Don Foreman wrote:
On Sun, 06 Mar 2011 14:06:42 -0800, Rich Grise
wrote:
Pete C. wrote:
Rich Grise wrote:
Don Foreman wrote:
On Sat, 5 Mar 2011 12:38:30 -0500, "Phil Kangas"
How would you move a large barn?
Check out these guys!
http://www.youtube.com/watch?v=o83W0gj_CRE
That is downright inspiring!
17,000 lb, 334 lifters = less than 50 lb per lifter on average. Gives
real meaning to the old saw "many hands make light work".
If a man can build a garage in 60 days, can 60 men build a garage in a
day? ;-)
If it takes one man 60 days to build a garage, he needs some remedial
construction classes. Building an average two car free standing garage
solo should not take more than a week of full days of work.
Okay, seven then. Can seven men throw one up in a day?
If 24 guys poured the slab, would it reach full cure strength in a
day?
No, but it only takes a couple days to reach sufficient strength to
continue construction. This is a garage we're talking about, not a
skyscraper, so 28 day compressive strength is not an issue. While the
slab is curing, it is entirely possible to continue framing out the
walls of such a garage so that can be tipped up and secured when the
concrete has sufficiently set. A week is very feasible.