ted posted for all of us...
Answers in-line
We are pouring 3 ft concrete footings 2 feet deep so 3'x3'x2'deep footings
Why so wide and not very deep? Did you get a plan for this? Any rebar? 18 cu
feet will = .67 cu yd. Means hand mixing. Ready mix trucks usually have a
minimum so you have any more to pour?
I was wondering the dry time would be approximately before we can put load bearing posts on the footing
7 days and make sure to cure it properly.
This is for opening a load bearing wall to the kitchen
Ok, you got permits?
any ideas as to when the footings should have aout 3000psi strength?
28 days
--