Dave wrote:
Here's another one for the assembled experts ...
I've got one joist that's been cut short and then attached to a trimmer
in order to get round a soil stack - but I want to remove the trimmer as
part of some building work. I plan to screw & glue the extension timber
to the side of the existing joist, are there any rules on how much
overlap, etc?
The joists are about 195x48, it's the joist nearest the wall, it'll be
about 40mm too short when the trimmer is removed.


.... that should be 400mm!
--
Dave S