In article ,
Hugo Nebula abuse@localhost writes:

Building Control then have up to six weeks to issue a Section 81
notice, giving the conditions relating to the demolition that the
applicant must comply with, such as making sure that the site is
hoarded, any adjoining buildings are made watertight, etc. You should
receive a copy of this notice if you are an adjoining owner (ie, your
building or land is physically attached to the demolition site) when
it's issued to the applicant. Copies are also sent to the Health &
Safety Exec so they can control the demolition, and to statutory
undertakers.


So they can be on hand to come and scrape up squashed demolition workers?

--