Also, if there is adequate access to the site, hire a crane operator and a
couple of friends. You can set the trusses in less than an hour on a
building that size with a crane there to lift them up. A crane for an hour
plus drive time may only run $300 or so. Have the gable ends sheeted before
the crane arrives, and have some lineal tubafor on hand to brace the trusses
(rat runs) For the inital bracing, i usually cut some tubafor blocks 25
1/2" long if the trusses are 24 O.C.
and nail these from truss to truss as they are being set. They will hold
until the rat runs are installed and sheeting put on. Hope this
elps. --dave
"Wilson Lamb" wrote in message
nk.net...
Visit the truss company and discuss the job. Before taking the order,
they
will produce a drawing and have you sign it, to cover their ass. Get
plenty
of overhang. It doesn't cost much and will help keep the building from
rotting.
The designer will be happy to discuss all options. Storage is easy, but
usually takes a little beefing up, especially of the lower chord.
GET THREE PRICES, if possible. I see up to 25% variation around here.
Wilson
"Bullwinkle J. Moose" wrote in message
news:yPSCd.853149$8_6.482306@attbi_s04...
I know you guys have used trusses before so question is, what's the
proper
way to get the length? What I'm meaning to say is, are the overhangs
included in the measurement? Outside wall to outside wall is 20 feet.
Would
I order a 20 foot truss or would it be a 22 foot truss. The extra 2 feet
is
a foot overhang on each side. Snow and ice has recently collapsed my dads
garage roof. I've never used trusses before. Thanks.
|