On Sun, 6 Feb 2011 08:06:40 -0800 (PST), Kipper at sea
wrote:

On Feb 6, 11:33*am, John wrote:
How much ahould I expect to pay for a builder to rake out and re-point
a brick wall, priced either by the square yard/metre or by the day?


By the day about £130 labour only, not including material or
scaffolding. Best to get a fixed quote for the whole lot. usually
quoted on the square yard/metre. Day rate is a no no, believe me.


Thanks Kipper. I'd be worried about a day rate for the obvious
reasons.
How many square metres should a good man be able to do in a day,
assuming all materials available on site?