UK diy (uk.d-i-y) For the discussion of all topics related to diy (do-it-yourself) in the UK. All levels of experience and proficency are welcome to join in to ask questions or offer solutions.

Reply
 
LinkBack Thread Tools Search this Thread Display Modes
  #1   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 6,938
Default Mortar setting time

I am lifting the roof on an old pig farrowing barn to accommodate a
furniture restorer.

The roof is heavy but can be moved in one piece. So far I have raised
one side on Acrows and intend to lay two courses of brick to gain the
height needed.

What is a reasonable time to wait before heavily loading fresh
brickwork? I am particularly nervous of any side thrust encountered as I
start to jack up the other side.

regards
--
Tim Lamb
  #2   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 203
Default Mortar setting time

On 29 Oct, 11:19, Tim Lamb wrote:
I am lifting the roof on an old pig farrowing barn to accommodate a
furniture restorer.

The roof is heavy but can be moved in one piece. So far I have raised
one side on Acrows and intend to lay two courses of brick to gain the
height needed.

What is a reasonable time to wait before heavily loading fresh
brickwork? I am particularly nervous of any side thrust encountered as I
start to jack up the other side.

regards
--
Tim Lamb


I would leave it 48Hrs ... 24 Hrs is no problem if a simple daed load,
but as you point out there is side thrust, and bricks not particularly
strong in that direction.

use a good 3:1 mix and suitable bricks, deep frog frettons as a
minimum, laid frog up, and fully filled ... or engineering if you have
them.
  #3   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 2,379
Default Mortar setting time


I would leave it 48Hrs ...


That seems very, very short.

Watching my brickies recently take off a couple of courses where
they'd made a mistake on a chimney stack, 2 days after they'd gone on
- they had not the slightest difficulty in such green mortar - still
very easy to clean off.

ISTR - a long, long time ago when I worked for Costain - the cure time
for mass concrete (in the Summer) was 4 weeks after the shutters came
off. Certainly when I'm using concrete, I'm surprised how easy it is
to chip for the first week or two - compared to how hard it gets
eventually.

In the current cold weather I'd plan on doing some other job - before
putting, as you say, a significant sheer load on your new courses.

You might find useful manufacturers data here - certainly their advice
on concrete I found useful:

http://www.lafargecement.co.uk/site_...ge/default.asp
  #4   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 6,938
Default Mortar setting time

In message
,
Osprey writes
On 29 Oct, 11:19, Tim Lamb wrote:
I am lifting the roof on an old pig farrowing barn to accommodate a
furniture restorer.

The roof is heavy but can be moved in one piece. So far I have raised
one side on Acrows and intend to lay two courses of brick to gain the
height needed.

What is a reasonable time to wait before heavily loading fresh
brickwork? I am particularly nervous of any side thrust encountered as I
start to jack up the other side.

regards
--
Tim Lamb


I would leave it 48Hrs ... 24 Hrs is no problem if a simple daed load,
but as you point out there is side thrust, and bricks not particularly
strong in that direction.

use a good 3:1 mix and suitable bricks, deep frog frettons as a
minimum, laid frog up, and fully filled ... or engineering if you have
them.


OK. The brickwork will be Flettons for the first course and
semi-engineering for the top. Basically because that is what I have
lying about the farm:-) I can easily wait 3 days as I also have to fit a
wider door and re-plumb the electrical conduit.

regards
--
Tim Lamb
  #5   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 6,938
Default Mortar setting time

In message
,
" writes

I would leave it 48Hrs ...


That seems very, very short.

Watching my brickies recently take off a couple of courses where
they'd made a mistake on a chimney stack, 2 days after they'd gone on
- they had not the slightest difficulty in such green mortar - still
very easy to clean off.

ISTR - a long, long time ago when I worked for Costain - the cure time
for mass concrete (in the Summer) was 4 weeks after the shutters came
off. Certainly when I'm using concrete, I'm surprised how easy it is
to chip for the first week or two - compared to how hard it gets
eventually.

In the current cold weather I'd plan on doing some other job - before
putting, as you say, a significant sheer load on your new courses.

You might find useful manufacturers data here - certainly their advice
on concrete I found useful:

http://www.lafargecement.co.uk/site_...ge/default.asp


Interesting site.

They give 2 days = 16-26 N/mm2

7 days= 27-37 N/mm2

28 days= 37-47 N/mm2

for compressive strength on CEM 1 product.

I should be able to wait 5 days and get roughly half final strength.

regards

--
Tim Lamb


  #6   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 1,158
Default Mortar setting time


"Tim Lamb" wrote in message
...
In message
,
Osprey writes
On 29 Oct, 11:19, Tim Lamb wrote:
I am lifting the roof on an old pig farrowing barn to accommodate

a
furniture restorer.

The roof is heavy but can be moved in one piece. So far I have

raised
one side on Acrows and intend to lay two courses of brick to gain

the
height needed.

What is a reasonable time to wait before heavily loading fresh
brickwork? I am particularly nervous of any side thrust

encountered as I
start to jack up the other side.

regards
--
Tim Lamb


I would leave it 48Hrs ... 24 Hrs is no problem if a simple daed

load,
but as you point out there is side thrust, and bricks not

particularly
strong in that direction.

use a good 3:1 mix and suitable bricks, deep frog frettons as a
minimum, laid frog up, and fully filled ... or engineering if you

have
them.


OK. The brickwork will be Flettons for the first course and
semi-engineering for the top. Basically because that is what I have
lying about the farm:-) I can easily wait 3 days as I also have to

fit a
wider door and re-plumb the electrical conduit.

regards
--
Tim Lamb


Tim,

Very temperature dependant: I've just laid 8 cu m of RC40 concrete and
it took two days in the current cold snap to 'not' take a finger
impression. Earlier in the year I laid a batch of the very same stuff
on a blazing hot day and we couldn't finish tamping before it set
solid (perhaps 1.5 hours from delivery)

Cement re-hydradtion (ie setting) is a chemical reaction and thus very
dependent on the temp. When it starts to go off though it is
exothermic - ie gives off heat.

AWEM


  #7   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 6,938
Default Mortar setting time

In message , Andrew Mawson
writes
Tim,

Very temperature dependant: I've just laid 8 cu m of RC40 concrete and
it took two days in the current cold snap to 'not' take a finger
impression. Earlier in the year I laid a batch of the very same stuff
on a blazing hot day and we couldn't finish tamping before it set
solid (perhaps 1.5 hours from delivery)

Cement re-hydradtion (ie setting) is a chemical reaction and thus very
dependent on the temp. When it starts to go off though it is
exothermic - ie gives off heat.


Hmm.. only a few degrees above freezing for the next few days:-(

I suppose I could make a temporary timber frame to support side 1 while
I move the acrows to side 2. Lots of extra work though.

I think I will avoid bricks with a high moisture content (stored
outside) and try poking the mortar after a few days. The wall plate will
be strapped down anyway. Temporary buttresses could be screwed to
various bits of concrete if it still looks dodgy.

Thanks all.

regards

--
Tim Lamb
  #9   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 1,026
Default Mortar setting time

On Oct 29, 10:54 pm, "Andrew Mawson"
wrote:
"Tim Lamb" wrote in message

...



In message
,
Osprey writes
On 29 Oct, 11:19, Tim Lamb wrote:
I am lifting the roof on an old pig farrowing barn to accommodate

a
furniture restorer.


The roof is heavy but can be moved in one piece. So far I have

raised
one side on Acrows and intend to lay two courses of brick to gain

the
height needed.


What is a reasonable time to wait before heavily loading fresh
brickwork? I am particularly nervous of any side thrust

encountered as I
start to jack up the other side.


regards
--
Tim Lamb


I would leave it 48Hrs ... 24 Hrs is no problem if a simple daed

load,
but as you point out there is side thrust, and bricks not

particularly
strong in that direction.


use a good 3:1 mix and suitable bricks, deep frog frettons as a
minimum, laid frog up, and fully filled ... or engineering if you

have
them.


OK. The brickwork will be Flettons for the first course and
semi-engineering for the top. Basically because that is what I have
lying about the farm:-) I can easily wait 3 days as I also have to

fit a
wider door and re-plumb the electrical conduit.


regards
--
Tim Lamb


Tim,

Very temperature dependant: I've just laid 8 cu m of RC40 concrete and
it took two days in the current cold snap to 'not' take a finger
impression. Earlier in the year I laid a batch of the very same stuff
on a blazing hot day and we couldn't finish tamping before it set
solid (perhaps 1.5 hours from delivery)

Cement re-hydradtion (ie setting) is a chemical reaction and thus very
dependent on the temp. When it starts to go off though it is
exothermic - ie gives off heat.


The heat given off can be an issue with bulk concrete (they
incorporated cooling pipes in the Hoover Dam), but it's extremely
likely to be detectable for mortar joints between bricks - there just
isn't enough of it!

(But the point about temperature dependance is /very/ relevant.)
  #10   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 9,045
Default Mortar setting time

Martin Bonner wrote:
On Oct 29, 10:54 pm, "Andrew Mawson"
wrote:
"Tim Lamb" wrote in message

...



In message
,
Osprey writes
On 29 Oct, 11:19, Tim Lamb wrote:
I am lifting the roof on an old pig farrowing barn to accommodate

a
furniture restorer.
The roof is heavy but can be moved in one piece. So far I have

raised
one side on Acrows and intend to lay two courses of brick to gain

the
height needed.
What is a reasonable time to wait before heavily loading fresh
brickwork? I am particularly nervous of any side thrust

encountered as I
start to jack up the other side.
regards
--
Tim Lamb
I would leave it 48Hrs ... 24 Hrs is no problem if a simple daed

load,
but as you point out there is side thrust, and bricks not

particularly
strong in that direction.
use a good 3:1 mix and suitable bricks, deep frog frettons as a
minimum, laid frog up, and fully filled ... or engineering if you

have
them.
OK. The brickwork will be Flettons for the first course and
semi-engineering for the top. Basically because that is what I have
lying about the farm:-) I can easily wait 3 days as I also have to

fit a
wider door and re-plumb the electrical conduit.
regards
--
Tim Lamb

Tim,

Very temperature dependant: I've just laid 8 cu m of RC40 concrete and
it took two days in the current cold snap to 'not' take a finger
impression. Earlier in the year I laid a batch of the very same stuff
on a blazing hot day and we couldn't finish tamping before it set
solid (perhaps 1.5 hours from delivery)

Cement re-hydradtion (ie setting) is a chemical reaction and thus very
dependent on the temp. When it starts to go off though it is
exothermic - ie gives off heat.


The heat given off can be an issue with bulk concrete (they
incorporated cooling pipes in the Hoover Dam), but it's extremely
likely to be detectable for mortar joints between bricks - there just
isn't enough of it!

(But the point about temperature dependance is /very/ relevant.)


Indeed. 2 hours to 2 days to just go 'crunchy' is the variation I have
noted. Over 0C-30C temp range.




  #11   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 299
Default Mortar setting time


"Tim Lamb" wrote in message
...
In message
,
Osprey writes
On 29 Oct, 11:19, Tim Lamb wrote:
I am lifting the roof on an old pig farrowing barn to accommodate a
furniture restorer.

The roof is heavy but can be moved in one piece. So far I have raised
one side on Acrows and intend to lay two courses of brick to gain the
height needed.

What is a reasonable time to wait before heavily loading fresh
brickwork? I am particularly nervous of any side thrust encountered as I
start to jack up the other side.

regards
--
Tim Lamb


I would leave it 48Hrs ... 24 Hrs is no problem if a simple daed load,
but as you point out there is side thrust, and bricks not particularly
strong in that direction.

use a good 3:1 mix and suitable bricks, deep frog frettons as a
minimum, laid frog up, and fully filled ... or engineering if you have
them.


OK. The brickwork will be Flettons for the first course and
semi-engineering for the top. Basically because that is what I have lying
about the farm:-) I can easily wait 3 days as I also have to fit a wider
door and re-plumb the electrical conduit.

regards
--
Tim Lamb



Tim .... my comment about 48 Hrs is a practical one, if you are using an OPC
& sand mix .... it would have enough partial strength after 48 Hrs.
If you have any doubt use rapid set cement ... or an accelerator additive.

If you can leave it longer then all the better.

Some of the other comments about exothernmic reactions, and time to
compressive strength are valid for bulk concrete, but not that relevant for
coursed brickwork.

Obviously the longer you leave it the more strength it has, but courses and
lintols (=dead load) are built up next working day on site.

  #12   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 9,560
Default Mortar setting time

On Oct 29, 11:19*am, Tim Lamb wrote:
I am lifting the roof on an old pig farrowing barn to accommodate a
furniture restorer.

The roof is heavy but can be moved in one piece. So far I have raised
one side on Acrows and intend to lay two courses of brick to gain the
height needed.

What is a reasonable time to wait before heavily loading fresh
brickwork? I am particularly nervous of any side thrust encountered as I
start to jack up the other side.

regards



would it be practical to add temporary wooden legs to the roof
structure so it sits on the original brickwork, then the fill-in
brickwork doesn't support the load. At a later date the legs could be
cut away and brickwork finished. Or perhaps timber legs, if they ever
deteriorate the roof will already be sitting on the newer fully cured
brickwork by then.


NT
  #13   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 6,938
Default Mortar setting time

In message
,
writes
On Oct 29, 11:19*am, Tim Lamb wrote:
I am lifting the roof on an old pig farrowing barn to accommodate a
furniture restorer.

The roof is heavy but can be moved in one piece. So far I have raised
one side on Acrows and intend to lay two courses of brick to gain the
height needed.

What is a reasonable time to wait before heavily loading fresh
brickwork? I am particularly nervous of any side thrust encountered as I
start to jack up the other side.

regards



would it be practical to add temporary wooden legs to the roof
structure so it sits on the original brickwork, then the fill-in
brickwork doesn't support the load. At a later date the legs could be
cut away and brickwork finished. Or perhaps timber legs, if they ever
deteriorate the roof will already be sitting on the newer fully cured
brickwork by then.


Certainly practical. Is it necessary?

Work is rarely scheduled on farms so there is always something waiting
to be done. Even in the current *overnight frost* weather it looks as
though half compressive strength will be reached after 5 days. My plan
is to get the brickwork done today (snow was melting off the roof
yesterday and dripping down my neck!) and get on with other things.

I see the danger point as when I start to jack up the other side to
match. The only thing preventing the whole roof sliding sideways will be
the new brickwork and wall straps. Elsewhere I have secured some strong
angle iron to the concrete floor and a wall and then used an acrow to
straighten the wall which was *leaning* from the damp course. I suppose
something similar could be done with a couple of timber
braces/buttresses to provide reassurance:-)

The mortar from a superficial pier I finished yesterday evening is
*biscuity* this morning.

regards

--
Tim Lamb
Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Time to make a bowl (for use in setting a price) tww Woodturning 15 January 30th 08 05:33 PM
If you will threaten Sherry's pavement from time to time clients, it will consistently travel the protocol. Jessica[_6_] Metalworking 0 December 10th 07 12:41 AM
mortar bed under bathtub dry time spam disintegrator Home Repair 3 July 29th 07 02:52 AM
Time setting to within 50ms - nistime-32bit.rar (1/1) JackShephard Electronic Schematics 0 June 9th 07 07:51 AM
Time setting to within 50ms - nistime-32bit.rar (0/1) JackShephard Electronic Schematics 0 June 9th 07 07:51 AM


All times are GMT +1. The time now is 09:23 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"