Goodbye 100w, 75w Incandescent Lamps
In article , CJT wrote in part:
I suggest that the two are similar in magnitude. After all, there
haven't been all that many projects blocked -- just delayed. But the
corporate follies will be with us for decades in many cases.
Delays of projects are expensive. One big example: A lot of nuclear
plants had construction drawn out by delays in the 1970's when interest
rates were at high levels, and after that the antinukers blamed the nukes
for their electricity being expensive.
- Don Klipstein )
|