Default full plans / building notice at same time ?

In an earlier contribution to this discussion,
wrote:

Any problems with full plans / building notice at same time ?
Will the BCO get confused and have to take a month's bed rest ?
Cheers,
Simon.


What's the point?

You would normally use a building notice when you need to get on with the
work straight away, and can negotiate with the BCO as you go along. You
would use full plans when you want to be *sure* that your total design is
compliant *before* starting work. Approval takes a finite time (maybe 3
weeks?) after submitting the plans.

What are you hoping to achieve by using both methods at the same time?
--
Cheers,
Roger