  #1   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 48
Default weak screed mix

i'm getting UFH laid over 70m2 as per this diagram http://bordersunderfloor.co.uk/stfd.htm

there will be 2"x1" spacers screwed to the joists at 450mm centres,
the UFH pipes are laid between these and the screed goes in to fill in
the gaps. then the final floor surface will be T&G bamboo floated on
self adhesive underlay.

the screed is only to transfer the heat ... but i've never used a weak
dry mix (8:1 dry sand / cement) like this before and i'm wondering if
it will set and be stable enough without crumbling for me to work on
it ie to finish the refurb, plaster boarding, painting, wiring etc

or perhaps it would be better to use a stronger mix? or put down a
temporary floor?

  #2   Report Post  
Posted to uk.d-i-y
R R is offline
external usenet poster
 
Posts: 72
Default weak screed mix


wrote in message
oups.com...
i'm getting UFH laid over 70m2 as per this diagram
http://bordersunderfloor.co.uk/stfd.htm

there will be 2"x1" spacers screwed to the joists at 450mm centres,
the UFH pipes are laid between these and the screed goes in to fill in
the gaps. then the final floor surface will be T&G bamboo floated on
self adhesive underlay.

the screed is only to transfer the heat ... but i've never used a weak
dry mix (8:1 dry sand / cement) like this before and i'm wondering if
it will set and be stable enough without crumbling for me to work on
it ie to finish the refurb, plaster boarding, painting, wiring etc

or perhaps it would be better to use a stronger mix? or put down a
temporary floor?


Personally I'd put down a temp floor or boarding to protect it


  #3   Report Post  
Posted to uk.d-i-y
external usenet poster
 
Posts: 9,045
Default weak screed mix

wrote:
i'm getting UFH laid over 70m2 as per this diagram
http://bordersunderfloor.co.uk/stfd.htm

there will be 2"x1" spacers screwed to the joists at 450mm centres,
the UFH pipes are laid between these and the screed goes in to fill in
the gaps. then the final floor surface will be T&G bamboo floated on
self adhesive underlay.

the screed is only to transfer the heat ... but i've never used a weak
dry mix (8:1 dry sand / cement) like this before and i'm wondering if
it will set and be stable enough without crumbling for me to work on
it ie to finish the refurb, plaster boarding, painting, wiring etc

or perhaps it would be better to use a stronger mix? or put down a
temporary floor?

That diagram assumes you have something like a basic later of ply or
chip over the lot.

I am pretty concerned with just laing bamboo over it all without some
seal..as they point out the screed is simply a conductive layer.

If the bamboo is thin enough, consider laying 12mm ply over the lot
after screeding.
Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Screed help red.fox UK diy 1 January 24th 07 05:53 PM
Screed help red.fox UK diy 0 January 24th 07 04:57 PM
OT - High-mix and low-mix concrete Jim Stewart Metalworking 5 May 18th 06 12:43 PM
"Dry" mix screed Omri UK diy 11 December 8th 04 10:24 AM
Talking of screed... Mungo \two sheds\ Toadfoot UK diy 4 September 12th 04 10:39 AM


All times are GMT +1. The time now is 12:26 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 DIYbanter.
The comments are property of their posters.
 

About Us

"It's about DIY & home improvement"