DIYbanter

DIYbanter (https://www.diybanter.com/)
-   Home Repair (https://www.diybanter.com/home-repair/)
-   -   conduit question for garage (https://www.diybanter.com/home-repair/179927-conduit-question-garage.html)

Chris Friesen October 21st 06 01:28 AM

conduit question for garage
 

I'm purchasing a house with an attached garage, and will be adding a
subpanel for use as a shop. The garage is already insulated and
drywalled, so I'll be running conduit (most likely EMT).

The most-filled run will have three 20A 120V circuits for outlets wired
with #12, and 2 30A circuits for 240V wired with #10. (One 240V for the
dust collector, and one for everything else.)

I'm currently planning to run a single #10 ground wire (bare or green)
to ground everything on this run. I think this meets code, but I'd like
confirmation.

Assuming the above is okay, I'll have 11 wires in that conduit. Given
that I'm allowed 11 #10 wires in a 3/4" conduit, does that sound like a
reasonable conduit fill? Max spacing between conduit openings will be
about 10 ft.

Since this is a one-man shop I'll only ever be using two tools at once,
maybe three if someone is helping. I'm working on the assumption that
my load diversity is enough that I can use the 70% ampacity derate for
10 conductors. Is this reasonable, or do I have to go down to the 50%?
Should I go with two 1/2" conduits instead of a single 3/4"?

Finally, what's the best way to pull this given that the various wires
are going to different places, and one of the 240V circuits is going
right to the end? Do I pull one section at a time with all the wires
for that section?

Thanks,

Chris

James \Cubby\ Culbertson October 21st 06 02:54 AM

conduit question for garage
 

"Chris Friesen" wrote in message
...

I'm purchasing a house with an attached garage, and will be adding a
subpanel for use as a shop. The garage is already insulated and
drywalled, so I'll be running conduit (most likely EMT).

The most-filled run will have three 20A 120V circuits for outlets wired
with #12, and 2 30A circuits for 240V wired with #10. (One 240V for the
dust collector, and one for everything else.)

I'm currently planning to run a single #10 ground wire (bare or green) to
ground everything on this run. I think this meets code, but I'd like
confirmation.

Assuming the above is okay, I'll have 11 wires in that conduit. Given
that I'm allowed 11 #10 wires in a 3/4" conduit, does that sound like a
reasonable conduit fill? Max spacing between conduit openings will be
about 10 ft.

Since this is a one-man shop I'll only ever be using two tools at once,
maybe three if someone is helping. I'm working on the assumption that my
load diversity is enough that I can use the 70% ampacity derate for 10
conductors. Is this reasonable, or do I have to go down to the 50%?
Should I go with two 1/2" conduits instead of a single 3/4"?

Finally, what's the best way to pull this given that the various wires are
going to different places, and one of the 240V circuits is going right to
the end? Do I pull one section at a time with all the wires for that
section?

Thanks,

Chris


First off, I'm not an electrician. The specifics of conduit fill and such
I would personally refer to the NEC codebook to verify. That being said,
your wire sizes look ok to me. On the conduit, the fill may be fine but
you'll find that pulling 11 wires through one 3/4" will be very tough unless
all you have is a purely straight run. I would recommend at least 1" or
break it up into two 1/2 or even 3/4 runs. As for pulling to various
locations, I've found that you want to pull all your wires in at once and
not try to finagle another set in after others have been pulled. I assume
you'll be installing junction boxes somewhere along the run (keeping in
mind you are limited as to how much bend you can have in the line without a
box or other pull access....360 degrees if I remember correctly) so pull to
the J-Box, route what you need out of the bundle then continue pulling the
rest of the wires to the next J-Box. Not sure if this helps or confuses
but good luck with it!
Cheers,
cc




Tazz October 21st 06 03:30 AM

conduit question for garage
 

http://www.lanshack.com/DesigningConduitRuns.aspx


this wll help.

You dont mention if your 120v circuits wil be sharing neutrals.
I am guessing it wont from the desrption.
Also remember there is a derate for having that many current carrying
conductors in a raceway

Insulation is factor.

40% FILL



On Fri, 20 Oct 2006 18:28:30 -0600, Chris Friesen
wrote:


I'm purchasing a house with an attached garage, and will be adding a
subpanel for use as a shop. The garage is already insulated and
drywalled, so I'll be running conduit (most likely EMT).

The most-filled run will have three 20A 120V circuits for outlets wired
with #12, and 2 30A circuits for 240V wired with #10. (One 240V for the
dust collector, and one for everything else.)

I'm currently planning to run a single #10 ground wire (bare or green)
to ground everything on this run. I think this meets code, but I'd like
confirmation.

Assuming the above is okay, I'll have 11 wires in that conduit. Given
that I'm allowed 11 #10 wires in a 3/4" conduit, does that sound like a
reasonable conduit fill? Max spacing between conduit openings will be
about 10 ft.

Since this is a one-man shop I'll only ever be using two tools at once,
maybe three if someone is helping. I'm working on the assumption that
my load diversity is enough that I can use the 70% ampacity derate for
10 conductors. Is this reasonable, or do I have to go down to the 50%?
Should I go with two 1/2" conduits instead of a single 3/4"?

Finally, what's the best way to pull this given that the various wires
are going to different places, and one of the 240V circuits is going
right to the end? Do I pull one section at a time with all the wires
for that section?

Thanks,

Chris


Terry October 21st 06 04:36 AM

conduit question for garage
 
On Fri, 20 Oct 2006 18:28:30 -0600, Chris Friesen
wrote:


I'm purchasing a house with an attached garage, and will be adding a
subpanel for use as a shop. The garage is already insulated and
drywalled, so I'll be running conduit (most likely EMT).

The most-filled run will have three 20A 120V circuits for outlets wired
with #12, and 2 30A circuits for 240V wired with #10. (One 240V for the
dust collector, and one for everything else.)

I'm currently planning to run a single #10 ground wire (bare or green)
to ground everything on this run. I think this meets code, but I'd like
confirmation.

Assuming the above is okay, I'll have 11 wires in that conduit. Given
that I'm allowed 11 #10 wires in a 3/4" conduit, does that sound like a
reasonable conduit fill? Max spacing between conduit openings will be
about 10 ft.

Since this is a one-man shop I'll only ever be using two tools at once,
maybe three if someone is helping. I'm working on the assumption that
my load diversity is enough that I can use the 70% ampacity derate for
10 conductors. Is this reasonable, or do I have to go down to the 50%?
Should I go with two 1/2" conduits instead of a single 3/4"?

Finally, what's the best way to pull this given that the various wires
are going to different places, and one of the 240V circuits is going
right to the end? Do I pull one section at a time with all the wires
for that section?

Thanks,

Chris


You should ask this again at alt.engineering.electrical. Those guys
can tell you more than you want to know over there. :)

BobK207 October 21st 06 04:40 AM

conduit question for garage
 

Chris Friesen wrote:
I'm purchasing a house with an attached garage, and will be adding a
subpanel for use as a shop. The garage is already insulated and
drywalled, so I'll be running conduit (most likely EMT).

The most-filled run will have three 20A 120V circuits for outlets wired
with #12, and 2 30A circuits for 240V wired with #10. (One 240V for the
dust collector, and one for everything else.)

I'm currently planning to run a single #10 ground wire (bare or green)
to ground everything on this run. I think this meets code, but I'd like
confirmation.

Assuming the above is okay, I'll have 11 wires in that conduit. Given
that I'm allowed 11 #10 wires in a 3/4" conduit, does that sound like a
reasonable conduit fill? Max spacing between conduit openings will be
about 10 ft.

Since this is a one-man shop I'll only ever be using two tools at once,
maybe three if someone is helping. I'm working on the assumption that
my load diversity is enough that I can use the 70% ampacity derate for
10 conductors. Is this reasonable, or do I have to go down to the 50%?
Should I go with two 1/2" conduits instead of a single 3/4"?

Finally, what's the best way to pull this given that the various wires
are going to different places, and one of the 240V circuits is going
right to the end? Do I pull one section at a time with all the wires
for that section?

Thanks,

Chris



Chris-

Don't skimp on conduit size....your pulls will be easier with bigger
conduit.


Also check box fills to make sure your boxes are large enough.....don't
skimp on box sizes either.

cheers
Bob


Bud-- October 22nd 06 09:58 AM

conduit question for garage
 
Chris Friesen wrote:


I'm purchasing a house with an attached garage, and will be adding a
subpanel for use as a shop. The garage is already insulated and
drywalled, so I'll be running conduit (most likely EMT).

The most-filled run will have three 20A 120V circuits for outlets wired
with #12, and 2 30A circuits for 240V wired with #10. (One 240V for the
dust collector, and one for everything else.)

I'm currently planning to run a single #10 ground wire (bare or green)
to ground everything on this run. I think this meets code, but I'd like
confirmation.

With EMT and metal boxes you aren't required to run a ground wire, but
if you do #10 is OK.

Assuming the above is okay, I'll have 11 wires in that conduit. Given
that I'm allowed 11 #10 wires in a 3/4" conduit, does that sound like a
reasonable conduit fill? Max spacing between conduit openings will be
about 10 ft.

Using THHNs the wire fill is about 35%. Should be managable for 10 ft.
Carefully avoid wire crossovers feeding the wire into the pipe.

Since this is a one-man shop I'll only ever be using two tools at once,
maybe three if someone is helping. I'm working on the assumption that
my load diversity is enough that I can use the 70% ampacity derate for
10 conductors. Is this reasonable, or do I have to go down to the 50%?
Should I go with two 1/2" conduits instead of a single 3/4"?

You are (I assume)ignoring the ground wire to get from 11 to 10 which is
correct. At 10 wires the derate is 50% - you aren't likely to use them
all at once, but use in the future is unknown. If you ran a common
neutral for 2 of the 20A circuits the wire count would be 9 (actually
only 8 since the common neutral doesn't count) and the derate 70%. If
using THHN wire in a dry garage the "ampacity" of #12 wire is 30 amps
(but 20A max breaker). Using 70% derate the allowable current is 21A, so
they can be on a 20A breaker. The "ampacity" of a #10 THHN wire is 40A
(30A max breaker). Derated to 70% gives 28A - should be on a 25A
breaker. If the conductor count is 6 or less, the derate is 80% which
gives 32A for the #10s - can go on a 30A breaker. If the dust collector
is hardwired the rules change.

Finally, what's the best way to pull this given that the various wires
are going to different places, and one of the 240V circuits is going
right to the end? Do I pull one section at a time with all the wires
for that section?

Yes, pull all the wires in one run at the same time. Lot less mess in
the boxes if the wires unused in that box loop through without splice
(but harder to pull). I agree with Bob - box fill with that many wires
is another thing to watch.

bud--


All times are GMT +1. The time now is 08:17 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004 - 2014 DIYbanter