Unfused connection
On Apr 23, 11:10 pm, Boden wrote:
Is it required that I run rigid conduit inside a building from the meter
base to the entrance panel? The run from the meter to the entrance
panel will be at least 20 feet. Locating this outside the building
would be very difficult.
Thanks,
Boden
Check with your power company and your building inspection department.
In some localities, like ours, conduit is required and distance from
the meter base to the service panel is limited to 5' or less. HTH