I need to know what my best underlayment option is for ceramic tile based on
MY PERSONAL CRITERIA. Please help. I have tried to outline all the
information below. If some going back and forth is required I will be glad
to clarify or answer any questions you might have.

A special note:

The Tile Council of America doesn't have my personal criteria in mind. The
Tile Council of America has emphasis on quality beyond economic sanity. I
have to run my business as a business so I am seeking your help instead of
just doing what the Tile Council of America tells me.

A made up example: = this example is fictional

Tile Council of America would never suggest tiling once knowing it will
crack in 10 years. Even if tiling over the cracked layer again will produce
a lasting product. (The first layer of tile in addition to the underlayment
will prevent the second layer from ever cracking.) If the money saved from
the corner cutting in the first tiling invested for 10 years would more than
pay for the second tiling then the Tile Council of America isn't making
economic sense.

Economics:

If I am not looking for "the best" tile job what am I looking for? I am NOT
LOOKING FOR THE CHEAPEST JOB. I am looking for the most economical tile job
IN THE LONG RUN. For instance, I wouldn't want to install tile only to have
to replace it in three years. I would also not want to pay an extra 10% to
extend the life of the tile from 50 to 300 years because I'll be dead. If I
can cut the cost of the job by $1000.00 but I'll have to spend $30.00 fixing
popped tiles every year it is worth it. If I cut the cost by $1000.00 but I
have to spend $250.00 replacing cracked and popped tile every year it is
not.

The Goal:

I would like to tile the first floor of several rental properties to reduce
future costs.

Facts:

The tile:

Type: Ceramic

Size: 6x6 and 12x12

Amount: roughly 5000 sq. ft.

Note: I already purchased the tile, in bulk. It cannot be returned.

The houses:

Brick Row homes

Built in late 1800's

Floor spans: 12-15 ft

Joist spacing: 16 inches on center

Joist size: 2x10 (some 2x8)

Basement present: Yes, on all

Current floor: painted and unpainted floor boards 1x6 and 1x4 (3/4" thick)

Labor costs:

Low

First question:

How do I determine the amount of weight the floor will safely support?

Second question:

What underlayment should I use? Below are several choices under
consideration.

PLAN A

=================

Use 1/2" wonderboard and thinset

Cost: $3300.00 + latex modifed thinset

PLAN B

=================

Put down 15 lb felt and pour as thick a mud bed as the floor will support.
If metal lath is absolutely required that would probably price the mud bed
option out. If no metal lath is required this might be the cheapest option.
A 1 part Portland, 6 part sand mud bed costs $60 per cubic yard. If I added
$10 worth of fiber reinforcement per yard a 2 inch thick mud bed would still
cost less than 45 cents per square foot or $2250.00 for the whole project. A
1 1/4 inch mud bed would cost about $1400. The problem is that I think it
might be too heavy and I don't know if I could increase the strength of the
floors for the money I would be saving over Wonderboard. I also don't know
if fiber cement is going to allow me to not use steel reinforcement and
lath.

PLAN C

==================

Pour a thin layer of "high performance" mortar. If I could match the
properties of Wonderboard somehow that would be ideal. Does anyone know what
I need to do to make a similar product? How many parts sand / lime / cement?
Is that fiberglass matting and how could I obtain it? Does Wonderboard use
some special magical ingredient that I do not know about? At $430.00 per
cubic yard Wonderboard is phenomenally expensive concrete. Sand is only $30
per cubic yard. Pure Portland cement is about $175 per cubic yard. That
leaves a lot of extra money to purchase fiberglass matting and still come
out ahead. I also like this option over Wonderboard because some rooms on t
he first floor are 1/8th inch higher or lower than ajoining rooms and could
easily be "made level" during the process.

PLAN D

==================

Put down plywood / OSB over the floorboards and then tile directly onto the
plywood. The cost, of course, depends on how thick a sheet of plywood used.
I imagine the cost is probably slightly less than Wonderboard. Since I have
reason to believe the floor may be exposed to moisture from time to time I
would opt for Wonderboard

PLAN E

==================

Put down 1 / 4 inch Luan and tile over. Cost, around $1720. This is the
cheapest option other than a mud bed which might weigh too much for the
floor.

A final note:

Please don't say: "do this, do that". Explain WHY and where possible use
numbers.

Thank you all very much for your help,

William


  #2   Report Post  
Hayduke
 
Posts: n/a
Default

"William Deans" wrote in message news:1100064687.cMB+c5J2jfVEF9qgNO/PEw@teranews...
Greetings,

I need to know what my best underlayment option is for ceramic tile based on
MY PERSONAL CRITERIA. Please help. I have tried to outline all the
information below. If some going back and forth is required I will be glad
to clarify or answer any questions you might have.

A special note:

The Tile Council of America doesn't have my personal criteria in mind. The
Tile Council of America has emphasis on quality beyond economic sanity. I
have to run my business as a business so I am seeking your help instead of
just doing what the Tile Council of America tells me.

A made up example: = this example is fictional

Tile Council of America would never suggest tiling once knowing it will
crack in 10 years. Even if tiling over the cracked layer again will produce
a lasting product. (The first layer of tile in addition to the underlayment
will prevent the second layer from ever cracking.) If the money saved from
the corner cutting in the first tiling invested for 10 years would more than
pay for the second tiling then the Tile Council of America isn't making
economic sense.

Economics:

If I am not looking for "the best" tile job what am I looking for? I am NOT
LOOKING FOR THE CHEAPEST JOB. I am looking for the most economical tile job
IN THE LONG RUN. For instance, I wouldn't want to install tile only to have
to replace it in three years. I would also not want to pay an extra 10% to
extend the life of the tile from 50 to 300 years because I'll be dead. If I
can cut the cost of the job by $1000.00 but I'll have to spend $30.00 fixing
popped tiles every year it is worth it. If I cut the cost by $1000.00 but I
have to spend $250.00 replacing cracked and popped tile every year it is
not.

The Goal:

I would like to tile the first floor of several rental properties to reduce
future costs.

Facts:

The tile:

Type: Ceramic

Size: 6x6 and 12x12

Amount: roughly 5000 sq. ft.

Note: I already purchased the tile, in bulk. It cannot be returned.

The houses:

Brick Row homes

Built in late 1800's

Floor spans: 12-15 ft

Joist spacing: 16 inches on center

Joist size: 2x10 (some 2x8)

Basement present: Yes, on all

Current floor: painted and unpainted floor boards 1x6 and 1x4 (3/4" thick)

Labor costs:

Low

First question:

How do I determine the amount of weight the floor will safely support?

Second question:

What underlayment should I use? Below are several choices under
consideration.

PLAN A

=================

Use 1/2" wonderboard and thinset

Cost: $3300.00 + latex modifed thinset

PLAN B

=================

Put down 15 lb felt and pour as thick a mud bed as the floor will support.
If metal lath is absolutely required that would probably price the mud bed
option out. If no metal lath is required this might be the cheapest option.
A 1 part Portland, 6 part sand mud bed costs $60 per cubic yard. If I added
$10 worth of fiber reinforcement per yard a 2 inch thick mud bed would still
cost less than 45 cents per square foot or $2250.00 for the whole project. A
1 1/4 inch mud bed would cost about $1400. The problem is that I think it
might be too heavy and I don't know if I could increase the strength of the
floors for the money I would be saving over Wonderboard. I also don't know
if fiber cement is going to allow me to not use steel reinforcement and
lath.

PLAN C

==================

Pour a thin layer of "high performance" mortar. If I could match the
properties of Wonderboard somehow that would be ideal. Does anyone know what
I need to do to make a similar product? How many parts sand / lime / cement?
Is that fiberglass matting and how could I obtain it? Does Wonderboard use
some special magical ingredient that I do not know about? At $430.00 per
cubic yard Wonderboard is phenomenally expensive concrete. Sand is only $30
per cubic yard. Pure Portland cement is about $175 per cubic yard. That
leaves a lot of extra money to purchase fiberglass matting and still come
out ahead. I also like this option over Wonderboard because some rooms on t
he first floor are 1/8th inch higher or lower than ajoining rooms and could
easily be "made level" during the process.

PLAN D

==================

Put down plywood / OSB over the floorboards and then tile directly onto the
plywood. The cost, of course, depends on how thick a sheet of plywood used.
I imagine the cost is probably slightly less than Wonderboard. Since I have
reason to believe the floor may be exposed to moisture from time to time I
would opt for Wonderboard

PLAN E

==================

Put down 1 / 4 inch Luan and tile over. Cost, around $1720. This is the
cheapest option other than a mud bed which might weigh too much for the
floor.

A final note:

Please don't say: "do this, do that". Explain WHY and where possible use
numbers.

Thank you all very much for your help,

William




William,

Here is my opinion. And just for the record, I USED to lay tile and
did so for just a couple years. Most of my tiling experience was new
construction but did do a few remodels as well.

OK Here goes....

Situation:
It doesn't sound to me like the floor/area to be tiled is too
expansive and sounds like it should be fairly sturdy "Floor spans:
12-15 ft; Joist spacing: 16 inches on center; Joist size: 2x10 (some
2x8); Basement present: Yes, on all; current floor: painted and
unpainted floor boards 1x6 and 1x4 (3/4" thick)". Though this is hard
to say with any certainty just by reading a few specs.

Here is what I might consider:

Plan A: I have used wonderboard before to tile over subfloor and have
used it on stairways that were somewhat rickety. I layed the
wonderboard onto a spread of latex added thinset and then screwed it
down. Used thinset with latex to set 12x12 tiles and in 4 years of
frequent traffic, no cracks at all.
I think this would be a good option because, though more expensive
materials, your labor costs would be lower because I think it would
take less time. (though this may not be the case depending on your
experience and if you are working alone. A person can spread mortar
pretty fast and with a helper, could make quick work of this type of
installation.)
http://www.ontariotile.com/cbuwonder.html

Plan B: Though 'mudding' does produce a pretty strong/hard surface,
I'm not so sure you could get away with not using metal in it for
stregnth. Also, I think this would take alot longer, therefore
increasing costs of labor by having to prep, mix, haul, spread,
screed, etc. This also requires a good bit of skill to do preoperly.
I'm not sure if using fiber cement is enough to not use metal, like
you said.

Plan C: I don;t know the 'chemical/or mix' properties of wonderboard
but I do know that it does have a fiberglass mesh on both sides for
stregnth. You pay more for convenience. Buy it, deliver it, install
it. no mess, no mix, etc. As for the 1/8 difference in floor height.
There are 2 thicknesses of wonderboard, 1/2 and 1/4 and you might be
able lay wonderboard on a thicker spread of mortar where the floor is
higher using a deeper trowel to spread.

Plan D: Be careful using OSB. OSB isn't made for wet applications
and may separate with the wet thinset and therefore may not provide a
good secure bond. If you suspect any moisture problems, I would not
consider this at all.

Plan E: Just read the link.........
http://www.c-cure.com/servref/techsupp/115.htm

Again, It is hard to know exactly what your up against but these are
my opinions based on what I got from your descriptions.

I hope this helps.

Doug
  #3   Report Post  
Hayduke
 
Posts: n/a
Default

"William Deans" wrote in message news:1100064687.cMB+c5J2jfVEF9qgNO/PEw@teranews...
Greetings,

I need to know what my best underlayment option is for ceramic tile based on
MY PERSONAL CRITERIA. Please help. I have tried to outline all the
information below. If some going back and forth is required I will be glad
to clarify or answer any questions you might have.

A special note:

The Tile Council of America doesn't have my personal criteria in mind. The
Tile Council of America has emphasis on quality beyond economic sanity. I
have to run my business as a business so I am seeking your help instead of
just doing what the Tile Council of America tells me.

A made up example: = this example is fictional

Tile Council of America would never suggest tiling once knowing it will
crack in 10 years. Even if tiling over the cracked layer again will produce
a lasting product. (The first layer of tile in addition to the underlayment
will prevent the second layer from ever cracking.) If the money saved from
the corner cutting in the first tiling invested for 10 years would more than
pay for the second tiling then the Tile Council of America isn't making
economic sense.

Economics:

If I am not looking for "the best" tile job what am I looking for? I am NOT
LOOKING FOR THE CHEAPEST JOB. I am looking for the most economical tile job
IN THE LONG RUN. For instance, I wouldn't want to install tile only to have
to replace it in three years. I would also not want to pay an extra 10% to
extend the life of the tile from 50 to 300 years because I'll be dead. If I
can cut the cost of the job by $1000.00 but I'll have to spend $30.00 fixing
popped tiles every year it is worth it. If I cut the cost by $1000.00 but I
have to spend $250.00 replacing cracked and popped tile every year it is
not.

The Goal:

I would like to tile the first floor of several rental properties to reduce
future costs.

Facts:

The tile:

Type: Ceramic

Size: 6x6 and 12x12

Amount: roughly 5000 sq. ft.

Note: I already purchased the tile, in bulk. It cannot be returned.

The houses:

Brick Row homes

Built in late 1800's

Floor spans: 12-15 ft

Joist spacing: 16 inches on center

Joist size: 2x10 (some 2x8)

Basement present: Yes, on all

Current floor: painted and unpainted floor boards 1x6 and 1x4 (3/4" thick)

Labor costs:

Low

First question:

How do I determine the amount of weight the floor will safely support?

Second question:

What underlayment should I use? Below are several choices under
consideration.

PLAN A

=================

Use 1/2" wonderboard and thinset

Cost: $3300.00 + latex modifed thinset

PLAN B

=================

Put down 15 lb felt and pour as thick a mud bed as the floor will support.
If metal lath is absolutely required that would probably price the mud bed
option out. If no metal lath is required this might be the cheapest option.
A 1 part Portland, 6 part sand mud bed costs $60 per cubic yard. If I added
$10 worth of fiber reinforcement per yard a 2 inch thick mud bed would still
cost less than 45 cents per square foot or $2250.00 for the whole project. A
1 1/4 inch mud bed would cost about $1400. The problem is that I think it
might be too heavy and I don't know if I could increase the strength of the
floors for the money I would be saving over Wonderboard. I also don't know
if fiber cement is going to allow me to not use steel reinforcement and
lath.

PLAN C

==================

Pour a thin layer of "high performance" mortar. If I could match the
properties of Wonderboard somehow that would be ideal. Does anyone know what
I need to do to make a similar product? How many parts sand / lime / cement?
Is that fiberglass matting and how could I obtain it? Does Wonderboard use
some special magical ingredient that I do not know about? At $430.00 per
cubic yard Wonderboard is phenomenally expensive concrete. Sand is only $30
per cubic yard. Pure Portland cement is about $175 per cubic yard. That
leaves a lot of extra money to purchase fiberglass matting and still come
out ahead. I also like this option over Wonderboard because some rooms on t
he first floor are 1/8th inch higher or lower than ajoining rooms and could
easily be "made level" during the process.

PLAN D

==================

Put down plywood / OSB over the floorboards and then tile directly onto the
plywood. The cost, of course, depends on how thick a sheet of plywood used.
I imagine the cost is probably slightly less than Wonderboard. Since I have
reason to believe the floor may be exposed to moisture from time to time I
would opt for Wonderboard

PLAN E

==================

Put down 1 / 4 inch Luan and tile over. Cost, around $1720. This is the
cheapest option other than a mud bed which might weigh too much for the
floor.

A final note:

Please don't say: "do this, do that". Explain WHY and where possible use
numbers.

Thank you all very much for your help,

William


William,

You can also use an addative to the grout and that can help prevent
cracks as well. Your local tile distributor/shop should have
different additives you can purchase.

Doug
  #4   Report Post  
Charles Spitzer
 
Posts: n/a
Default


"William Deans" wrote in message
news:1100064687.cMB+c5J2jfVEF9qgNO/PEw@teranews...
Greetings,

I need to know what my best underlayment option is for ceramic tile based
on
MY PERSONAL CRITERIA. Please help. I have tried to outline all the
information below. If some going back and forth is required I will be glad
to clarify or answer any questions you might have.

A special note:

The Tile Council of America doesn't have my personal criteria in mind. The
Tile Council of America has emphasis on quality beyond economic sanity. I
have to run my business as a business so I am seeking your help instead of
just doing what the Tile Council of America tells me.

A made up example: = this example is fictional

Tile Council of America would never suggest tiling once knowing it will
crack in 10 years. Even if tiling over the cracked layer again will
produce
a lasting product. (The first layer of tile in addition to the
underlayment
will prevent the second layer from ever cracking.) If the money saved from
the corner cutting in the first tiling invested for 10 years would more
than
pay for the second tiling then the Tile Council of America isn't making
economic sense.

Economics:

If I am not looking for "the best" tile job what am I looking for? I am
NOT
LOOKING FOR THE CHEAPEST JOB. I am looking for the most economical tile
job
IN THE LONG RUN. For instance, I wouldn't want to install tile only to
have
to replace it in three years. I would also not want to pay an extra 10% to
extend the life of the tile from 50 to 300 years because I'll be dead. If
I
can cut the cost of the job by $1000.00 but I'll have to spend $30.00
fixing
popped tiles every year it is worth it. If I cut the cost by $1000.00 but
I
have to spend $250.00 replacing cracked and popped tile every year it is
not.

The Goal:

I would like to tile the first floor of several rental properties to
reduce
future costs.

Facts:

The tile:

Type: Ceramic

Size: 6x6 and 12x12

Amount: roughly 5000 sq. ft.

Note: I already purchased the tile, in bulk. It cannot be returned.

The houses:

Brick Row homes

Built in late 1800's

Floor spans: 12-15 ft

Joist spacing: 16 inches on center

Joist size: 2x10 (some 2x8)

Basement present: Yes, on all

Current floor: painted and unpainted floor boards 1x6 and 1x4 (3/4" thick)

Labor costs:

Low

First question:

How do I determine the amount of weight the floor will safely support?

Second question:

What underlayment should I use? Below are several choices under
consideration.

PLAN A

=================

Use 1/2" wonderboard and thinset

Cost: $3300.00 + latex modifed thinset


the right way to do it

PLAN B

=================

Put down 15 lb felt and pour as thick a mud bed as the floor will support.
If metal lath is absolutely required that would probably price the mud bed
option out. If no metal lath is required this might be the cheapest
option.
A 1 part Portland, 6 part sand mud bed costs $60 per cubic yard. If I
added
$10 worth of fiber reinforcement per yard a 2 inch thick mud bed would
still
cost less than 45 cents per square foot or $2250.00 for the whole project.
A
1 1/4 inch mud bed would cost about $1400. The problem is that I think it
might be too heavy and I don't know if I could increase the strength of
the
floors for the money I would be saving over Wonderboard. I also don't
know
if fiber cement is going to allow me to not use steel reinforcement and
lath.


the hard way to do it. much more labor intensive to get flat and get right.

PLAN C

==================

Pour a thin layer of "high performance" mortar. If I could match the
properties of Wonderboard somehow that would be ideal. Does anyone know
what
I need to do to make a similar product? How many parts sand / lime /
cement?
Is that fiberglass matting and how could I obtain it? Does Wonderboard use
some special magical ingredient that I do not know about? At $430.00 per
cubic yard Wonderboard is phenomenally expensive concrete. Sand is only
$30
per cubic yard. Pure Portland cement is about $175 per cubic yard. That
leaves a lot of extra money to purchase fiberglass matting and still come
out ahead. I also like this option over Wonderboard because some rooms on
t
he first floor are 1/8th inch higher or lower than ajoining rooms and
could
easily be "made level" during the process.


another hard way to do it

PLAN D

==================

Put down plywood / OSB over the floorboards and then tile directly onto
the
plywood. The cost, of course, depends on how thick a sheet of plywood
used.
I imagine the cost is probably slightly less than Wonderboard. Since I
have
reason to believe the floor may be exposed to moisture from time to time I
would opt for Wonderboard

PLAN E

==================

Put down 1 / 4 inch Luan and tile over. Cost, around $1720. This is the
cheapest option other than a mud bed which might weigh too much for the
floor.


wood is not to be used for laying tile unless you're going to use exterior,
and even in that case, you won't get a good bond using thinset. the wood
sucks the water out of the thinset too quickly and you get a crappy hold.

A final note:

Please don't say: "do this, do that". Explain WHY and where possible use
numbers.

Thank you all very much for your help,

William




  #5   Report Post  
William Deans
 
Posts: n/a
Default

Greetings,

Thanks you VERY MUCH for your input. I was worried that my request might
have been a little too "heavy" to elicit any worthwhile help. I am very
thankful for your time.

No one seems to object to the idea of me making my own "high performance mud
bed" (except it might be take extra time and prove difficult to produce a
flat surface). Everyone seemed to champion the official Wonderboard product.

I did a little research and ended up purchasing 5.40 ounce/M2 6X6 mesh/inch
white coated alkali resistant fiberglass mesh fabric. Based on my
calculations I will be able to lay a 3/4 inch mudbed of 1:1:4
(portland/lime/sand) fiber reinforced mortar with fiberglass mesh embedded
near the top and bottom for a cost of $1835 plus labor. This is $1332 less
than the cost of Wonderboard. I am gambling the extra work will be less than
$1332 in labor costs.

I now have two options:

1.. Attempt to manufacture 334 sheets of Wonderboard in my basement and
then install as regular Wonderboard
2.. Embed the fiberglass mesh within a monolithic mud bed
I would like to hire someone for $10/hour to make the Wonderboard in my
basement. If they could average a sheet every five minutes the total labor
cost would be about $280. The total savings would be $1052. This would allow
me to wet cure the 11.57 yards of underlayment in my basement for a full 30
days to ensure full strength was achieved. Any shrinkage could occur before
I installed the boards. This method would allow me to ensure their flatness.
Before making the 334 sheets I will make a test board or two and allow it to
cure for a week. This will allow me to compare it to the official
Wonderboard to ensure it isn't obviously inferior. If the board is inferior
(or seems labor intensive) I am only out the cost of the one or two boards
($10).

Thanks again,

William

Note: I still don't know what ratio of Portland / Lime / Sand to use. The
ratio above was only used for cost calculation reasons.

Legal Note: Wonderboard is obviously a trademark and I obviously cannot
produce it any more than Cannon could make a Xerox machine.



"Hayduke" wrote in message
om...
"William Deans" wrote in message

news:1100064687.cMB+c5J2jfVEF9qgNO/PEw@teranews...
Greetings,

I need to know what my best underlayment option is for ceramic tile

based on
MY PERSONAL CRITERIA. Please help. I have tried to outline all the
information below. If some going back and forth is required I will be

glad
to clarify or answer any questions you might have.

A special note:

The Tile Council of America doesn't have my personal criteria in mind.

The
Tile Council of America has emphasis on quality beyond economic sanity.

I
have to run my business as a business so I am seeking your help instead

of
just doing what the Tile Council of America tells me.

A made up example: = this example is fictional

Tile Council of America would never suggest tiling once knowing it will
crack in 10 years. Even if tiling over the cracked layer again will

produce
a lasting product. (The first layer of tile in addition to the

underlayment
will prevent the second layer from ever cracking.) If the money saved

from
the corner cutting in the first tiling invested for 10 years would more

than
pay for the second tiling then the Tile Council of America isn't making
economic sense.

Economics:

If I am not looking for "the best" tile job what am I looking for? I am

NOT
LOOKING FOR THE CHEAPEST JOB. I am looking for the most economical tile

job
IN THE LONG RUN. For instance, I wouldn't want to install tile only to

have
to replace it in three years. I would also not want to pay an extra 10%

to
extend the life of the tile from 50 to 300 years because I'll be dead.

If I
can cut the cost of the job by $1000.00 but I'll have to spend $30.00

fixing
popped tiles every year it is worth it. If I cut the cost by $1000.00

but I
have to spend $250.00 replacing cracked and popped tile every year it is
not.

The Goal:

I would like to tile the first floor of several rental properties to

reduce
future costs.

Facts:

The tile:

Type: Ceramic

Size: 6x6 and 12x12

Amount: roughly 5000 sq. ft.

Note: I already purchased the tile, in bulk. It cannot be returned.

The houses:

Brick Row homes

Built in late 1800's

Floor spans: 12-15 ft

Joist spacing: 16 inches on center

Joist size: 2x10 (some 2x8)

Basement present: Yes, on all

Current floor: painted and unpainted floor boards 1x6 and 1x4 (3/4"

thick)

Labor costs:

Low

First question:

How do I determine the amount of weight the floor will safely support?

Second question:

What underlayment should I use? Below are several choices under
consideration.

PLAN A

=================

Use 1/2" wonderboard and thinset

Cost: $3300.00 + latex modifed thinset

PLAN B

=================

Put down 15 lb felt and pour as thick a mud bed as the floor will

support.
If metal lath is absolutely required that would probably price the mud

bed
option out. If no metal lath is required this might be the cheapest

option.
A 1 part Portland, 6 part sand mud bed costs $60 per cubic yard. If I

added
$10 worth of fiber reinforcement per yard a 2 inch thick mud bed would

still
cost less than 45 cents per square foot or $2250.00 for the whole

project. A
1 1/4 inch mud bed would cost about $1400. The problem is that I think

it
might be too heavy and I don't know if I could increase the strength of

the
floors for the money I would be saving over Wonderboard. I also don't

know
if fiber cement is going to allow me to not use steel reinforcement and
lath.

PLAN C

==================

Pour a thin layer of "high performance" mortar. If I could match the
properties of Wonderboard somehow that would be ideal. Does anyone know

what
I need to do to make a similar product? How many parts sand / lime /

cement?
Is that fiberglass matting and how could I obtain it? Does Wonderboard

use
some special magical ingredient that I do not know about? At $430.00 per
cubic yard Wonderboard is phenomenally expensive concrete. Sand is only

$30
per cubic yard. Pure Portland cement is about $175 per cubic yard. That
leaves a lot of extra money to purchase fiberglass matting and still

come
out ahead. I also like this option over Wonderboard because some rooms

on t
he first floor are 1/8th inch higher or lower than ajoining rooms and

could
easily be "made level" during the process.

PLAN D

==================

Put down plywood / OSB over the floorboards and then tile directly onto

the
plywood. The cost, of course, depends on how thick a sheet of plywood

used.
I imagine the cost is probably slightly less than Wonderboard. Since I

have
reason to believe the floor may be exposed to moisture from time to time

I
would opt for Wonderboard

PLAN E

==================

Put down 1 / 4 inch Luan and tile over. Cost, around $1720. This is the
cheapest option other than a mud bed which might weigh too much for the
floor.

A final note:

Please don't say: "do this, do that". Explain WHY and where possible use
numbers.

Thank you all very much for your help,

William




William,

Here is my opinion. And just for the record, I USED to lay tile and
did so for just a couple years. Most of my tiling experience was new
construction but did do a few remodels as well.

OK Here goes....

Situation:
It doesn't sound to me like the floor/area to be tiled is too
expansive and sounds like it should be fairly sturdy "Floor spans:
12-15 ft; Joist spacing: 16 inches on center; Joist size: 2x10 (some
2x8); Basement present: Yes, on all; current floor: painted and
unpainted floor boards 1x6 and 1x4 (3/4" thick)". Though this is hard
to say with any certainty just by reading a few specs.

Here is what I might consider:

Plan A: I have used wonderboard before to tile over subfloor and have
used it on stairways that were somewhat rickety. I layed the
wonderboard onto a spread of latex added thinset and then screwed it
down. Used thinset with latex to set 12x12 tiles and in 4 years of
frequent traffic, no cracks at all.
I think this would be a good option because, though more expensive
materials, your labor costs would be lower because I think it would
take less time. (though this may not be the case depending on your
experience and if you are working alone. A person can spread mortar
pretty fast and with a helper, could make quick work of this type of
installation.)
http://www.ontariotile.com/cbuwonder.html

Plan B: Though 'mudding' does produce a pretty strong/hard surface,
I'm not so sure you could get away with not using metal in it for
stregnth. Also, I think this would take alot longer, therefore
increasing costs of labor by having to prep, mix, haul, spread,
screed, etc. This also requires a good bit of skill to do preoperly.
I'm not sure if using fiber cement is enough to not use metal, like
you said.

Plan C: I don;t know the 'chemical/or mix' properties of wonderboard
but I do know that it does have a fiberglass mesh on both sides for
stregnth. You pay more for convenience. Buy it, deliver it, install
it. no mess, no mix, etc. As for the 1/8 difference in floor height.
There are 2 thicknesses of wonderboard, 1/2 and 1/4 and you might be
able lay wonderboard on a thicker spread of mortar where the floor is
higher using a deeper trowel to spread.

Plan D: Be careful using OSB. OSB isn't made for wet applications
and may separate with the wet thinset and therefore may not provide a
good secure bond. If you suspect any moisture problems, I would not
consider this at all.

Plan E: Just read the link.........
http://www.c-cure.com/servref/techsupp/115.htm

Again, It is hard to know exactly what your up against but these are
my opinions based on what I got from your descriptions.

I hope this helps.

Doug





  #6   Report Post  
Hayduke
 
Posts: n/a
Default

"William Deans" wrote in message news:1100152320.VWiqj2Tg/15IRZZ0GO/zPA@teranews...
Greetings,

Thanks you VERY MUCH for your input. I was worried that my request might
have been a little too "heavy" to elicit any worthwhile help. I am very
thankful for your time.

No one seems to object to the idea of me making my own "high performance mud
bed" (except it might be take extra time and prove difficult to produce a
flat surface). Everyone seemed to champion the official Wonderboard product.

I did a little research and ended up purchasing 5.40 ounce/M2 6X6 mesh/inch
white coated alkali resistant fiberglass mesh fabric. Based on my
calculations I will be able to lay a 3/4 inch mudbed of 1:1:4
(portland/lime/sand) fiber reinforced mortar with fiberglass mesh embedded
near the top and bottom for a cost of $1835 plus labor. This is $1332 less
than the cost of Wonderboard. I am gambling the extra work will be less than
$1332 in labor costs.

I now have two options:

1.. Attempt to manufacture 334 sheets of Wonderboard in my basement and
then install as regular Wonderboard
2.. Embed the fiberglass mesh within a monolithic mud bed
I would like to hire someone for $10/hour to make the Wonderboard in my
basement. If they could average a sheet every five minutes the total labor
cost would be about $280. The total savings would be $1052. This would allow
me to wet cure the 11.57 yards of underlayment in my basement for a full 30
days to ensure full strength was achieved. Any shrinkage could occur before
I installed the boards. This method would allow me to ensure their flatness.
Before making the 334 sheets I will make a test board or two and allow it to
cure for a week. This will allow me to compare it to the official
Wonderboard to ensure it isn't obviously inferior. If the board is inferior
(or seems labor intensive) I am only out the cost of the one or two boards
($10).

Thanks again,

William

Note: I still don't know what ratio of Portland / Lime / Sand to use. The
ratio above was only used for cost calculation reasons.

Legal Note: Wonderboard is obviously a trademark and I obviously cannot
produce it any more than Cannon could make a Xerox machine.

Wow,


You are more ambitious than I would be. :-)

I'd be interested in hearing how it turns out, if the homemade
sheets work ok. Pictures would even be cool also(if you're feeling
that much more ambitious). I'm just curious to see how they are made
and how it works out.

Good luck!

Doug
Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
AC Advice Needed! unix-freak Home Ownership 27 June 14th 04 03:53 PM
No fee needed for extra principal payments Ablang Home Ownership 0 November 18th 03 02:08 AM
Tiling Shower Area - adhesive spreading and tile cutting problems JohnB UK diy 7 July 20th 03 10:43 AM
Tiling Guides -any recommendations ? John Schmitt UK diy 5 July 14th 03 08:47 AM


All times are GMT +1. The time now is 03:23 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"