, why am paying for extra labor costs. Do
all contractors pay this game, and how can I prevent this in the future?



  #15   Report Post  
Posted to alt.home.repair
external usenet poster
 
Posts: 1,313
Default How do I avoid Contractor nickel and diming me?


cost, and is given the option of stopping if a large unexpected cost comes
up, they'll be happy. so far, its worked. The worst thing I've had happen
was a customer that had started a job (major deck/sunporch enlargement), and
we did hit a large area of ledge. We spent a few hours trying to work around
it (looking for other ways to place the footings), and when it just wasn't
possible, the customer decided to stop the job because they could not afford



I'm a little confused. If you have solid ledge, what
do you need footings for? Why can't you just drill
holes and epoxy post-bases right to the planet?

--goedjn
Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT +1. The time now is 11:36 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"