On 5/5/2010 3:23 PM, SonomaProducts.com wrote:
Question one might be "is there a better forum for this question?"
Need to understand sequencing of installation of new doors and new
hardwood floor in existing home.
When your house was built, the doors were installed first, then the
flooring is done prior to trim out.
There are many reasons for that, Mike hit on most of them.
Do your doors first, floors afterward.
--
www.e-woodshop.net
Last update: 4/15/2010
KarlC@ (the obvious)