Got my first quote today. $750 to tape/mud/sand all the joints and
corners. The installer said it would take about 3 days to complete.
One full day to get the first coat on everything and get the corners.
Two more days at about 2-3 hours per day to put the rest of the coats
on and finish it. Sounds reasonable to me.

I guess I'll be comparing to my other quotes when I get them in about
a week. But, how does the initial $750 sound for about 1150 square
feet? High, low, or average?

Thanks,
Kevin