Default A story unfolds Aaaaaaaaaagh!

I'm having Double glazing put in on this property I'm renting,the council
are footing the bill.
However the landlord has an property managment agent to manage the running
of the property.

In june of last year 2007 I handed the form into the property managment
agents in which I had to wait two weeks for any development as the surveyor
was on holiday.

November came and no contact was made with me over the what was going on so
contacted the surveyor and he informed me that the landlord gave the consent
to have the work done and we arranged a time for him to come out and inspect
the windows to see what needed doing.

He came and went,december the council came out to inspect the same thing and
that was that.

Got the bloke from the council that came out in december knocking on me door
this morning and was informed that all the proposed work was passed and he
was still waiting on the form that got passed into the agents in June of
2007 as this was a signed agreement and the work could not go ahead until he
had that form on his desk

Aggggggggggggh! I cannot believe that this piece of paper brings everything
to a standstill just because some council worker has not bothered to inform
the surveyor that he has not recieved a form back or the surveyor has not
informed the landlord to send it back to him or the council.

Seven months and not even past the bloody gate.

Anyone got a gun to lend me.