View Single Post
  #19   Report Post  
Dave Plowman
 
Posts: n/a
Default Earth bonding queries

In article ,
Steven Briggs wrote:
To quote from "Commentary on the IEE Wiring Regulations" (Paul Cook)
"There is particular requirement that the supplementary bonding itself
be carried out within the bathroom, simply that the parts themselves be
supplementary bonded. Supplementary bonding maybe installed underneath
floorboards, above ceilings or in an adjacent airing cupboard, as long
as it is accessible for inspection"


"Use can also be made of copper pipes as the supplementary bonding
conductor if the joints are electrically continuous"


Now that's interesting, as mine certainly is. So in theory, all the pipes
might be bonded to the bath and whatever by just one set of clamps?

--
*The statement below is true.

Dave Plowman London SW 12
RIP Acorn